Validity of the employer's verbal instruction (to be confirmed in writing) to change the design: invalid in principle, with two remedial paths
A verbal instruction (to be confirmed in writing) from the employer to change the design is in principle invalid: a design change (designer-issued variation) must be issued by the design unit in the form of drawings or a designer's change instruction (CJJ/T 91-2017 8.2.4, T11 IESB 0001-2017 4.2.4), and must undergo certification and sign-off by the employer, design unit, contractor, and supervision unit, and the variation instruction must be issued by the Engineer (chief supervising engineer under China's supervision regime) before construction may proceed (GB/T 50319-2013 6.3.1); construction must not proceed without the issued instruction. For pricing, GB/T 50500-2024 China national pricing standard for BOQ, Clause 12.2.2 states that "verbal instructions shall not serve as pricing vouchers, except where there is evidence proving the contractor has completed construction per the verbal instruction". Remedies: (1) subsequent written form (a verbal instruction converted into a written site instruction / variation record is valid, GB/T 51262-2017 Section 5.9); (2) evidence preservation — keep photos/videos, meeting minutes, supervision logs, and other physical evidence proving construction per the instruction; where there is neither written form nor physical evidence and the employer does not acknowledge it, the construction cost expert assessment (judicial appraisal) makes a negative finding on the ground of lack of legal evidence (GB/T 51262-2017 5.9.3).
Applicable Codes
- 《建设工程勘察设计管理条例》(国务院令第687号,2017修订)第二十八条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第12.2.2条
- GB/T 50319-2013 · Code for Construction Project Supervision 第6.3.1条
- GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.9、5.9.3条
- T11 IESB 0001-2017《建筑电气工程施工资料管理规程》第4.2.4条
- CJJ/T 91-2017 第8.2.4条
- DB13(J)/T 8161-2019 第9.1.1条
Topic Positioning
Answers "whether the employer's verbal instruction (to be confirmed in writing) to change the design is valid": the validity determination and remedial paths of verbal instructions at three levels — variation formation, pricing voucher, and construction cost expert assessment (judicial appraisal).
Core Conclusions
A verbal instruction (to be confirmed in writing) from the employer to change the design in principle produces no variation effect — it constitutes neither a valid design change (designer-issued variation) nor a pricing voucher directly; both paths of "design document modification procedure + written site instruction / variation record" must be completed. Three levels of basis:
(1) Variation formation level: Article 28 of the Regulations on the Administration of Survey and Design of Construction Projects (State Council Decree No. 687, 2017 revision) states — "The employer, contractor, or supervision unit shall not modify the survey and design documents of construction projects; where modification is genuinely needed, it shall be made by the original survey and design unit" — a verbal decision by the employer produces no effect of modifying design documents; a design change proposed by the employer must be issued by the design unit via a designer's change instruction (T11 IESB 0001-2017 Clause 4.2.4). Procedurally, per GB/T 50319-2013 Code for construction project supervision, Clause 6.3.1: a variation shall undergo certification and sign-off by the employer, design unit, contractor, and supervision unit, and the contractor may proceed with construction only after the Engineer (chief supervising engineer under China's supervision regime) issues the variation instruction; where the modification involves engineering design documents, the employer shall transfer them to the original design unit for modification.
(2) Pricing level: GB/T 50500-2024 China national pricing standard for BOQ, Clause 12.2.2 — "verbal instructions shall not serve as pricing vouchers, except where there is evidence proving the contractor has completed construction per the verbal instruction".
(3) Dispute resolution level: GB/T 51262-2017 Code for construction cost expert assessment (judicial appraisal) of construction projects, Clause 5.9.3 — "where the contractor claims payment for a piece of miscellaneous work or works completed solely per the employer's verbal instruction, the employer does not acknowledge it, and there is no physical evidence, the expert assessor shall make a negative assessment on the ground of lack of legal evidence".
Two remedial paths: (1) subsequent written form — request a supplementary written variation notice, or have the contractor convert the verbal instruction into a written site instruction / variation record; once converted into a written site instruction / variation record it is valid (GB/T 51262-2017 Section 5.9); (2) evidence preservation — photos and videos, signed meeting minutes, supervision logs, WeChat/email correspondence, forming a complete physical-evidence chain of "construction completed per instruction".
Applicable Boundaries
Applies to scenarios where the employer gives a verbal instruction at the construction/supervision stage; the 12.2.2 exception requires a complete physical-evidence chain capable of rebutting the employer's non-acknowledgment; where the contract stipulates stricter requirements on written form and reply time limits, the contract prevails; variations requiring modification of design documents and involving fire protection, civil air defence, environmental protection, energy saving, structure, etc. shall be re-examined by the relevant authorities as required (GB/T 50319-2013 Clause 6.3.1); dispute expert assessment follows the evidence-grading rules of T/ZBD 100.4-2023 Clause 4.6.6.
Further Reading
GB/T 50500-2024 China national pricing standard for BOQ, Clause 12.2.2; GB/T 51262-2017 Clauses 5.9, 5.9.3; GB/T 50319-2013 Clause 6.3.1; Regulations on the Administration of Survey and Design of Construction Projects (State Council Decree No. 687) Article 28; T11 IESB 0001-2017 Management regulation for construction documentation of building electrical works, Clause 4.2.4; CJJ/T 91-2017 Clause 8.2.4; DB13(J)/T 8161-2019 Clause 9.1.1.