Settlement of unfinished works: pricing method by contract type and termination cause (unit rate measured per actuals / lump-sum deduction or direct pricing)

Settlement of unfinished works settles only the completed part: re-measurable (unit-rate) contracts measure completed quantities × the contract all-in unit rate per actuals; on termination for contractor breach, lump-sum contracts use the "contract price − unfinished work price" deduction method, and on termination for employer breach the contractor may claim direct pricing of the completed work per the pricing bases (GB/T 51262-2017 §5.10.7), together with the BOQ-ratio method (GB/T 50500-2024 §9.4.3); cost-plus is on agreed cost + fee. Six classes of chargeable cost (completed work costs including changes plus amortised temporary works and site establishment costs and management fees; materials and equipment delivered to site; materials already purchased and paid for, or return losses; demobilisation costs; claims; other losses); the procedure is inventory and measurement → checking → certification and sign-off → separate pricing; quality acceptance is the precondition for pricing, and the assessor does not judge termination liability.

Applicable Codes

  • GB/T 51262-2017 建设工程造价鉴定规范
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • GB/T 50500-2024 建设工程工程量清单计价标准

Topic Positioning

The methodology for settling unfinished works upon contract termination/suspension: pricing method by contract type and termination cause, the scope of chargeable costs, and the settlement procedure. Basis: GB/T 51262-2017 "Code for construction cost expert assessment (judicial appraisal)", Section 5.10; T/ZBD 100.4-2023, Section 4.9; GB/T 50500-2024.

Core Conclusions

Core principle: settle only the completed part; nothing further for the unfinished part. Pricing method by contract type + termination cause: (1) re-measurable (unit-rate) contracts — completed quantities × the contract all-in unit rate measured per actuals, the unit rate being relatively fixed with only changes/claims adjusted, and unfinished portions deducted; (2) lump-sum contracts (contract agreement prevails) — termination for contractor breach uses the deduction method "contract total price − unfinished work price computed at the contemporaneous pricing bases" (the breaching party shall not profit); termination for employer breach may claim direct pricing of the completed work per the pricing bases; (3) lump-sum ratio method — cumulative completed quantity of a billed (BOQ) item ÷ that item's total quantity × the item's total price (GB/T 50500-2024 §9.4.3); (4) cost-plus — cost per the agreed measurement rules + the agreed fee. Six classes of chargeable cost: completed work costs (including changes) together with amortised temporary works and site establishment costs and management fees; costs of materials and equipment delivered to site; costs of materials already purchased and paid for, or return losses; losses from demobilising personnel, machinery and turnover materials; claim costs; other losses. Five-step procedure: inventory the completed parts and measure quantities (a third-party survey may be commissioned where they cannot be verified) → inventory the labour, materials and machinery on site → check site instruction and variation records and claim documentation → summarise into registers for the parties' certification and sign-off → price each separately.

Applicable Boundaries

Applies to unfinished-work settlement and construction cost expert assessment upon contract termination/suspension; where the contract so provides, the contract prevails; quality acceptance is the precondition for pricing (no price may be claimed for parts that remain unqualified after repair); the assessor only quantifies amounts and does not analyse the causation of termination or liability (which rests with the client), and should specify the assessment base date; in lump-sum termination disputes the completed and unfinished portions may be assessed separately at the client's request.

Further Reading

GB/T 51262-2017, Section 5.10 (5.10.1-5.10.7, procedure and the two lump-sum methods); T/ZBD 100.4-2023, Clauses 4.9.2-4.9.4 (six cost classes, no assessment of liability, completed and unfinished portions assessed separately) and Clause 4.2.4 (choice of assessment method by contract type); GB/T 50500-2024, Clause 9.4.3 (lump-sum ratio method) and Section 10.4 (settlement on force majeure / termination for breach).