Whether the arbitration clause in the main contract binds a subcontractor: privity of the arbitration agreement, sorting the statutory extension scenarios, and the timing of procedural objections (Arbitration Law (2025 revision) Articles 4, 5 and 27-31; Civil Code Articles 465 and 555; Fa Shi [2015] No. 5 Articles 215 and 216; Fa Shi [2023] No. 13 Article 36)
As a rule, not bound: the sole source of arbitral jurisdiction is the arbitration agreement (Arbitration Law (2025 revision) Article 4: 'where there is no arbitration agreement and one party applies for arbitration, the arbitration institution shall not accept the case'), and the main contract 'is legally binding only on the parties' (Civil Code Article 465(2)); a subcontractor that is not a signatory to that arbitration clause may sue directly in court over subcontract disputes. The subcontractor is bound only where the subcontract expressly incorporates the main contract's dispute resolution clause, the subcontractor separately signs or accepts the arbitration clause in writing, the subcontract itself provides for arbitration, the subcontractor takes over the main contract position in its entirety, or the subcontractor fails to deny arbitration before the first hearing after the tribunal's reminder is recorded (an arbitration agreement being deemed to exist).
Applicable Codes
- 《中华人民共和国仲裁法》(2025修订)第四条、第五条、第六条、第十条、第二十七条、第二十八条、第二十九条、第三十条、第三十一条
- 《中华人民共和国民法典》(主席令第45号)第四百六十五条、第五百三十五条、第五百五十五条、第七百九十一条
- 《中华人民共和国民事诉讼法》(2023修正)第二十四条、第一百二十七条第(二)项
- 法释〔2015〕5号《最高人民法院关于适用〈中华人民共和国民事诉讼法〉的解释》(2022修正)第三十三条、第二百一十五条、第二百一十六条
- 法释〔2023〕13号《最高人民法院关于适用〈中华人民共和国民法典〉合同编通则若干问题的解释》(2023年12月5日施行)第三十三条至第三十六条 https://www.court.gov.cn/fabu/xiangqing/419382.html
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第四十三条、第四十四条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第六条、第七条、第二十三条(2026年6月30日施行)
- 《中华人民共和国建筑法》(2019修正)第二十九条
- 法〔2019〕254号《全国法院民商事审判工作会议纪要》第98条
Topic Positioning
This card answers a frequent procedural dispute point along the main contractor-subcontractor chain: the construction contract between the employer and the main contractor (the main contract) contains an arbitration clause, while the subcontract between the main contractor and the subcontractor has none (and no incorporation clause) -- is the subcontractor thereby deprived of the right to litigate and compelled to arbitrate?
Core Conclusions
1. The test runs in three steps
Step one: does an arbitration agreement exist that points to 'the subcontractor'. Article 27 of the Arbitration Law (2025 revision): 'An arbitration agreement includes arbitration clauses concluded in a contract and other agreements in writing, reached before or after the dispute arises, to request arbitration. An arbitration agreement shall contain: (1) an expression of intent to arbitrate; (2) the matters to be arbitrated; (3) the chosen arbitration institution.' The parties to the main-contract arbitration clause as written are the employer and the main contractor only, which forms no consensus with the subcontractor. Article 4 of the Arbitration Law: 'Where the parties choose arbitration to resolve a dispute, they shall follow the principle of voluntariness and reach an arbitration agreement. Where there is no arbitration agreement and one party applies for arbitration, the arbitration institution shall not accept the case.' Article 465(2) of the Civil Code: 'A contract formed in accordance with law is legally binding only on the parties, except as otherwise provided by law.' That is, the arbitration clause does not automatically extend by virtue of the main contractor-subcontractor relationship in the works.
Step two: if not, does the case fall within a statutory extension scenario (see the table below). Subcontracting is 'independent contracting' and does not fall within the extension paths of a comprehensive transfer of contractual rights and obligations, statutory assignment of claims, or subrogation rights.
Step three: does the invalidity of the subcontract (or of the main contract) itself affect the analysis. It does not, but the direction is one-way -- Article 30 of the Arbitration Law: 'An arbitration agreement exists independently. Whether the contract is formed and its amendment, non-effectiveness, termination, revocation or invalidity do not affect the validity of the arbitration agreement already reached. The arbitral tribunal has the power to confirm the validity of the contract.' That article answers 'the existing arbitration clause remains valid'; it cannot be read backwards into 'an absent arbitration clause may be presumed'; re-letting of the whole works and unlawful subcontracting generate no arbitration consensus.
2. Affirmative scenarios (subcontractor bound or procedurally constrained)
| # | Scenario | Conclusion | Basis |
|---|---|---|---|
| A1 | The subcontract expressly provides that 'the main contract (including its dispute resolution clause) forms part of the subcontract' or that 'disputes are handled under the main contract's dispute resolution clause', and it can be proved that the subcontractor knew of that arbitration clause | Bound by that arbitration clause (an incorporated arbitration consensus); arbitration only | Arbitration Law Article 27(1), Article 4 |
| A2 | The subcontractor signs the main contract containing the arbitration clause or a tripartite agreement, or issues a letter of undertaking or meeting minutes accepting that arbitration clause in writing | Bound (an independent written arbitration consensus, not an extension) | Arbitration Law Article 27(1) |
| A3 | The subcontract itself provides for arbitration (including by reference: 'submit to the arbitration institution agreed in the main contract') and a unique institution is determinable | Bound by the subcontract's own arbitration clause; where the institution cannot be determined, invalid for failure of supplementation under Article 29 | Arbitration Law Articles 27(1) and (2), Article 29 |
| A4 | The subcontractor is the comprehensive transferee of the rights and obligations under the main contract (acquiring the contract position with the employer's consent, rather than concluding a separate subcontract) | The arbitration clause passes with the contract position; bound | Civil Code Article 555; by reference Fa Shi [2015] No. 5 Article 33 (where a contract is transferred, its jurisdiction agreement is effective against the transferee, except where the transferee did not know of it at the transfer, or the transfer agreement provides otherwise and the original counterparty consents) |
| A5 | The subcontractor participates in the main contractor-employer arbitration in its own name and raises no objection to the existence or validity of the arbitration agreement before the first hearing, after the tribunal has reminded it and recorded this | An arbitration agreement is deemed to exist between the parties; the objection is lost as out of time | Arbitration Law Article 27(3), Article 31(2) |
| A6 | After the dispute arises, the main contractor and the subcontractor conclude a separate written arbitration agreement | From then on that dispute goes to arbitration | Arbitration Law Article 27(1) |
| A7 | The subcontractor (actual constructor) sues the employer by subrogation right, while the debtor and the counterparty have already applied for arbitration over the same creditor-debtor relationship before the first hearing | The court 'may' suspend the subrogation action -- a procedural suspension, not the subcontractor coming under arbitral jurisdiction | Fa Shi [2023] No. 13 Article 36 |
3. Negative scenarios (subcontractor not bound, may litigate)
| # | Scenario | Conclusion | Basis |
|---|---|---|---|
| B1 | The subcontract has no arbitration clause and no incorporation clause | Not bound; may sue in court; the court may not refuse to accept the case on the ground of the main-contract arbitration clause | Arbitration Law Articles 4 and 5; Civil Code Article 465(2); Civil Procedure Law Article 127(2) |
| B2 | In litigation, an objection to the court's competence is raised against the subcontractor on the ground that 'the main contract has an arbitration clause' | The objection fails | Fa Shi [2015] No. 5 Article 215: acceptance is affected only where 'the arbitration clause or arbitration agreement is not formed, is invalid, has lapsed, or its content is unclear and incapable of execution'; here 'no agreement directed at the subcontractor exists' |
| B3 | The subcontract has no arbitration clause; the subcontractor sues the employer by subrogation and the employer objects to the court's competence citing the main-contract arbitration agreement | The court does not support the objection | Fa Shi [2023] No. 13 Article 36, first part: 'where, after the creditor brings a subrogation action, the debtor or the counterparty objects to the court's competence on the ground that an arbitration agreement governs the creditor-debtor relationship between them, the people's court does not support the objection.' |
| B4 | The subcontractor argues that 'since arbitration applies between the main contractor and the employer, subcontract disputes are arbitrated together' | No basis; fails | Arbitration Law Article 6 (arbitration institutions are chosen by the parties' agreement, with no hierarchical or territorial jurisdiction) and Article 10 (one award is final) both presuppose an arbitration agreement |
| B5 | Analogy with insurer subrogation: statutory assignment of claims binding the transferee | A special rule of statutory assignment of claims, inapplicable to subcontracting | Fa [2019] No. 254 Article 98 (an arbitration agreement reached between the insured and a third party before the insurance event binds the insurer exercising the subrogation right; foreign-related civil and commercial cases fall outside that article's scope) -- the subcontractor is an independent contracting party, not a transferee of claims |
4. Procedure and timing
- Arbitration Law Article 31: 'Where a party objects to the validity of an arbitration agreement, it may request the arbitration institution or the arbitral tribunal to decide, or request the people's court to rule. Where one party requests the arbitration institution or the arbitral tribunal to decide and the other party requests the people's court to rule, the people's court rules. An objection to the validity of an arbitration agreement shall be raised before the arbitral tribunal's first hearing.'
- Court-side review: Fa Shi [2015] No. 5 Article 216 -- where the defendant objects before the people's court's first hearing to the acceptance of a civil case on the ground of a written arbitration agreement, the court shall review; if upon review '(1) the arbitration institution or the people's court has already confirmed the arbitration agreement as valid; (2) the parties raised no objection to the validity of the arbitration agreement before the arbitral tribunal's first hearing; (3) the arbitration agreement satisfies Article 16 of the Arbitration Law and none of the circumstances of Article 17 applies', the court rules to dismiss the action.
- Jurisdiction where the subcontractor sues on its own: subcontract disputes are contract disputes, governed under Civil Procedure Law Article 24 by the people's court of the defendant's domicile or the place of performance of the contract (unrelated to the main contract's arbitration clause).
- Practical risk points: once the subcontractor 'participates in the main contractor-employer arbitration and does not deny it before the first hearing', an arbitration agreement is deemed to exist and the opportunity to litigate is lost; conversely, where the employer or the main contractor pleads the main-contract arbitration clause when the subcontractor sues, that plea usually fails.
Boundaries of Application
- This card addresses the basic case of 'no court/arbitration dispute resolution clause in the subcontract'; where the subcontract itself has an arbitration or jurisdiction clause, first determine the dispute resolution method under that clause, then discuss whether the main-contract arbitration clause can be incorporated.
- Where the subcontract expressly incorporates the main contract's dispute resolution clause, the incorporation further requires review of its explicitness and of the subcontractor's awareness; a blanket 'matters not covered shall follow the main contract' generally does not incorporate the dispute resolution clause.
- Where the works are re-let or unlawfully subcontracted, the route for the unit or individual accepting the re-letting or the unlawful subcontract to claim payment from the employer follows separate rules: Fa Shi [2026] No. 12 Article 6 (the party accepting the re-letting or unlawful subcontracting may claim discounted compensation from the contractor by reference to the re-letting or subcontract; a claim against the employer, with whom it has no contract, for discounted compensation or damages is not supported) and Article 7 (subrogation against the employer under Civil Code Article 535 is available); Fa Shi [2020] No. 25 Articles 43 and 44 are the former rules. Fa Shi [2026] No. 12 Article 23: 'This Interpretation takes effect on 30 June 2026. It applies to first-instance construction contract dispute cases newly accepted by the people's courts after its entry into effect. Where judicial interpretations previously issued by the Supreme People's Court conflict with this Interpretation after its entry into effect, this Interpretation prevails.' Accordingly, first-instance cases newly accepted after 30 June 2026 apply Interpretation (II); cases accepted earlier follow the former interpretations.
- The Arbitration Law articles are quoted from the 2025 revised text; its effective date and new-old transition follow the promulgated text of that law; for arbitration agreements concluded before the 2025 revision, check against the Arbitration Law and its interpretations then in force.
Further Reading
- Arbitration Law of the PRC (2025 revision), Chapter I General Provisions (Articles 4-12: the principle of voluntariness, agreement-based exclusion of litigation, institutional choice by agreement, finality of one award, good faith, online arbitration) and Chapter III Arbitration Agreements (Articles 27-31: form and three required contents, three invalidity scenarios, supplementation and invalidity where the agreement is unclear, independence, objections to validity).
- Civil Code of the PRC, Articles 465 (privity of contract), 535 (subrogation right), 555 (transfer of contractual rights and obligations together) and 791 (prohibition of unlawful subcontracting and re-letting).
- Civil Procedure Law of the PRC (2023 amendment), Article 24 and Article 127(2).
- Fa Shi [2015] No. 5, Interpretation of the Supreme People's Court on the Application of the Civil Procedure Law (2022 amendment), Articles 33, 215 and 216.
- Fa Shi [2023] No. 13, Interpretation of the Supreme People's Court on Several Issues concerning the General Provisions of the Contract Part of the Civil Code (effective 5 December 2023), Articles 33-36 (preservation of contract, subrogation actions and conflicts with arbitration agreements), original text at https://www.court.gov.cn/fabu/xiangqing/419382.html .
- Fa Shi [2020] No. 25, Interpretation on Construction Contract Cases (I), Articles 43 and 44; Fa Shi [2026] No. 12, Interpretation on Construction Contract Cases (II), Articles 6, 7 and 23 (effective 30 June 2026).
- Building Law of the PRC (2019 amendment), Article 29 (subcontracting, self-performance of the main structure, prohibition of further subcontracting).
- Fa [2019] No. 254, Minutes of the National Courts' Civil and Commercial Trial Work Conference, Article 98 (effect of arbitration agreements on insurers; the contrasting rule of statutory assignment of claims).
Keywords
- 仲裁协议相对性
- 分包人受总包仲裁条款约束
- 仲裁条款并入
- 默示仲裁协议
- 首次开庭前异议
- 合同权利义务概括移转
- 代位权诉讼与仲裁协议
- 仲裁法2025修订第二十七条