Engineering Knowledge Cards.

variation record / site instruction

44 knowledge cards · sorted by most recently updated

Concept Guide

Concept

In Chinese construction practice, the site visa (现场签证) is a written, certified record of site events that the contract drawings, bills of quantities or specifications did not anticipate — dayworks, minor demolition, ground conditions differing from the site investigation, substituted materials, suspension or idle time. The contractor raises the request, stating the cause, quantities, resources used and cost build-up; the employer, or its appointed supervisor or cost consultant, verifies and signs it. The signed document then serves as evidence for measurement, interim payment, the final account and any subsequent claim.

Mechanism: the contractor initiates and the employer certifies. Certification normally confirms the facts and quantities only, and does not by itself fix the price; unit rates and valuation rules are agreed separately under the contract or by negotiation. Uncertified site facts remain the contractor's burden to prove, and the time limits for raising and certifying site records may bar a late claim. The record interacts with neighbouring mechanisms: a variation changes the design or scope, whereas a record confirms work already carried out; a claim asserts an entitlement and the record is often its factual basis; a certified record of agreed material prices fixes prices the parties have accepted.

FIDIC Mapping

Chinese term FIDIC term Relation Key point
现场签证 site instruction / variation record distinct Certified evidence vs. instruction
工程变更 variation adjacent Engineer initiates by notice
口头指令 verbal instruction (to be confirmed in writing) adjacent To be confirmed in writing
变更计价 valuation of variations adjacent Valued from instruction and particulars

Key differences: under the 2017 Yellow Book, Sub-Clause 3.5 [Engineer's Instructions] allows the Engineer to issue, at any time, instructions necessary for the execution of the Works, and the Contractor takes instructions only from the Engineer, the Engineer's Representative or an assistant duly authorised under Sub-Clause 3.4. Variations are initiated by the Engineer/Employer giving a notice describing the required change and stating any requirements for the recording of costs, in accordance with Sub-Clause 3.5/3.4 and subject to Clause 13.1; the Contractor has the right to object to a variation instruction. Where the Engineer issues an instruction that it does not state to be a variation but the Contractor considers it to be one, the Contractor may, following a Notice to the Engineer with reasons under Sub-Clause 3.5, have the Engineer confirm, reverse or vary that instruction. Within 28 days of receiving the instruction, the Contractor submits detailed particulars, including a description of the varied work and the resources and methods adopted, a programme for its execution and any proposed modifications to the Programme. The distinction is therefore structural rather than verbal: FIDIC operates an instruction regime in which the Engineer's instruction is itself the basis for the variation and for valuation, with no parallel two-track system of a contractor's application plus the employer's certified record, whereas the Chinese mechanism operates a certification regime in which the site fact arises first and is certified afterwards, the signed record being the evidence of additional cost.

Use with caution: when reading a FIDIC contract, do not borrow the literal Chinglish rendering of the Chinese term, and do not assume that a signed paper record from the employer must be in hand before work proceeds — under FIDIC an Engineer's instruction takes effect, and becomes the basis for valuation, on issue.

Chinese TermEnglish TermFIDIC TermRelationNotes
现场签证site instruction / variation recordEngineer's instruction (Sub-Clause 3.5)distinct中国由承包人申请、发包人签认形成增支凭证;FIDIC 由工程师发出指令,指令本身即变更与计价依据,无对等的签证凭证双轨。
工程变更variationVariation (Clause 13.1; Sub-Clause 13.3.1)adjacentFIDIC 变更由工程师/业主发通知发起,承包商享有异议权;中国变更通常须经设计、业主、监理多方签认后实施。
口头指令verbal instruction (to be confirmed in writing)instruction to be confirmed (Sub-Clause 3.5)adjacentFIDIC 允许工程师发指令后书面确认,承包商可依 3.5 请工程师确认、撤销或修改;中国口头指令一般须另补签认手续。
变更计价valuation of variationsVariation by Instruction (Sub-Clause 13.3.1)adjacentFIDIC 计价以指令及承包商 28 天内提交的详细资料为基础;中国先以签证确认事实与数量,单价另按合同或协商确定。
签证时效time limits for raising and certifying site records28-day particulars under the variation procedure (Sub-Clause 13.3.1)adjacent两者均设时限,但 FIDIC 约束变更详情的提交,中国时效约束签证主张与签认本身。

Updated 2026-09-13

Topic Overview Cards

Site instructions and certified records overview: applicable matters and prohibited items, the five-node handling procedure, graded signing authority, the 2024 standard basis and settlement application

Certification runs a five-node closed loop: assess reasonableness beforehand and survey the original conditions → at occurrence, measure on site, keep photos, have all parties sign the original vouchers → submit the certification file within the contract-agreed time → the supervising engineer reviews, the chief supervising engineer signs, the employer approves → participate in acceptance, confirm the completed content and compute the final cost. Signature authority: written documents signed by both parties' site management within their scope of duty are valid pricing vouchers (GB/T 50500-2024 cl. 12.2.1); the supervisor certifies facts strongly but prices weakly — priced certifications need the joint sign-off of employer, contractor and supervisor (T/CAEC 006-2024 cl. 7.2.9); a one-party signature binds only the signing party. With the 2024 code dropping the site-certification clause, off-contract work flows through three channels — variation, additional works and dayworks — and dayworks certification reports not verified in time are deemed accepted (cl. 7.5.5).

An entry card for the domain of site instructions and certified records (China's gongcheng qianzheng,