Whether a variation without the design unit's confirmation can serve as the basis for settlement: the evidentiary status of design confirmation and the five-tier classification

A design change notice is the construction basis and the pricing precondition — not usable in the works without countersignature and seals; yet design confirmation is not the only path to establish a change — with written instructions from the employer/supervision but no design document, the change may still stand. Settlement is decided by a five-tier evidence chain: changes proposed by the contractor with no confirmation and no drawings should not adjust the cost; remedies include completing the change formalities, securing written instructions, preserving as-built evidence, and mutual countersignature.

Applicable Codes

  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51262-2017 建设工程造价鉴定规范
  • DB11/T 1745-2020 建筑工程施工技术管理规程
  • T11 IESB 0001-2017 建筑电气工程施工资料管理规程
  • GB 55032-2022 建筑与市政工程施工质量控制通用规范
  • 建设工程勘察设计管理条例(国务院令第687号)

Topic Positioning

Answers "can a change without the design unit's confirmation serve as the settlement basis": the status of design change documents (change notice/change drawings) in the settlement and judicial appraisal evidence chain, the five-tier classification, and remedy paths — for settlement audit, judicial appraisal, and in-process evidence management.

Core Conclusions

A design change notice supplements and amends the construction drawings and is the construction basis; one lacking four-party countersignature and complete seals must not be used in the project (DB11/T 1745-2020 5.2.4, T11 IESB 0001-2017 4.2.4), and the contractor must not alter the design on its own (Building Law Article 58, "Regulations on administration of survey and design of construction projects" Article 28) — design confirmation is the formal element of the "design-document change" path. But it is not the only path to establish a change: settlement audit recognizes three change bases — instructions of the employer and its supervision (consultant), design-document changes, and approved contractor rationalization proposals (T/ZBD 100.5-2023 3.1.8); a change may stand on written instructions without design documents. Judicial appraisal classifies by the five-tier evidence chain (T/ZBD 100.4-2023 4.6.6): not contractor-proposed with both instruction and drawing -> definitive opinion; only one of the two -> definitive opinion with explanation; contractor-proposed with one party's consent -> definitive opinion; contractor-proposed with drawing but no confirmation -> selective opinion, settlement at risk; neither confirmation nor drawing -> no cost adjustment, not settleable. Remedies: complete the change formalities; seek written instructions from the employer/supervision; oral instructions evidenced by as-built proof are excepted (GB/T 50500-2024 12.2.2); mutually countersign the total price, quantities, or labor/material/machinery unit prices (4.6.3); site survey (GB/T 51262-2017 5.4.2).

Applicable Boundaries

Applies to settlement audit and judicial appraisal; contract agreements prevail. Changes touching structure, fire protection, civil air defense, energy saving, or environmental protection must be re-reviewed; railways and other industries have separate change-classification and approval measures. Design-confirmed but seal-deficient documents are procedural defects (distinct from "no design confirmation at all" here) — see the related signature-defect card.

Further Reading

T/ZBD 100.4-2023 Clauses 4.6.1, 4.6.2, 4.6.3, 4.6.6; T/ZBD 100.5-2023 Clause 3.1.8; GB/T 50500-2024 Clause 12.2.2 and Section 8.9; GB/T 51262-2017 Clauses 5.4.2, 5.9.3; DB11/T 1745-2020 Clause 5.2.4; T11 IESB 0001-2017 Clause 4.2.4; GB 55032-2022 Clause 2.0.5; "Regulations on administration of survey and design of construction projects" Article 28.