construction cost expert assessment (judicial appraisal)
Concept Guide
Concept
A construction cost expert assessment (judicial appraisal) is a Chinese procedural institution, not an audit: in litigation or arbitration over a construction price dispute, the court or tribunal commissions a qualified cost consultancy to issue an expert report that serves as evidence. The report must be cross-examined; the court may adopt it wholly, partly, or not at all. Commissioning starts from a party's application or the court's own motion, with the institution chosen from a court register. The assessor works from the contract and supplements, tender documents, the bill of quantities, drawings, variation instructions, site and settlement records; where the contract is silent on pricing, quota norms and published price information are used. Fees are advanced by the applicant and allocated by the court, and items such as all-in unit rates, provisional sums and retention money are computed line by line.
FIDIC Mapping
| Chinese term | FIDIC term | Relation | Note |
|---|---|---|---|
| construction cost expert assessment (judicial appraisal) | DAAB adjudication — Sub-Clause 21.4 [Obtaining the DAAB's Decision] | distinct | Judicial evidence vs contractual adjudication |
| expert assessment report | DAAB's decision — Sub-Clause 21.4 [Obtaining DAAB's Decision] | distinct | Must be cross-examined vs binding on the Parties |
| assessment fee sharing | adjudication: each party bears its own costs | distinct | No inter-party cost recovery |
| pricing from quota norms / published price information | rates from the Bill of Quantities or reasonable Cost plus profit percentage | adjacent | Both start from the Contract |
Key differences
- Initiation: only a court or tribunal can commission an assessment; under FIDIC either Party may refer a dispute to the DAAB (21.4) as a contractual right.
- Nature of the body: the assessing consultancy is an external judicial auxiliary; the DAAB is constituted under 21.1, with 21.2 covering failure to appoint member(s).
- Procedural rigidity: FIDIC imposes a mandatory chain — DAAB decision (21.4), amicable settlement (21.5), then arbitration only on or after the 28th day after the NOD.
- Data source and risk allocation: an assessment may fall back on quota norms and published prices; FIDIC returns first to the Bill of Quantities and agreed rates, and only where none apply to reasonable Cost plus the profit percentage stated in the Contract Data.
Usage warning: Translating this term into an international contract invites the false assumption that a third party can "assess" a price that is automatically effective. FIDIC has no judicial appraisal; a third party's opinion does not bind the Parties, and price disputes must go through the DAAB and arbitration. Reconstructing prices from quota norms will conflict with the contract's rates and risk allocation.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 造价鉴定 | construction cost expert assessment (judicial appraisal) | DAAB adjudication — Sub-Clause 21.4 [Obtaining the DAAB's Decision](争议避免见 21.3) | distinct | 鉴定是法院或仲裁庭委托的诉讼/仲裁外证据程序,当事人不能单方启动;DAAB 是合同内部的争议避免与裁断机制,任一方可提交(21.4),其后仍有 21.5 友好解决与仲裁路径。二者都产生第三方定价意见,但启动权、程序性质与效力完全不同。 |
| 鉴定意见书 | expert assessment report | DAAB's decision — Sub-Clause 21.4 [Obtaining DAAB's Decision] | distinct | 鉴定意见只是证据,须经庭审质证,法院可采信、部分采信或不采信;DAAB 决定按合同约定对双方具约束力,不服只能循 21.5 友好解决或仲裁,不能再另行委托第三方「鉴定」价格。 |
| 鉴定费 | expert assessment fee | adjudication (each party bears its own costs; no recovery from the other party) | distinct | 中国鉴定费由申请方预交,最终按责任比例或败诉方分担,存在费用转移;英式 adjudication 下任何一方均无权向对方索取己方费用,费用风险自担,分配逻辑相反。 |
| 定额/信息价取价 | pricing from quota norms / published price information | new rates or prices based on the Bill of Quantities or other Schedule; otherwise reasonable Cost plus the profit percentage stated in the Contract Data | adjacent | FIDIC 新费率首先回归合同清单与约定费率,无相应费率时才以 reasonable Cost 加合同数据中的利润百分比;中国鉴定在合同约定不足时可整体转向定额与信息价,数据源优先级与调整自由度不同。 |
Updated 2026-09-13
- 01
How construction cost expert assessment handles defective site instruction records (signature proving receipt only without consent, records stating the work item but no quantity or price, verbal instruction only without physical evidence, certification out of time), the evidentiary force of pricing vouchers, and the paths of proof and corroboration
A defective site record is not automatically void; it is handled on thre…
GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.4.2、5.9.1、5.9.2条T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第2.4.7、4.2.2、4.3.6、4.6.6条T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第2.2.3条2026-11-10 - 02
Price adjustment for quantity increases caused by the contractor's construction-stage design development under an EPC lump-sum contract: no adjustment in principle; adjustment only where the difference constitutes an employer-required variation or arises from employer causes
No adjustment in principle; adjustment only by exception. Where the cont…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.25条、第1.0.2条、第3.3.1~3.3.3条、第3.3.9条、第8.2.3条、第8.10.1条T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.4.6条、第4.6节建市〔2020〕96号 建设项目工程总承包合同(示范文本)GF-2020-0216 通用合同条件 第5.1.3款、第5.2.1款、第5.6款、第13.1.1款、第13.3.3款2026-10-29 - 03
Evidence system for a contractor claiming additional works quantities outside the contract scope: four layers of facts to be proved, expert assessment routing where no site instruction records exist, and evidence-gathering means
Claiming additional works quantities cannot rest merely on proof that th…
法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第二十条法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第二十三条(2026年6月30日起施行)GB/T 50500-2024 建设工程工程量清单计价标准 第7.1.1、7.5.5、8.10.1、8.10.2、12.2.1、12.2.2条2026-10-29 - 04
Validity and evidentiary chain where the employer's site representative verbally instructs additional quantities: the four requirements - a competent instructing party, clear content, works actually built, verifiable quantities - with the clause basis and evidence checklist for each, and the path for turning a verbal instruction into a valid pricing voucher
A verbal instruction is not invalid of itself - GB/T 50500-2024 Clause 1…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第12.2.1、12.2.2条法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十条法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第二十三条2026-10-29 - 05
Whether a settlement agreement on the discounted compensation payment, reached after a construction contract is held invalid and the quality of the works is qualified, between the employer and the contractor (or with the unit or individual accepting the contract transfer or unlawful subcontract) is valid: rights and obligations determined by the agreement (Fa Shi [2026] No. 12 Article 12), three preconditions, the relation to 'by reference to the agreed contract price', independent review of the agreement's own invalidity or revocability, and the exclusion of construction cost expert assessment
In principle valid and enforced as agreed: Fa Shi [2026] No. 12 Article…
《中华人民共和国民法典》第一百四十三条、第一百四十六条、第一百五十二条、第一百五十三条、第一百五十四条、第一百五十七条、第五百零四条、第五百零七条、第五百六十七条、第七百九十一条、第七百九十三条《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》法释〔2026〕12号第三条、第六条、第十一条、第十二条、第十三条、第二十一条、第二十三条《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》法释〔2020〕25号第一条、第二十四条、第二十九条、第四十一条、第四十三条2026-10-29 - 06
Rules for handling contract price adjustment for cost fluctuation in final account review and construction cost expert assessment: routing by contract type, price-dating principles for delay periods, the exception for government-priced materials, and the eight categories of costs not adjusted for changes in costs listed in GB/T 50500-2024 clause 8.7.6
Final account review and expert assessment proceed on two levels. (i) Ro…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.6条、第8.7.2条、第8.7.3条、第8.7.6条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.6.2条T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-10-29 - 07
How quantities actually executed but not certified by the supervising engineer or the employer are measured at settlement: the GB 50500-2013 Chapter 8 measurement procedure, the 'deemed approval' rule where verification is overdue, hard cases of non-measurement, and the routes of evidence reinforcement and construction cost expert assessment
Quantities not certified under the standard procedure are in principle n…
GB 50500-2013 建设工程工程量清单计价规范 Ch. 8 工程计量(8.1.1、8.1.2、8.1.3、8.2.1、8.2.3、8.2.4、8.2.5、8.2.6)GB/T 50500-2024 建设工程工程量清单计价标准 第7.1.5、7.1.8、12.2.1条GB/T 51262-2017 建设工程造价鉴定规范 第5.4.2、5.9.2、5.9.3条2026-10-25 - 08
Identifying and pricing additional works from the settlement-review and construction cost expert assessment perspective: supplementary agreements first, no supplementary agreement does not automatically bind the original contract's pricing principles, rate build-up classified by the original pricing method, and the burden of proof (T/ZBD 100.5-2023 clause 3.1.10; T/ZBD 100.4-2023 clause 4.8.3)
Per T/ZBD 100.5-2023 clause 3.1.10 and T/ZBD 100.4-2023 clause 4.8.3: wo…
T/ZBD 100.5-2023 第3.1.10条T/ZBD 100.4-2023 第4.8.3条GB/T 50500-2024 第8.10节2026-10-18 - 09
Cost expert assessment of quantity disputes under unit-rate contracts: the stepped determination where design drawings are missing or cannot show the quantities, and the handling of missing construction or as-built drawings
With design drawings, the assessor re-computes the quantities on the dra…
T/ZBD 100.4-2023 第4.3.5条、第4.3.6条T/ZBD 100.4-2023 第4.6.3条GB/T 51262-2017 第5.4.1条2026-10-01 - 10
Priority order when methods of measurement of different disciplines/versions conflict: contractual agreement -> national standard for measurement of the works matching the contract category -> industry/local standard -> fallback chain for version disputes
On conflict, determine the applicable methods of measurement by the orde…
GB/T 51262-2017 建设工程造价鉴定规范 第5.5.1条T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.3.1、4.3.2条GB 50861-2013 城市轨道交通工程工程量计算规范 第4.2.5条(强制性条文)2026-09-29 - 11
Risks of site instructions and certified records lacking dates (missing the date element): time-bar forfeiture, authenticity doubts, un-anchorable prices, and remedial paths
The date is a statutory content element of site instructions and certifi…
DB37/T 5028-2022 建设工程监理工作规程 第6.3.3条GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.3、7.5.5条DB37/T 5130-2018 建设工程造价咨询服务规范 第7.6.4、9.3.7、9.3.8条2026-09-25 - 12
Determining quantity calculation rules in cost authentication: contract agreement -> national standard -> industry/local standard, and handling version disputes (T/ZBD 100.4-2023)
Quantity calculation rules are the foundation of measurement: where the…
T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.3.1、4.3.2条GB 50861-2013 城市轨道交通工程工程量计算规范 第4.2.5条GB/T 50353-2013 建筑工程建筑面积计算规范2026-09-25 - 13
Determining validity when a site instruction / variation record conflicts with meeting minutes: the three-tier cascade of certification and sign-off validity -> formation time -> actual completion
When a site instruction / variation record conflicts with meeting minute…
GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.9节、第5.9.1条T/GAEC 201-2018 · Guideline for Compilation and Management of Supervision Documents of Construction Projects 第5.1.4条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第12.2.1条2026-09-25 - 14
Whether a variation without the design unit's confirmation can serve as the basis for settlement: the evidentiary status of design confirmation and the five-tier classification
A design change notice is the construction basis and the pricing precond…
T/ZBD 100.4-2023 建设工程造价鉴定作业指引T/ZBD 100.5-2023 建设工程结算审核作业指引GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 15
Determining quantities where drawing dimensions are incomplete: three-tier fallback plus provisional quantities at the tender/preparation stage; re-measurement plus five-tier progressive determination at the settlement stage
Where drawings are incomplete, quantities are determined along two track…
GB/T 50500-2024 建设工程工程量清单计价标准GB 50861-2013 城市轨道交通工程工程量计算规范T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 16
GB/T 50500-2024 Chapter 11 contract-price dispute resolution procedure: the amicable negotiation → dispute review/mediation → arbitration/litigation progression (compared with the repealed GB 50500-2013 Section 13.1 the Engineer's 14-day interim-determination mechanism; including the deletion of the construction cost expert assessment chapter, now carried by GB/T 51262-2017)
GB/T 50500-2024 Chapter 11 provides that contract-price disputes escalat…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works Ch. 11及前言GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第13、14章(已废止)GB/T 51262-2017 · Code for Construction Cost Appraisal2026-09-25 - 17
Settlement of works variations without signed instructions (qianzheng): five-tier determination rules, substitute evidence chains, and variation pricing principles
Signed instructions are not the only settlement basis. Whether an un-ins…
T/ZBD 100.4-2023 建设工程造价鉴定作业指引GB/T 51262-2017 建设工程造价鉴定规范GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 18
Pricing and construction cost expert assessment rules when the price is not confirmed in a site instruction and certified record (GB/T 51262-2017 5.9 tiered pricing)
Price is not a statutory mandatory element of a site instruction and cer…
GB/T 51262-2017 建设工程造价鉴定规范T/ZBD 100.4-2023 建设工程造价鉴定作业指引GB/T 50319-2013 建设工程监理规范2026-09-25 - 19
Document verification in subcontract final account disputes: a five-tier order of evidentiary weight (contract sets the tone → certification and sign-off lock quantities → drawings verify quantities → price evidence verifies prices → supporting evidence validates)
Documents in subcontract final account disputes are checked in tiers of…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 20
Settlement effect of retrospective site instructions and evidence preservation for verbal instructions: five-attribute review, the 7-day certification rule, and the determination ladder in construction cost expert assessment
Retrospectively certified site instructions are not automatically invali…
GB/T 50500-2024 建设工程工程量清单计价标准 第12.2.1/7.5.5/8.1.3条T/ZBD 100.5-2023 建设工程结算审核作业指引 第2.2.3条GB/T 51262-2017 建设工程造价鉴定规范 第5.4.2/5.9节2026-09-25 - 21
Settlement of unfinished works: pricing method by contract type and termination cause (unit rate measured per actuals / lump-sum deduction or direct pricing)
Settlement of unfinished works settles only the completed part: re-measu…
GB/T 51262-2017 建设工程造价鉴定规范T/ZBD 100.4-2023 建设工程造价鉴定作业指引GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 22
Pricing path for variation items with no applicable or analogous all-in unit rate: agreeing a market-reasonable all-in rate, the cost-plus-profit fallback, and the expert-assessment position (GB/T 50500-2024 clauses 8.9 and 8.6.3; GB/T 50319-2013 clause 6.3.3; T/ZBD 100.4-2023 clause 4.6.2)
When a variation item has neither an identical nor an analogous all-in u…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.9.1条、第8.9.2条、第8.9.3条、第8.6.3条GB/T 50319-2013 · Code for Construction Project Supervision 第6.3.3条T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.6.2条2026-09-25 - 23
Order of application of pricing bases for the final account: contract agreement first (agreed terms prevail); quota norms and construction cost management agency's pricing bases as fallback
Final account prices take the contract as the fundamental basis: pricing…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 24
Handling paths when published price information clearly deviates from actual market prices: unify the bases of comparison first to exclude illusions, then correct by scenario (temporary adjustment with later true-up / price certification / expert assessment as fallback)
Published price information is only a reference guide price issued by th…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范GB/T 50875-2013 工程造价术语标准2026-09-25