Whether the employer's site representative's signature has price-confirmation effect: authorised scope and validity of certified records
Written documents certified and signed off by the employer's site representative (the employer's on-site management personnel) within the contractually agreed duties are valid pricing vouchers (GB/T 50500-2024 Clause 12.2.1, false ones excepted). Ultra vires signatures have pending validity: where the contractor is in good faith and unaware, apparent agency applies and the employer remains liable; where the contractor knew, the employer may assert non-effectiveness but must prove it. The employer limits authority by stating in the contract the site representative's duties and signature-authority boundaries, not by after-the-fact denial.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 12.2.1
- GB/T 50875-2013 工程造价术语标准 3.4.8
- DB37/T 5028-2022 建设工程监理工作规程 2.0.2
- FIDIC 银皮书 3.3
Topic Positioning
Does the signature of the employer's site representative on site instructions and measurement/pricing documents produce price-confirmation effect? This card gives the determination framework of "valid within authorised scope, pending when ultra vires, false ones excepted".
Core Conclusions
GB/T 50500-2024 Clause 12.2.1: written documents certified and signed off by both parties' on-site management personnel within the contractually agreed duties are valid pricing vouchers for engineering pricing (except those proven false by evidence). The employer's site representative is the employer's on-site management personnel; site instructions certified and signed off within the authorised scope are the direct basis for settlement and construction cost expert assessment (judicial appraisal); GB/T 50875-2013 Clause 3.4.8 lists them among the statutory sign-off subjects of site instructions and variation records, and FIDIC Silver Book Clause 3.3 is aligned (acts within authorisation are deemed the Employer's own acts). Validity boundaries: where signed ultra vires but the contractor is in good faith and unaware, apparent agency applies — the employer remains liable with subsequent recourse; where the contractor knew of the excess, the employer may assert non-effectiveness but must prove it; records proven false are invalid. Authority is limited by stating in the contract the site representative's duties and signature-authority boundaries (e.g., "price sign-off requires the responsible person's approval"), not by after-the-fact denial.
Applicable Boundaries
Targets the employer-side site representative's signature; for cases with only the supervisor's signature and no employer's signature, see the related card (not automatically invalid; may be ratified by retrospective certification). Where the contract makes the employer's signature a validity requirement and it cannot be supplemented, the effect is limited; major price-related certified records bearing only the site representative's signature without the employer's corporate seal increase the burden of proof. Validity review proceeds in two steps: first whether the signer had authority, then whether the content is genuine.
Further Reading
GB/T 50500-2024 Clause 12.2.1 (chapter on pricing results and archive management); GB/T 50875-2013 Clause 3.4.8; DB37/T 5028-2022 Clause 2.0.2 (definition of commercial (priced) variation record); FIDIC Silver Book Clause 3.3 Delegated Persons.
Keywords
- 现场代表签字
- 工程价款确认效力
- 工程计价有效凭证
- variation record / site instruction
- 授权范围
- 签字效力