Exclusive court jurisdiction over construction contract disputes (treated as real property disputes) and the rule that an arbitration agreement bars court acceptance; review of arbitration agreement validity and the timing of challenges

Construction contract disputes are governed as real property disputes and fall under the exclusive jurisdiction of the court at the place of the real property (for registered property, the place recorded in the register; for unregistered property, the place of actual situation) (Civil Procedure Law, Article 34; Fa Shi [2015] No. 5, Article 28). Where the contract contains an arbitration clause or the parties later reach a written arbitration agreement, the court shall direct the party to apply for arbitration and, if it insists on suing, rule non-acceptance; the exceptions are that the arbitration clause is not formed, invalid or lapsed, or its content is unclear and incapable of execution (Fa Shi [2015] No. 5, Article 215; Arbitration Law, Article 5). The separability of the arbitration agreement means it does not lapse with the invalidity of the construction contract (Arbitration Law, Article 30), and a challenge to its validity must be raised before the first hearing of the arbitral tribunal (Article 31).

Applicable Codes

  • 中华人民共和国民事诉讼法(2023修正)第三十四条、第一百二十二条
  • 法释〔2015〕5号 最高人民法院关于适用《中华人民共和国民事诉讼法》的解释(2022修正)第二十八条、第二百一十五条
  • 中华人民共和国仲裁法(2025修订)第五条、第二十七条、第二十八条、第二十九条、第三十条、第三十一条

Subject Positioning

Which court to sue in for construction contract disputes (including suits by the actual constructor, subcontractors and migrant workers for payment), and whether the court accepts the case when the contract contains an arbitration clause: this card sorts out exclusive jurisdiction, the conditions for filing suit, the rule that an arbitration agreement bars court jurisdiction, and the timing of challenges.

Core Conclusions

I. Construction contract disputes are governed as real property disputes and fall under the jurisdiction of the court at the place of the real property.

  • Article 28 of the Interpretation of the Supreme People's Court on the Application of the Civil Procedure Law (Fa Shi [2015] No. 5, 2022 revision): 'Real property disputes under item 1 of Article 34 of the Civil Procedure Law means property rights disputes arising from confirmation, division or neighbouring relations of real property. Rural land contract disputes, housing lease disputes, construction contract disputes and policy housing sale disputes are governed as real property disputes. Where the real property is registered, the place recorded in the real property register is the place of the real property; where it is not registered, the place where the real property is actually situated is the place of the real property.'
  • Article 34 of the Civil Procedure Law (2023 revision): 'The following cases fall under the exclusive jurisdiction of the people's courts designated in this Article: (1) suits over real property disputes fall under the jurisdiction of the people's court at the place of the real property; (2) suits over disputes arising in port operations fall under the jurisdiction of the people's court at the place of the port; (3) suits over inheritance disputes fall under the jurisdiction of the people's court at the domicile of the deceased at the time of death or at the place of the principal estate.'
  • In practice: sue where the works are; for cross-region projects (line works, several sections) jurisdiction follows the works section or the actual location, distinguishing 'place in the register' from 'actual place' under paragraph 2 of Article 28 above according to registration. The parties cannot displace exclusive jurisdiction by agreement on jurisdiction.

II. Where the contract contains a valid arbitration clause, the court will not accept the case.

  • Article 215 of the Interpretation on the Application of the Civil Procedure Law: 'Under item 2 of Article 127 of the Civil Procedure Law, where the parties have included an arbitration clause in their written contract, or have reached a written arbitration agreement after the dispute arose, and one party sues in a people's court, the people's court shall inform the plaintiff to apply to an arbitration institution for arbitration; if the plaintiff insists on suing, the court rules non-acceptance, except where the arbitration clause or arbitration agreement is not formed, is invalid or has lapsed, or its content is unclear and cannot be executed.'
  • Article 5 of the Arbitration Law (2025 revision): 'Where the parties have reached an arbitration agreement and one party sues in a people's court, the people's court will not accept the case, unless the arbitration agreement is invalid or the law provides otherwise.' Article 10: 'Arbitration follows a system of one final award. After an award is made, where a party applies for arbitration again over the same dispute or sues in a people's court, the arbitration institution or the people's court will not accept it. Where the award is set aside by ruling of a people's court according to law or enforcement is refused, the parties may, over that dispute, apply for arbitration under a new arbitration agreement reached between them, or sue in a people's court.'

III. Review points for the validity of an arbitration agreement.

  • Content requirements (Arbitration Law, Article 27): an arbitration agreement includes an arbitration clause concluded in the contract and other written agreements to submit a dispute to arbitration reached before or after the dispute arises; it shall contain: (1) an expression of intent to request arbitration; (2) the matters to be arbitrated; (3) the arbitration institution designated. 'Where a party asserts an arbitration agreement when applying for arbitration and the other party does not deny it before the first hearing, an arbitration agreement is deemed to exist between the parties.'
  • Grounds of invalidity (Article 28): (1) the agreed matters for arbitration exceed the scope of arbitration prescribed by law; (2) the arbitration agreement was concluded by a person with no civil capacity or limited civil capacity; (3) one party coerced the other into concluding the arbitration agreement.
  • Unclear agreement (Article 29): 'Where the arbitration agreement contains no agreement, or an unclear agreement, on the matters for arbitration or the arbitration institution, the parties may conclude a supplementary agreement; where none is reached, the arbitration agreement is invalid.'
  • Separability (Article 30): 'The arbitration agreement exists independently. Whether the contract is concluded, and its amendment, non-entry into force, termination, rescission or invalidity, do not affect the validity of the arbitration agreement reached. The arbitral tribunal has the power to confirm the validity of the contract.' Hence an invalid construction contract does not mean the arbitration clause has lapsed.
  • Challenges to validity (Article 31): the party may request a decision by the arbitration institution or the arbitral tribunal, or a ruling by the people's court; where one party requests a decision by the arbitration institution or tribunal and the other a ruling by the court, the court rules; the challenge must be raised before the first hearing of the arbitral tribunal.
  • Arbitrable scope (Article 3): contract disputes and other property rights and interests disputes between natural persons, legal persons and unincorporated organisations of equal standing may be arbitrated; disputes over marriage, adoption, guardianship, support and inheritance, and administrative disputes that must by law be handled by administrative organs, cannot be arbitrated.

IV. Formal conditions for filing suit.

  • Article 122 of the Civil Procedure Law: 'A suit must meet the following conditions: (1) the plaintiff is a citizen, legal person or other organisation with a direct interest in the case; (2) there is a definite defendant; (3) there are concrete claims, facts and reasons; (4) the case falls within the scope of civil actions accepted by the people's courts and within the jurisdiction of the court seised.'

Scope of Application

  • Exclusive jurisdiction governs the territorial division of labour within the court system and cannot be varied by agreement on jurisdiction; but a valid arbitration agreement is an independent defence barring acceptance. Where both are present, first examine whether the arbitration clause is formed and valid (the four exceptions - not formed, invalid, lapsed, unclear and incapable of execution - allow the court to accept).
  • A written arbitration agreement reached after the contract, or an arbitration agreement deemed to exist because one party asserted it and the other did not deny before the first hearing, likewise bars acceptance.
  • An arbitration agreement binds only its parties: where the actual constructor, subcontractors or migrant workers who are not parties sue the employer or the contractor, the arbitration clause between those parties does not bind them, but they may be affected procedurally by the arbitration agreement between the debtor and the counterparty in a subrogation suit (applying for arbitration before the first hearing can stay the subrogation suit).
  • This card covers civil court jurisdiction versus arbitration; it does not cover administrative complaints, the labour arbitration pre-stage (the labour dispute route for wage claims) or dispute adjudication of project price disputes.

Further Reading

  • Civil Procedure Law (2023 revision), Article 34 (exclusive jurisdiction), Article 122 (conditions of suit), Article 127 item 2 (arbitration agreement and non-acceptance).
  • Interpretation of the Supreme People's Court on the Application of the Civil Procedure Law (Fa Shi [2015] No. 5, 2022 revision), Article 28 (construction contract disputes governed as real property disputes) and Article 215 (arbitration clause and non-acceptance).
  • Arbitration Law (2025 revision), Chapter I General Provisions, Articles 3 to 10; Chapter III Arbitration Agreements, Articles 27 to 31.

Keywords

  • 专属管辖
  • 不动产纠纷
  • 建设工程施工合同纠纷 管辖
  • 仲裁条款
  • 仲裁协议效力异议
  • 不予受理
  • 一裁终局