Evidence system for a contractor claiming additional works quantities outside the contract scope: four layers of facts to be proved, expert assessment routing where no site instruction records exist, and evidence-gathering means

Claiming additional works quantities cannot rest merely on proof that the works 'were carried out'; the contractor must also prove (i) instruction or consent by the employer, (ii) actual completion of the works, and (iii) that the quantities are measurable and verifiable ((iv) price supported by evidence). Article 20 of Fa Shi [2020] No. 25 ranks site instruction records and other written documents as first-tier evidence, but also provides that 'where the contractor can prove that the employer consented to the works but fails to produce site instruction records to prove the quantities, the quantities actually incurred may be determined on the basis of other evidence provided by the parties'; where there is only a verbal instruction, the employer does not recognise it and no physical evidence exists, the construction cost expert assessment should reach a negative opinion on the ground of absence of legal evidence (GB/T 51262-2017, Clause 5.9.3).

Applicable Codes

  • 法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第二十条
  • 法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第二十三条(2026年6月30日起施行)
  • GB/T 50500-2024 建设工程工程量清单计价标准 第7.1.1、7.5.5、8.10.1、8.10.2、12.2.1、12.2.2条
  • GB/T 51262-2017 建设工程造价鉴定规范 第5.4.2、5.9.1、5.9.2、5.9.3条
  • 财建〔2004〕369号 建设工程价款结算暂行办法 第十四、十五、十六条
  • 中华人民共和国民法典 第五百一十一条、第五百四十四条
  • 中华人民共和国民事诉讼法(2023修正)第六十七条
  • 法释〔2015〕5号 最高人民法院关于适用《中华人民共和国民事诉讼法》的解释(2022修正)第一百一十二条
  • 中华人民共和国国务院令第802号 保障中小企业款项支付条例(2025修订)第十二条

Topic positioning

This card answers 'what evidence a contractor needs to claim additional works quantities outside the contract scope (including variation increments, sundry works and dayworks)': an evidence checklist layered by the fact to be proved, quotable original standard clauses, the routing rules of construction cost expert assessment where site instruction records are missing or defective, and remedial evidence-gathering measures. For use in final account submission, expert assessment proof and litigation evidence planning.

Core conclusions

I. General principle of proof Fa Shi [2020] No. 25, the SPC Interpretation on the Application of Law to Construction Contract Dispute Cases (I), Article 20: 'Where the parties are in dispute over quantities, determination shall be made on the basis of written documents formed during construction, such as site instruction records. Where the contractor can prove that the employer consented to the works but fails to produce site instruction records evidencing the quantities, the quantities actually incurred may be determined on the basis of other evidence provided by the parties.' That is: site instruction records and other written documents are the first tier, but not the only basis; the proof must simultaneously cover the four links 'employer instruction/consent -> works actually completed -> quantities measurable and verifiable -> (price)'; if one link of the chain is missing, the amount is unsupported.

II. Four layers of facts to be proved and the corresponding evidence

Fact to be proved Primary evidence (direct probative force) Corroborating evidence Standard anchor
(i) Employer instruction/consent to the works variation instructions, supplementary agreements, written commissions or work contact sheets (with proof of receipt), minutes of meetings WeChat/email/text messages, countersigned regular meeting records, supervising engineer's logs, programme submission records GB/T 50500-2024 Clause 12.2.2; GB/T 51262-2017 Clause 5.4.2
(ii) Works actually completed and conforming in quality site instruction records, quantity confirmation sheets, concealed works acceptance records, inspection lot and sub-item acceptance documents, as-built drawing annotations site diaries (daily, no retrospective entries), material delivery and test reports, plant machine-shift records, photographic and survey output, third-party survey results GB/T 50500-2024 Clauses 12.2.1 and 7.1.1
(iii) Quantities measurable and verifiable quantity take-off statements prepared under the measurement standards and calculation rules agreed in the contract (with drawings, formulae and locations) comparison of contract drawings against as-executed drawings and variation instructions, site inspection GB/T 50500-2024 Clause 7.1.1; GB/T 51262-2017 Clause 5.4.2 paragraph 2
(iv) Price (the amount claimed) priced BOQ of work items and preliminaries, unit rates agreed in supplementary agreements unit rates of similar contemporaneous projects, published price information and market price enquiries, quota-based rate build-up statements GB/T 50500-2024 Clauses 8.10.1 and 8.10.2; Civil Code Article 511 item (ii)

III. Expert assessment routing where site instruction records are missing or defective

  1. Where the works lie outside the construction drawings or the agreed contract scope and the contractor demands settlement for sundry works ordered by the employer but holds no site instruction record or written approval, GB/T 51262-2017 Clause 5.4.2: '1. Where the employer approves, or other evidence provided by the contractor can prove the works, the assessor should issue a positive assessment opinion for the commissioning party's judgement; 2. where the employer does not approve but the works admit of site inspection, the assessor should request the commissioning party to organise a site inspection and assess on the basis of the inspection results.'
  2. Where the sundry works were carried out on a verbal instruction only, the employer does not recognise it and no physical evidence exists, GB/T 51262-2017 Clause 5.9.3: 'The assessor should issue a negative assessment opinion on the ground of absence of legal evidence.'
  3. Where the site instruction record is defective, Clause 5.9.2: '1. Where on the record the employer merely signed acknowledgement of receipt without indicating approval, and the contractor has evidence that the works under the record were completed, the assessor may issue an assessment opinion and list it separately for the commissioning party's judgement; 2. where the record contains neither quantity nor price but only the work item, the parties shall negotiate; failing agreement, the assessor may, following the principles and methods agreed in the construction contract, professionally analyse the item and issue an inferential opinion for the commissioning party's judgement.'
  4. For the tiered pricing of records having quantity but no price, see GB/T 51262-2017 Clause 5.9.1 (labour unit rate referenced to the labour unit rate of the corresponding works plus about 20%, materials and machine-shifts at the prices of the corresponding works, etc.).

IV. Written form and the evidentiary force of pricing documents GB/T 50500-2024 Clause 12.2.1: 'The employer and the contractor shall agree in the contract the scope of duties of their respective on-site management personnel; written documents confirmed by signature by the on-site management personnel of both parties within their scope of duties shall be valid documents for construction pricing, except where other valid evidence or verified proof establishes that they are false.' Clause 12.2.2: notices, approvals, certifications, certificates, instructions, orders, requests, consents, opinions, determinations and decisions relating to construction pricing shall all be in written form and, within the agreed time limit (or a reasonable period where none is agreed), be delivered to the designated receiving address by express courier, dedicated person, registered mail, fax, email, WeChat or other instant messaging tools, or an agreed electronic means; 'a verbal instruction shall not serve as a pricing document, except where evidence proves that the contractor has completed the works pursuant to the verbal instruction.' Clause 7.5.5: where the employer fails to provide verification or review results within the agreed time limit, 'the contents of the statements or dayworks reports submitted by the contractor shall be deemed approved by the employer'; the numbers of construction personnel, materials and construction plant in a dayworks report constitute the measured quantities and exclude the contractor's own on-site management personnel and the construction plant already on site.

V. Procedural preconditions for additional works (without them, even ample proof can hardly be priced) Clause 8.10.1: where the contractor completes, at the employer's request, additional works outside the scope agreed in the contract, the price may be calculated under the bill itemisation requirements, measurement rules, contract unit rates and tender pricing level prescribed by the national and industry measurement standards agreed in the contract, or the parties may re-negotiate the measurement and pricing rules and conclude an additional works contract or a supplementary agreement; the preliminaries shall include the costs of extended use of, or additional, preliminary items. Clause 8.10.2: before implementing the additional works, the contractor shall submit to the employer for review its project execution plan or implementation scheme, its construction programme and the priced offer for its claimed costs (covering the work-item and preliminaries bills); the employer shall review and approve them within a reasonable time. Clause 7.1.1: re-measurement, measurement of variations and measurement of additional works shall be based on the qualified works which the contractor has completed as agreed in the contract and which are to be measured, and on the construction drawings and variation instructions issued by the employer, and shall be measured under the measurement standards and supplementary calculation rules agreed in the contract.

VI. Time limits and sign-off rules in the ministerial regulation (Cai Jian [2004] No. 369, Interim Measures for the Settlement of Construction Project Payments) Article 14: 'Where the employer requires the contractor to complete sundry items outside the contract, the contractor shall, within 7 days of accepting the employer's request, submit a construction site instruction record to the employer stating labour quantities and unit rates, plant machine-shift quantities and unit rates, materials used and amounts; the works proceed after the employer signs the record; where the employer has not signed and a dispute arises after the works, the responsibility is borne by the contractor.' Article 15: 'Site instruction records signed by the site representatives authorised by both parties, and claim fees agreed by both parties through negotiation, shall be handled faithfully in the final account of the works; their validity shall not be altered by a mid-way change of the site representatives of either party.' Article 16: where the employer raises no objection within the prescribed or agreed period after receiving the final account report and the complete documents, it is deemed to have approved them; where the contractor fails to provide complete documents on time and, after being urged, still fails to provide them or give a definite reply within 14 days, the employer may review on the basis of the documents available, and the responsibility is borne by the contractor.

VII. Burden of proof and evidence-gathering means Civil Procedure Law Article 67: 'A party has the responsibility to provide evidence for its own claims.' 'Evidence that a party or its agent ad litem cannot collect for objective reasons, or that the people's court considers necessary for the trial of the case, shall be investigated and collected by the people's court.' Fa Shi [2015] No. 5, Article 112: 'Where documentary evidence is under the control of the opposing party, the party bearing the burden of proof may, before the expiry of the evidence production period, apply in writing to the people's court to order the opposing party to produce it. ... Where the opposing party refuses to produce it without justified reasons, the people's court may find the contents of the documentary evidence alleged by the applicant to be true.' Supervising engineer's logs, the employer's internal approvals and technical verification sheets, and meeting minutes are often controlled by the other side; this procedure should be actively used to obtain them.

VIII. Substantive rules on variations and price (they decide where the evidence should aim) Civil Code Article 544: 'Where the parties' agreement on the content of the change of the contract is unclear, the change is presumed not to have been made.' Where the scope, quantity or price of a change is not fixed in writing, adjustment does not automatically follow the contractor's position. Article 511 item (ii): where the price or remuneration is unclear, 'performance shall be made at the market price of the place of performance at the time the contract was concluded; where government pricing or government guidance pricing should be executed as required by law, performance shall follow those provisions'. Regulation on Ensuring Payment to Small and Medium-sized Enterprises (State Council Decree No. 802, 2025 revision) Article 12: 'Government agencies, public institutions and large state-owned enterprises may not compel that the audit result of an audit authority serve as the basis for settlement, except as otherwise provided by laws or administrative regulations.' Payment of confirmed amounts may not be refused on the ground that the audit is unfinished.

Applicability boundaries

  • Applies to final account submission, construction cost expert assessment and litigation proof for additional works, variation increments, sundry works and dayworks between employer and contractor; it does not apply to judging whether a design change itself takes effect (see the separate card on expert assessment routing for variations without site instruction records), nor does it change the measurement basis of the quantities: evidence only proves 'what happened', while 'how to compute' still follows the measurement standards and calculation rules agreed in the contract (GB/T 50500-2024 Clause 7.1.1).
  • Time boundary: the SPC Interpretation on Construction Contract Disputes (II) (Fa Shi [2026] No. 12) takes effect on 30 June 2026; its Article 23 provides that 'this Interpretation applies to first-instance construction contract dispute cases newly accepted by the people's courts after its entry into force' and that 'where judicial interpretations previously issued by the Supreme People's Court are inconsistent with this Interpretation, this Interpretation prevails'. First-instance cases newly accepted after 30 June 2026 therefore follow Interpretation II, cases accepted earlier follow Interpretation I, and where the two diverge Interpretation II prevails: confirm the case acceptance date before citing any article.
  • Where the contract provides 'no price adjustment without site instruction records', proof is held to a stricter standard; but where employer consent to the works can be proved, settlement on the actual quantities may still be reached in practice.
  • Where there is only a verbal instruction, the employer does not recognise it and no physical evidence exists, the expert assessment is negative on the ground of absence of legal evidence; corroborating evidence of completion cannot substitute for the missing 'instruction' link.
  • The 7-day site instruction record deadline under Cai Jian [2004] No. 369 is a ministerial department rule; agreed contract terms prevail, but the risk of missing the deadline lies with the contractor.

Further reading

  • Fa Shi [2020] No. 25 Article 20; Fa Shi [2026] No. 12 Article 23 (entry into force and old-new transition)
  • GB/T 50500-2024, national BOQ pricing standard: Clauses 7.1.1, 7.5.5, 8.10.1, 8.10.2, 12.2.1, 12.2.2
  • GB/T 51262-2017, code for construction cost expert assessment: Clauses 5.4.2, 5.9.1, 5.9.2, 5.9.3
  • Cai Jian [2004] No. 369, Interim Measures for the Settlement of Construction Project Payments: Articles 14 to 16
  • Civil Code Articles 511 and 544; Civil Procedure Law Article 67; Fa Shi [2015] No. 5 Article 112; SME Payment Regulation Article 12
  • Evidence routes: the order to produce documentary evidence (materials controlled by the other side); site inspection (requested through the commissioning party at the assessment stage); cross-verification of the site diary against the supervising engineer's log