derivation of new (built-up) rates
- 01
Re-measurement and price splitting after rebar substitution: re-measure from the variation drawings, count the quantity once only (lap and wastage coverage), the splitting formula of the quantity difference at the contract rate plus the material price difference carrying VAT only, and the 15% clause boundary among adopting the contract rate / converting an analogous rate / building up a new rate (GB/T 50500-2024 cl. 7.4.2, 8.2.1, 8.9.1, 8.9.2 and 3.3.5)
After a rebar substitution, re-measure from the variation instruction an…
GB/T 50500-2024 第7.4.2条GB/T 50500-2024 第8.2.1条GB/T 50500-2024 第8.9.1条2026-11-08 - 02
Trigger table for the +/-15% quantity deviation threshold: the three outcomes of retaining the original price, adjusting the rate and deriving new rates, and the dividing lines between them (GB/T 50500-2024 Articles 8.2.1, 8.9.1, 8.9.2 and 8.9.3)
Under GB/T 50500-2024 the 15% mark is only a threshold on quantity, and…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.2.1条、第8.9.1条、第8.9.2条、第8.9.3条、第7.1/7.2/7.4节GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.6.2条、第9.6.3条、第9.3.1条T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.4.4条2026-11-08 - 03
Three-tier re-rating of all-in unit rates after changes in item description/work content: retain the contract unit rate, convert the contract unit rate, or negotiate a new rate (GB/T 50500-2024 Clause 8.9.1)
Changes in item description/construction conditions are handled in three…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.2.1条、第8.9.1条、第8.9.2条、第8.9.3条、第8.10.3条T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.4.4条GB/T 50319-2013 · Code for Construction Project Supervision 第6.3.3条2026-11-08 - 04
Whether varied works may be given newly built-up rates when the priced BOQ already contains an applicable rate: the three-tier decision table for variation valuation, the tests for 'applicable' and 'similar', and a clause-by-clause comparison of GB 50500-2013 clause 9.3.1 with GB/T 50500-2024 clause 8.9.1
For BOQ items whose applicable rate already exists in the contract, vari…
GB 50500-2013 建设工程工程量清单计价规范 第9.3.1条GB 50500-2013 建设工程工程量清单计价规范 第9.6.2条GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.24条2026-10-25 - 05
Rate build-up basis and confirmation procedure when a BOQ omission or new item has neither an applicable nor an analogous rate: GB 50500-2013 Section 9.5 (citing the four tiers of cl. 9.3.1) mapped against GB/T 50500-2024 Sections 8.2/8.9/8.10, plus the time limits for adjustment reports
GB 50500-2013 cl. 9.5.1 provides that 'where, during performance, new di…
GB 50500-2013 第9.1.2条、第9.1.4条、第9.3.1条、第9.3.2条、第9.5.1~9.5.3条、第9.6.2条(已废止)GB/T 50500-2024 第8.1.2~8.1.4条、第8.2.1~8.2.3条、第8.9.1~8.9.2条、第8.10.1~8.10.5条、第8.6.3条、第7.2.1条住房城乡建设部公告 2024 年第 212 号(GB/T 50500-2024 自2025年9月1日起实施)2026-10-25 - 06
Setting overheads and profit in repricing variations and other price adjustments (GB/T 50500-2024 Articles 3.6.6, 8.4.6, 8.8.5, 8.9.1)
On repricing (no identical or similar rates), GB/T 50500-2024 Article 8…
GB/T 50500-2024 第3.3.5条、第3.6.6条、第8.4.6条、第8.6.3条、第8.8.5条、第8.9.1~8.9.3条T/ZBD 100.4-2023 第4.6.2条GB/T 50319-2013 第6.3.3条2026-10-12 - 07
Derivation of new (built-up) rates when a design change changes the construction process (construction method): qualifying the source + the three-tier path of GB/T 50500-2024 clause 8.9.1
"Change of construction method" is a price-impact factor of "item descri…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.9.1条、第8.9.2条、第8.9.3条GB/T 51095-2015 建设工程造价咨询规范 第5.3.9条DB11/T 382-2017 北京市建设工程造价管理暂行规定 第5.3.2条2026-09-25 - 08
Repricing the remaining works after a subcontractor's exit (subcontract termination): splitting into two accounts and three repricing modes for the successor
A subcontractor's exit is a subcontract termination, and pricing splits…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范DB37/T 5130-2018 建设工程造价咨询服务规范2026-09-25