Essential contents of an arbitration agreement, grounds of invalidity, separability and the procedure for challenging validity (Arbitration Law of the PRC, 2025 revision, Articles 27-31 and 89-96), including implied arbitration agreements and limitation rules for arbitration
Article 27 of the Arbitration Law (2025 revision, in force 1 March 2026) requires an arbitration agreement to contain an expression of intent to request arbitration, the matters for arbitration and the designated arbitration institution (where a party asserts an arbitration agreement when applying for arbitration and the other party does not deny it before the first hearing, and the arbitral tribunal notes it after drawing attention, an arbitration agreement is deemed to exist). Article 28 lists three grounds of invalidity: the agreed matters exceed the statutory scope of arbitration; the agreement was concluded by a person with no or limited civil capacity; one party coerced the other into concluding it. Article 29: where the matters or the institution are not agreed or the agreement is unclear, a supplementary agreement may be concluded; failing that, the arbitration agreement is invalid. Article 30: the arbitration agreement exists independently; the conclusion, amendment, termination, rescission or invalidity of the contract does not affect its validity, and the arbitral tribunal has power to confirm the validity of the contract. Article 31: a challenge to validity may be put to the arbitration institution or the arbitral tribunal for decision or to the people's court for a ruling; where both are seised, the people's court rules, and the challenge must be raised before the first hearing of the arbitral tribunal.
Applicable Codes
- 《中华人民共和国仲裁法》(2025修订)第二十七条、第二十八条、第二十九条、第三十条、第三十一条
- 《中华人民共和国仲裁法》(2025修订)第八十九条、第九十条、第九十一条、第九十二条、第九十三条、第九十四条、第九十五条、第九十六条
Subject Positioning
The validity basis of dispute resolution clauses in construction contracts: the provisions of the Arbitration Law of the PRC (2025 revision, in force from 1 March 2026) on the essential contents of an arbitration agreement, grounds of invalidity, separability and the procedure for challenges to validity, used to judge clause effectiveness at the contract review and case filing stages.
Core Conclusions
I. Form and essential contents (Article 27)
'An arbitration agreement includes an arbitration clause concluded in a contract and any other agreement in writing, reached before or after the dispute arises, to submit the dispute to arbitration.' An arbitration agreement shall contain the following: '(1) an expression of intent to request arbitration; (2) the matters to be arbitrated; (3) the arbitration institution designated.' Special case of formation by implication: 'Where a party asserts, when applying for arbitration, that an arbitration agreement exists and the other party does not deny it before the first hearing, an arbitration agreement is deemed to exist between the parties, after the arbitral tribunal draws attention to it and records it.'
II. Grounds of invalidity (Article 28)
'An arbitration agreement is invalid in any of the following circumstances: (1) the agreed matters for arbitration fall outside the scope of arbitration prescribed by law; (2) the arbitration agreement was concluded by a person with no civil capacity or limited civil capacity; (3) one party compelled the other to conclude the arbitration agreement by coercion.'
III. Cure of unclear agreement and its consequence (Article 29)
'Where the arbitration agreement contains no agreement, or an unclear agreement, on the matters for arbitration or the arbitration institution, the parties may conclude a supplementary agreement; where no supplementary agreement is reached, the arbitration agreement is invalid.' Accordingly, wording such as 'submit the dispute to the local arbitration institution' or 'apply to the arbitration institution having jurisdiction for arbitration', which fails to name a specific institution, must be fixed by a supplementary agreement or risks invalidity.
IV. Separability (Article 30)
'The arbitration agreement exists independently. Whether the contract is concluded, and its amendment, non-entry into force, termination, rescission or invalidity, do not affect the validity of the arbitration agreement reached. The arbitral tribunal has the power to confirm the validity of the contract.' That is, invalidity, termination or rescission of the main contract does not affect the validity of the dispute resolution clause; the arbitral tribunal retains jurisdiction and may confirm the validity of the contract.
V. Procedure and forum for challenges to validity (Article 31)
'A party that objects to the validity of an arbitration agreement may request the arbitration institution or the arbitral tribunal to decide, or request the people's court to rule. Where one party requests the arbitration institution or the arbitral tribunal to decide and the other party requests the people's court to rule, the people's court shall rule.' 'A party that objects to the validity of an arbitration agreement shall raise the objection before the first hearing of the arbitral tribunal.' - The objection deadline is a hard threshold; raising it late forfeits the right to object.
VI. Supporting definitions (Chapter VIII, supplementary provisions)
- Scope of arbitration institutions (Article 89): 'Arbitration institutions as referred to in this Law include arbitration commissions, arbitration courts and other institutions established according to law.'
- Limitation period for arbitration (Article 90): 'Where a law provides for a limitation period for arbitration, that provision applies; where there is none, the provisions on limitation of actions apply.'
- Rules and fees (Articles 91 and 92): an arbitration institution may formulate its arbitration rules by reference to the model arbitration rules prepared by the China Arbitration Association; the parties shall pay arbitration fees as prescribed, and the fee schedule is formulated by the arbitration institution under the relevant state provisions.
- Matters outside this Law (Article 93): arbitration of labour disputes, of rural land contract disputes and of sports disputes is governed by specific laws such as the Law on Mediation and Arbitration of Labour Disputes, the Law on Mediation and Arbitration of Rural Land Contract Disputes and the Sports Law.
- International investment arbitration (Article 94): it may be conducted under the arbitration rules agreed by the parties in accordance with the provisions of relevant international investment treaties or agreements on submitting investment disputes to arbitration.
- Entry into force (Article 96): 'This Law comes into force on 1 March 2026.'
Scope of Application
- Applies to civil and commercial arbitration between parties of equal standing (including construction contract disputes); labour disputes, rural land contract disputes and sports arbitration fall outside this Law and under their specific laws (Article 93).
- The arbitration agreement must be in writing: an arbitration clause in the contract, or another written agreement to arbitrate reached before or after the dispute arose; an oral agreement does not constitute an arbitration agreement.
- Where the arbitration agreement is invalid, or unclear and not cured, the dispute falls back to court jurisdiction; but invalidity of the main contract does not affect the validity of the arbitration agreement (Article 30).
- Objections to validity must be raised before the first hearing of the arbitral tribunal, and where one party requests a decision by the arbitration institution or tribunal and the other requests a ruling by the court, the ruling of the court prevails.
- Procedural rules on setting aside and enforcing arbitral awards are outside the scope of this card group; consult the relevant chapters of this Law and the relevant provisions of the Civil Procedure Law.
Further Reading
- Arbitration Law of the PRC (2025 revision), Chapter III Arbitration Agreements, Articles 27 to 31 (form and contents, grounds of invalidity, cure, separability, challenges to validity)
- Arbitration Law of the PRC (2025 revision), Chapter VIII Supplementary Provisions, Articles 89 to 96 (definition of arbitration institutions, limitation for arbitration, arbitration rules and fees, excluded matters, international investment arbitration, effective date 1 March 2026)
- Contract review points: an arbitration clause must state, in one place, the expression of intent to request arbitration, the matters for arbitration (refinable into disputes over project price, time for completion, quality and claims) and the name of the specific arbitration institution designated; avoid vague formulations
- Interface with dispute resolution procedure: the negotiation -> dispute adjudication / mediation -> arbitration or litigation sequence for contract price disputes, see GB/T 50500-2024 Chapter 11 (dedicated card)