Repricing the remaining works after a subcontractor's exit (subcontract termination): splitting into two accounts and three repricing modes for the successor
A subcontractor's exit is a subcontract termination, and pricing splits into two accounts: (1) settle the completed works with the exiting subcontractor under the termination rules (pay the agreed price for completed work that passes quality checks; a re-measurable (unit-rate) contract at completed quantity x the agreed unit rate; a lump-sum contract at the contract total price less the price of the unfinished works, or the completed price computed directly on the pricing bases); (2) reprice the works for the successor by choosing one of three options — continuing the original contract unit rates, deriving new (built-up) rates, or cost plus fee / an all-in lump sum — with reference to the review principles for additional works, and with interface treatment costs included where new rates are derived.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 51262-2017 建设工程造价鉴定规范
- DB37/T 5130-2018 建设工程造价咨询服务规范
- T/ZBD 100.5-2023 建设工程结算审核作业指引
- DB11/T 382-2017 建设工程监理规程
Topic Positioning
A subcontractor's exit means termination of the subcontract; this card gives the "two accounts" split after exit and the repricing rules for the remaining works, applicable to contract-change scenarios at all levels — main (general) contracting, specialist subcontracting, labour subcontracting.
Core Conclusions
Exit pricing splits into two accounts: (1) Closing out with the exiting subcontractor — termination only ends the unperformed part; the performed part must be settled, and completed work that passes quality checks is paid at the agreed price (Supreme People's Court Interpretation I on Construction Contracts, Article 10); for a re-measurable (unit-rate) contract, completed quantity x the agreed unit rate, with unit-price preliminary items considered by physical progress and total-price preliminary items proportionally to their linkage with unit-price items; for a lump-sum contract terminated through the contractor's breach, the contract total price less the price of the unfinished works computed on contemporary pricing bases; where the employer is in breach and termination results, the contractor may claim the completed price computed directly on those pricing bases (GB/T 51262-2017 Clause 5.10.6; DB37/T 5130-2018 Clause 9.3.17); on-site materials are attributed in three states — already incorporated into the works, ordered and delivered, and unpaid and undelivered. (2) Repricing for the successor by one of three options: continuing the original contract unit rates (where the completed/uncompleted boundary is clear and the BOQ is divisible, on a basis consistent with the main contractor's approach to the employer); derivation of new (built-up) rates (where the original unit rates are distorted or the works cannot be divided, using quota norms / BOQ plus current published price information (government guidance prices)); cost plus fee, or an all-in lump sum (for boundary-blurred closing and remedial work). The remaining works are a continuation outside the original contract scope and may refer to the review principles for additional works: where the parties sign a supplementary agreement clarifying the pricing principles, follow that agreement; where they do not, the original contract pricing principles do not necessarily apply (T/ZBD 100.5-2023, Clause 3.1.10). Derivation of new rates easily omits interface treatment costs (re-checking, trimming, connection works), which must be included.
Applicable Boundaries
The first account must be locked before discussing the second — letting the new subcontractor onto site before the completed quantities are locked creates overlapping measurement or a measurement vacuum. This card applies to termination/exit pricing; an invalid contract follows compensation at a discount (Civil Code Article 793), which is a separate rule; dayworks and site instruction pricing are not covered.
Further Reading
GB/T 50500-2024 Section 10.4 (settlement upon termination of contract); GB/T 51262-2017 Section 5.10 (expert assessment of termination disputes, Clause 5.10.6 re-measurable contracts); DB37/T 5130-2018 Clause 9.3.17 (expert assessment on suspension of lump-sum contracts); T/ZBD 100.5-2023 Clause 3.1.10 (final account review for additional works); DB11/T 382-2017 Clauses 7.2.18~7.2.19 (amounts due to each party upon termination).
Keywords
- 分包退场
- 合同解除
- 剩余工程重新计价
- 已完工程结算
- 续接单位
- derivation of new (built-up) rates
- 新增工程审核
- 分包合同解除结算