GB/T 50500-2024 Chapter 11 contract-price dispute resolution procedure: the amicable negotiation → dispute review/mediation → arbitration/litigation progression (compared with the repealed GB 50500-2013 Section 13.1 the Engineer's 14-day interim-determination mechanism; including the deletion of the construction cost expert assessment chapter, now carried by GB/T 51262-2017)

GB/T 50500-2024 Chapter 11 provides that contract-price disputes escalate "amicable negotiation → dispute review or mediation → arbitration or litigation": supplementary (settlement) agreements signed upon negotiation bind both parties (11.1.1); failing agreement, dispute review or mediation is preferred, with the review board (or body)/mediator (or body) jointly selected by the parties and free of conflicts of interest with either (11.1.2–11.1.4); failing that, arbitration or litigation per the contract — their final decisions are legally binding on employer and contractor and must be jointly observed (11.1.5, 11.4.6); where a party fails to implement a jointly confirmed review opinion or mediation statement, the other may submit the dispute to arbitration or litigation (11.4.5). The 2024 edition deleted wholesale GB 50500-2013 Section 13.1's pre-stage "the Engineer/cost engineer interim determination" (original rule: interim result notified within 14 days of submission; no confirmation within 14 days deemed acceptance) — whether an interim stage exists now depends entirely on the contract; the foreword's revision item 9 also "deletes the construction cost expert assessment chapter" (the former Chapter 14), that business being carried by the standalone GB/T 51262-2017 "Code for Construction Cost Expert Assessment (Judicial Appraisal)" — the pricing standard no longer duplicates it.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works Ch. 11及前言
  • GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第13、14章(已废止)
  • GB/T 51262-2017 · Code for Construction Cost Appraisal

Topic Positioning

This card covers the dispute-handling order prescribed by Chapter 11 "Resolution of Contract Price Disputes" of GB/T 50500-2024 "China national pricing standard for BOQ (GB/T 50500)" (amicable negotiation → dispute review or mediation → arbitration or litigation), the rules on determining the pricing basis and the effect of decisions at each stage, the important changes against the repealed GB 50500-2013 Section 13.1 "the Engineer/cost engineer interim determination" mechanism, and the background of deleting Chapter 14 "construction cost expert assessment (judicial appraisal)" in favour of GB/T 51262-2017 "Code for Construction Cost Expert Assessment (Judicial Appraisal)".

Core Conclusions

  1. Handling order (2024 Chapter 11, escalating):
  • Amicable negotiation (11.1.1): where employer and contractor, during performance, dispute the measurement of the works, adjustment of the contract price, interim payment, construction payment settlement (interim + final), or related quality, variation, additional works, claims, extension of time or delay, they "shall resolve the dispute through amicable negotiation"; supplementary (settlement) agreements signed upon agreement "bind both parties"; failing agreement, "handle per the contract, and where the contract is silent or unclear, per the provisions of this chapter". For price and/or duration-extension disputes, negotiate first; failing that, "dispute review or mediation is preferred, and failing consensus thereon, arbitration or litigation may be used".
  • Dispute review or mediation (11.1.2): handled per the contract and in the following ways: (1) entrust a dispute review board (or body) to review; (2) entrust a capable mediator (or body) to mediate; (3) arbitration or litigation.
  • Arbitration or litigation (11.1.5, 11.4.1): where 11.1.3 and 11.1.4 fail to resolve the dispute, "the employer or contractor may, per the contract, submit the dispute to the arbitration commission agreed by both parties for an award, or to the people's court for judgment" — arbitration or litigation is "the final method of resolving construction disputes".
  1. Composition and effect of review/mediation (11.1.3, 11.1.4): the dispute review board (or body) or mediator (or body) shall be jointly selected by the parties, and the reviewers and mediators "shall have no conflict of interest with either party"; their dispute decisions "shall carry such binding force as the parties' entrustment for the reviewed or mediated matters provides", and the parties may confirm the outcome per 11.1.1 or sign a settlement (supplementary) agreement — the effect flows from the entrustment, not from statutory compulsion.
  2. Supplementary rules for arbitration/litigation: after filing and before the commission's award or the court's judgment, the parties may still mediate per the commission's or court's mediation procedures, and the mediation statement reached may seek judicial confirmation (11.4.2); "the final decision of arbitration or litigation is legally binding on both employer and contractor and shall be jointly observed" (11.4.6).
  3. Consequences of non-implementation of review/mediation outcomes (11.4.5): "within the periods prescribed by Sections 11.1–11.3 of this standard, where either party fails to comply with a jointly confirmed dispute review opinion or mediation statement, the other party may submit the disputed matter to arbitration or litigation per the contract's dispute resolution clause"; "the arbitration award or the people's court judgment is the final decision on the dispute, and both parties shall jointly observe and implement it".
  4. Performance during disputes: "except as laws and regulations provide or the contract otherwise agrees, employer and contractor shall continue performing their contractual obligations during dispute resolution until the dispute is resolved"; and where price-adjustment disputes go to dispute resolution, this "shall not affect the employer's payment of progress payments and the adjusted contract prices already agreed per the provisions".
  5. Key changes vs. the 2013 edition (two parts):
  • Interim determination deleted: GB/T 50500-2024 Chapter 11 deleted wholesale the GB 50500-2013 Section 13.1 pre-stage "the Engineer/cost engineer interim determination" mechanism (2013 13.1.1–13.1.3: disputes first submitted to the Engineer or cost engineer within their contracted duties with a copy to the other party; the interim result notified to both parties within 14 days of receiving the submission; a written confirmation by both parties made it the final decision; no confirmation and no objection within 14 days of the notice deemed acceptance; a written objection turned the interim result into a dispute, but the parties implemented it pending resolution so long as it did not materially affect performance, until changed per the agreed dispute resolution). The national standard no longer uniformly provides an interim stage — whether to set one depends entirely on the contract.
  • Construction cost expert assessment chapter deleted: the 2024 foreword's "main technical revisions" item 9 states "delete the construction cost expert assessment chapter" — the former GB 50500-2013 Chapter 14 is removed entirely and the pricing standard no longer duplicates it; that business is carried by the standalone GB/T 51262-2017 "Code for Construction Cost Expert Assessment (Judicial Appraisal)", which continues to govern construction cost expert assessment in litigation/arbitration.

Applicable Boundaries

  • Chapter 11 is recommendatory and follows "contractual agreement takes precedence" throughout: 11.1.1 makes clear that failing negotiation one "shall handle per the contract; where the contract is silent or unclear, per this chapter". Contracts prescribing other dispute procedures (e.g., the Engineer's interim determination first, then review) are executed as written.
  • This card's Chapter 11 content applies only to GB/T 50500-2024; the GB 50500-2013 Section 13.1 mechanism and Chapter 14 construction cost expert assessment are repealed (the 2013 edition is replaced wholesale by the 2024 edition) — for comparative understanding only, not a current pricing basis.
  • Review/mediation decisions are not final: a non-implementing party faces referral to arbitration or litigation; only arbitration or litigation decisions carry legally final binding force.
  • Construction cost expert assessment does not vanish with the chapter's deletion: assessments in litigation/arbitration follow GB/T 51262-2017 "Code for Construction Cost Expert Assessment (Judicial Appraisal)".

Further Reading

  • GB/T 50500-2024 "China national pricing standard for BOQ (GB/T 50500)", Chapter 11 "Resolution of Contract Price Disputes": 11.1.1–11.1.5 (the escalating procedures of negotiation, review, mediation, arbitration/litigation), Section 11.4 (11.4.1 filing for arbitration/litigation; 11.4.2 pre-award mediation and judicial confirmation; 11.4.5 non-implementation of review/mediation outcomes referred to arbitration/litigation; 11.4.6 final decisions legally binding); the 2024 foreword's "main technical revisions" items 8 and 9 (revised dispute-resolution methods; deleted construction cost expert assessment chapter).
  • Read against the repealed GB 50500-2013 "Code for Bill of Quantities Pricing of Construction Works", Section 13.1 (interim-determination mechanism, 13.1.1–13.1.3) and Chapter 14 (construction cost expert assessment).
  • Practical successor standard for construction cost expert assessment: GB/T 51262-2017 "Code for Construction Cost Expert Assessment (Judicial Appraisal)" (e.g., Clause 5.9 rules on assessment of site instructions).