Stepwise procedure, stage time-limits and measurement-dispute routes for progress payment measurement and payment (GB/T 50500-2024 Sections 7.1, 9.1 / 9.4, Chapter 11; comparison with GB 50500-2013)

Progress payment measurement and payment turns on measurement period = payment period, in four steps: 1 the contractor submits measurement outputs and the payment application per measurement period and payment verification date (GB/T 50500-2024 Articles 7.1.5, 9.4.9); 2 the employer checks in writing and the contractor confirms in writing or submits review comments; failure to provide check / re-check results in time deems the contractor's outputs (or comments) accepted (7.1.5, 7.1.6), sign-off per 7.1.7; 3 the payment certificate goes to the contractor for confirmation first (9.1.10); the employer issues the certificate after checking within a reasonable time, pays the undisputed part first where some items are disputed (9.4.11), and pays before the contractual latest payment date (9.1.11); 4 failing agreement after checking, review and re-check, Article 7.1.7 routes to Chapter 11 - negotiation, dispute review or mediation, then arbitration or litigation (11.1.1, 11.1.2). The 2024 edition mostly says agreed time; the concrete day-counts (7-day verification, 24-hour notice, 7-day objection and re-check, 14-day certificate) appear only in the repealed GB 50500-2013 Articles 8.2.3 / 8.2.4 / 8.2.5 / 8.3.5 and 10.3.9, for comparison only.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第7.1节、第9.1节、第9.4节、Ch. 11
  • GB 50500-2013 建设工程工程量清单计价规范 第8.2.3、8.2.4、8.2.5、8.3.5条、第10.3.9条(已废止,作对照)
  • GB/T 50319-2013 建设工程监理规范 第5.3.1条
  • GB/T 51262-2017 建设工程造价鉴定规范 第5.5.2条
  • DB11/T 382-2017 建设工程监理规程 第5.3.5条
  • DBJ41/T 208-2018 建设工程监理工作标准 第7.3.3条
  • T11 IESB 0001-2017 建筑电气工程施工资料管理规程 第4.1.8条
  • 保障农民工工资支付条例(国务院令第724号)第二十五条
  • https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2025/art_9e68efb0f9064752bcdf79df20767be5.html
  • http://jst.zj.gov.cn/col/col1229159268/art/2026/art_419fb013d3204c668e3d6932c17c925a.html
  • https://jst.zj.gov.cn/col/col1229129246/art/2020/art_e21cc32a2c161aa30be4f4f7806e7fc1.html
  • https://zjj.wenzhou.gov.cn/col/col1229206191/art/2025/art_ee18fffa392f4da9b0db2cb7c01d9acd.html

Scope of the question

The full procedure chain from measurement application to checked payment of progress payments, the time-limit bases at each stage, and the route for measurement disputes. The spine is GB/T 50500-2024 (Section 7.1 measurement of contract works; Sections 9.1 / 9.4 interim payment; Chapter 11 resolution of price disputes), supplemented by the supervision code, local supervision rules, the cost assessment code and the repealed GB 50500-2013 for comparison. Only the provisions are stated.

Core conclusions

1. Overall frame: measurement period equals payment period

Article 9.4.1: the parties shall, at the time or physical-progress node agreed in the contract, measure and pay completed-work progress payments each measurement period, the measurement period matching the payment period; where the progress measurement period is unclear, monthly instalments may be used. Article 7.1.2: the parties measure per Sections 7.2 to 7.7 at the agreed time, target or progress nodes; progress measurement may follow Section 9.4. Re-measurement, variation and additional-works measurement rest on the qualified works the contractor completed and that are measurable per the contract, the construction drawings and variation instructions issued by the employer, and the agreed national and industry measurement standards and supplementary rules. Progress amount (9.1.6): progress payments are the current cumulative price less the previous cumulative price; payment shall not claw back advance payments of statutory safety provisions. Payment level (9.1.7): the payment level of completed works value and advance clawback follow the contract; absent agreement, not less than 80% of the cumulative completed works value ...

2. Step 1 - measurement application (contractor submits outputs and payment application)

Article 7.1.5: the contractor submits the measurement outputs in writing for the employer to check; the employer notifies the check result in writing within the agreed time. Absent a timely check result, the contractor's outputs are deemed accepted and, save as otherwise agreed, may serve as the basis of price calculation - but not as evidence the works are acceptably delivered. Article 9.4.9: the contractor submits the progress payment application by each measurement period and payment verification date, stating the amounts considered due, including construction workers' wages and specialist subcontractors' progress, with calculations. The application lists: cumulative completed works value (contract BOQ price; BOQ-defect adjustments incl. re-measurement under unit-rate contracts and provisional-quantity adjustments under lump-sum contracts; provisional sums; provisional-sum adjustments; attendance and coordination adjustments; dayworks; cost-fluctuation adjustments; laws and policy adjustments; variations; additional works; claims); cumulative advance clawback incl. the current instalment; cumulative payable progress; previous cumulative payments; employer deductions; current payable progress. Progress is the difference of current cumulative completed price and cumulative paid price, listing construction workers' wages separately.

3. Step 2 - measurement confirmation (check - confirm / review - re-check; silence deems acceptance)

Article 7.1.6: the contractor confirms the employer's check result in writing within the agreed time or submits written review comments with detailed calculations; the employer then confirms in writing or notifies the re-check result - absent a timely re-check result, the contractor's review comments are deemed accepted and Article 7.1.5 applies. Where the contractor neither confirms nor reviews in time, the employer's checked outputs are deemed accepted and, save as otherwise agreed, may serve as the price basis. Article 7.1.7: the parties sign off the agreed outputs; failing agreement after check, review and re-check, Chapter 11 applies. On-site verification (9.4.10): where the employer needs on-site progress verification, it notifies the contractor in good time; the contractor facilitates and attends; both agreeing, they sign. Unattended after notice, the contractor is deemed to accept the result; the employer failing to notify in time so that the contractor cannot attend renders the result void. Supervision sign-off (GB/T 50319-2013 Article 5.3.1): the professional supervising engineer checks quantities and amounts and proposes the due amount with support - the chief supervising engineer reviews, signs and submits to the employer for approval - the chief supervising engineer issues the payment certificate to the contractor per the approval. Review covers the contract price of works executed to the end of the period, variation additions and deductions, claim additions and deductions, advance payments and clawback, retention deductions and other agreed adjustments; retention is deducted from the first period per the particular conditions, its base excluding advance payments, clawbacks and price adjustments. Local rules: DBJ41/T 208-2018 Article 7.3.3 takes the same four steps; DB11/T 382-2017 Article 5.3.5: absent contract terms, monthly measurement from the 26th of the previous month to the 25th of the current month ...; unforeseeable quantities (ground treatment, buried obstructions) are measured jointly with video records. T11 IESB 0001-2017 Article 4.1.8: monthly measurement, 26th to 25th, the contractor reporting by the 26th per signed-off work items.

4. Step 3 - application, review and payment

Article 9.1.10: before issuing the certificate, the employer gives the draft certificate to the contractor, who confirms in writing within the agreed time or submits a written review report - stating omitted items and amounts, cumulative-value differences and computation errors - and checks with the employer within the agreed time. Article 9.4.11: the employer checks the application within a reasonable time, issues the certificate and pays on time; where some items are disputed, the certificate and payment cover the undisputed items. Article 9.1.11: after confirmation or correction, the employer pays the certified current amount by the contractual latest payment date. Article 9.4.13: quantities and prices of each verified period are summed on summary sheets signed by both parties. Remedy for late payment (9.4.12): where the employer pays late or not at all, the contractor may claim per Article 8.11.9.

5. Time limits: 2024 agreed times vs old fixed day-counts

GB/T 50500-2024 says agreed time / reasonable time throughout, without fixed days, discipline resting on deemed acceptance (7.1.5, 7.1.6) and pay-the-undisputed-first (9.4.11); unclear periods default to monthly instalments (9.4.1). The repealed GB 50500-2013 fixed days, for comparison only: 8.2.3 - the employer verifies within 7 days of the quantity report, failing which the reported quantities stand as actually completed; 8.2.4 - 24 hours' notice before on-site verification; unattended after notice deems acceptance, unnotified attendance failure voids the result; 8.2.5 - the contractor objects within 7 days, the employer re-checks within 7 days, unresolved disputes going to the contractual route; 8.3.5 - 7-day review to fix actual quantities; 10.3.9 - certificate within 14 days of the application, undisputed items certified where some are disputed. (Note: the model construction contract GF-2017-0201 general conditions Clause 12 gives per-stage day-counts; its text is not reproduced here - verify against the original before citing; do not cite day-counts from memory.)

6. Dispute route for measurement results

Article 7.1.7: failing agreement after check, review and re-check, Chapter 11 applies. Article 11.1.1: disputes over measurement, price adjustment, interim payment, settlement and related quality, variations, additional works, claims and time matters are settled by amicable negotiation and recorded in supplementary (settlement) agreements binding both parties; failing agreement, the contract governs, and absent or unclear terms this chapter. Price and time disputes go first to negotiation; failing that, preferably dispute review or mediation; failing that, arbitration or litigation. Article 11.1.2: the routes are 1 a dispute review board (or body); 2 a mediator (or body); 3 arbitration or litigation. Review procedure points: the board provides written opinions to both parties within the agreed time with reasons and basis (11.2.4); either party's objection goes to the board in writing, copied to the other, the board responding in writing within the agreed time (11.2.5); unobjected opinions are signed as settlement agreements binding both parties (11.2.6); objected opinions bind neither party, but save as otherwise agreed or terminated, the parties continue performing until resolution (11.2.7); failure to comply with a confirmed opinion or mediation settlement allows the other party to go to arbitration or litigation (11.4.5). Article 11.4.1: failing resolution, the parties may arbitrate per the contract or litigate ... Assessment of contested signed-off results (GB/T 51262-2017 Article 5.5.2): objection without evidence - assess on the original result; objection with evidence - re-check, on site if necessary, and assess per the re-checked result.

Applicability limits

1 GB/T 50500-2024 is a recommendatory national standard whose provisions become contractual when invoked; agreed times must be stated in the contract - absent agreement, the effect of deemed-acceptance is contested (the judicial interpretation requires express contract terms, duly served complete documents and silence within the period); do not rely on the implied terms of a recommendatory standard alone. 2 GB 50500-2013 is repealed; its 7-day, 24-hour and 14-day counts serve only as comparison, not as a current basis. 3 Deemed-accepted measurement outputs serve only as the price basis, never as evidence of acceptable delivery (7.1.5). 4 Void on-site verification is limited to the employer failing to notify in time so the contractor cannot attend; unattended after notice deems acceptance (9.4.10). 5 The supervision sign-off rests on GB/T 50319-2013 and local rules (DB11/T 382-2017 Beijing only; DBJ41/T 208-2018 Henan only; T11 IESB 0001-2017 for building electrical records); the 26th-to-25th monthly period is a recommendation absent contract terms. 6 Subcontract measurement and progress settlement terms are agreed in the written subcontract (Regulation on Wage Payment to Migrant Workers, Article 25) - the pricing standards alone do not govern. 7 This card states procedures only, no operational advice; other industries (railway, highway) have their own measurement and payment rules.