Whether a settlement agreement signed by a project manager without authorisation binds the construction enterprise: a three-layer test of agency by virtue of office, apparent agency and unauthorised agency

In most cases it binds the enterprise, but not always validly: where a project manager signs a settlement for the project in the enterprise's name, this is agency by virtue of office (Article 170 of the Civil Code), and the enterprise's internal limits on the manager's scope of authority cannot defeat a counterparty in good faith; where the manager signs beyond authority but an appearance of authority exists and the counterparty neither knew nor was negligent, apparent agency is made out and the agreement is valid (Article 172; Article 28 of Fa Shi [2022] No. 6); where there is no appearance of office or authorisation, or the counterparty is not in good faith, the agreement does not bind the enterprise unless the enterprise ratifies it (Article 171). A project manager is not the legal representative, so the rule on representation in excess of authority in Article 504 does not apply. Once the agreement takes effect for the enterprise, an application in litigation for construction cost expert assessment will not be permitted (Article 29 of Fa Shi [2020] No. 25).

Applicable Codes

  • 《中华人民共和国民法典》(主席令第45号)第170条、第171条、第172条、第188条、第504条
  • 法释〔2022〕6号《最高人民法院关于适用〈中华人民共和国民法典〉总则编若干问题的解释》第25条~第29条
  • 法〔2019〕254号《全国法院民商事审判工作会议纪要》第41条
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第29条
  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第23条,来源:https://www.court.gov.cn/fabu/xiangqing/504221.html
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第12.2.1条
  • 建建〔1995〕第1号《建筑施工企业项目经理资质管理办法》第八条
  • 《保障中小企业款项支付条例》(国务院令第802号,2025修订)第九条、第十条、第十四条、第十七条
  • 《中华人民共和国民事诉讼法》(2023修正)第67条
  • 《中华人民共和国仲裁法》(2025修订)第10条、第27条、第30条、第31条
  • 财建〔2004〕369号《建设工程价款结算暂行办法》第十五条、第十六条

Topic positioning

Determining whether a settlement agreement signed in the construction enterprise's name by a project manager without enterprise authorisation takes effect against the enterprise. A settlement agreement is a document disposing of substantive rights (confirming the settlement amount, extinguishing claims); its validity runs through the agency rules of the Civil Code, applied on three layers: status - authority - good faith of the counterparty. Once the agreement takes effect, the enterprise also loses the chance to apply for construction cost expert assessment in litigation.

Core conclusions

Up-front conclusion: it is neither 'valid once signed' nor 'void for want of authorisation'. The project manager is the post holder entrusted, on the project, to sign contracts and handle external relations in the representative capacity of the legal representative (Article 8(2) of Jian Jian [1995] No. 1: handles external relations relating to the project undertaken, in the representative capacity of the enterprise's legal representative, and signs the relevant contracts under authorisation). The manager's signing a settlement for the project in the enterprise's name falls, in principle, within the reach of agency by virtue of office, and internal limits of authority cannot defeat a good-faith counterparty; even beyond authority, the agreement remains valid once apparent agency is made out; only where the counterparty knew of the limits, where there is no appearance of office at all, or where the matter plainly exceeds the office, does it not bind the enterprise.

Layer 1: agency by virtue of office (Article 170 of the Civil Code) 'A person who performs tasks for a legal person or an unincorporated organisation, acting on matters within the scope of their authority in the name of the legal person or organisation, produces effects for the legal person or organisation. Any restriction imposed by the legal person or organisation on the scope of authority of the person performing its tasks cannot defeat a counterparty in good faith.' - So 'no authorisation' (internal non-authorisation or a capped authorisation) does not by itself defeat the agreement; the defence point is that 'the counterparty was not in good faith'.

Layer 2: apparent agency (Article 172 of the Civil Code + Article 28 of Fa Shi [2022] No. 6) Article 172: 'Where a person having no authority, exceeding authority, or whose authority has terminated still performs an act of agency, and the counterparty has reason to believe that the person has authority, the act of agency is effective.' Article 28 of Fa Shi [2022] No. 6 states two elements: '(1) an appearance of authority exists; (2) the counterparty did not know, at the time of the act, that the actor had no authority, and was without negligence.' Allocation of proof: the counterparty proves the 'existence of an appearance of authority'; the principal (the construction enterprise) proves that 'the counterparty fails the good-faith and no-negligence test'. Facts commonly constituting an appearance of authority: the manager's appointment document or labour contract, the project department seal or the enterprise seal or the special contract seal, prior documents of the same kind routinely signed by the manager and actually performed by the enterprise, and the correspondence of participation in settlement negotiations and reconciliations. Article 41 of the Minutes of the National Courts' Civil and Commercial Trial Work Conference (Fa [2019] No. 254, the Ninth Conference Minutes) sets the same review line: 'in hearing a case, the people's court shall chiefly examine whether the signatory had the power of representation or authority at the time of affixing the seal, so as to determine the validity of the contract under the rules of representation or agency'; and 'where the principal denies the validity of the contract on the grounds that the agent's authority had since lapsed, that the seal affixed was fake, or that the seal differs from the filed seal, the people's court will not support the denial'.

Layer 3: unauthorised agency (Article 171 of the Civil Code) 'Where a person having no authority, exceeding authority, or whose authority has terminated still performs an act of agency, and the principal does not ratify it, the act has no effect on the principal. The counterparty may urge the principal to ratify within 30 days of receiving notice. If the principal makes no expression, ratification is deemed refused. Before the act is ratified, a counterparty in good faith has the right to revoke, by notice. Where the act is not ratified, the counterparty in good faith has the right to request the actor to perform the obligation or to compensate the harm it has suffered; but the scope of compensation may not exceed the benefit the counterparty could have obtained had the principal ratified. Where the counterparty knew or should have known that the actor had no authority, the counterparty and the actor bear liability according to their respective fault.' Once ratification is made: under Article 29 of Fa Shi [2022] No. 6, the time the expression of ratification takes effect is determined under Article 137 of the Civil Code. Where the enterprise afterwards collects payment per the agreement, issues invoices, reconciles accounts, or uses the agreement to declare its settlement or its tax, practice treats this as implied ratification. Where unauthorised agency is not ratified, the actor bears the burden of proving that 'the counterparty knew or should have known of the lack of authority' (Article 27 of Fa Shi [2022] No. 6). Where several appointed agents exercise the authority jointly and one or some of them act without consulting the other agents, Articles 171 and 172 apply (Article 25).

Article 504 does not apply: Article 504 addresses 'a contract concluded by the legal representative of a legal person or the person in charge of an unincorporated organisation in excess of authority; except where the counterparty knew or should have known of the excess of authority, the act of representation is effective'. A project manager is not the legal representative; the path runs through Article 170 office agency or Article 172 apparent agency; only where the agreement is signed by the legal representative in person and bears the enterprise seal do Article 504 and the second paragraph of Article 41 of the Ninth Conference Minutes apply.

Affirmative and negative scenarios compared

No Scenario Conclusion Basis
1 Appointment document, labour contract or construction contract names them project manager for the project; the power of attorney permits signing settlement documents Binds the enterprise: office agency within the scope of authority Civil Code Art 170(1); Jian Jian [1995] No. 1 Art 8(2)
2 No written authorisation, but the manager has long signed measurement, site instruction record and reconciliation documents in the project department's name, and the enterprise performed them all Binds the enterprise: apparent agency Civil Code Art 172; Fa Shi [2022] No. 6 Art 28; Ninth Conference Minutes Art 41
3 The agreement bears the project department seal (or the enterprise seal, or the special contract seal) and the counterparty verified identity Binds the enterprise: appearance of authority exists; the authenticity or filing of the seal does not decide validity Civil Code Arts 170, 172; Ninth Conference Minutes Art 41
4 The enterprise afterwards collects payment per the agreement, issues invoices, reconciles accounts, or declares settlement or tax on the basis of the agreement Binds the enterprise: implied ratification by conduct Civil Code Art 171(1); Fa Shi [2022] No. 6 Art 29
5 The agreement only confirms facts such as quantities, amounts paid and the construction period, disposing of no substantive rights Binds the enterprise: factual confirmation within the scope of duties Civil Code Art 170(1); GB/T 50500-2024 Art 12.2.1
6 The signer is not the project manager of the project (ordinary crew member, resigned, removed), with no authorisation document and no project department seal Does not bind the enterprise: unauthorised agency, unless ratified Civil Code Art 171(1)
7 The enterprise has notified the limits in writing, or the contract expressly requires enterprise seal plus the legal representative's signature for settlement, yet the counterparty still signs with the manager personally Does not bind the enterprise: the counterparty is not in good faith and the limits can be set up against it Civil Code Art 170(2); Fa Shi [2022] No. 6 Art 28(2)
8 The agreement disposes of rights outside the project (claims on other projects, guarantee of the enterprise's debts, blanket waiver of the priority right to payment) or settles at a plainly unreasonable low price Does not bind the enterprise: beyond 'matters within the scope of authority' Civil Code Arts 170(1), 171
9 One of several appointed agents signs the settlement for the enterprise without consulting the others Handled separately under the rules of unauthorised or apparent agency Fa Shi [2022] No. 6 Art 25

The key consequence once effective - no more construction cost expert assessment: Article 29 of Fa Shi [2020] No. 25: 'Where the parties have already reached an agreement on the price settlement of the construction project before litigation, and one party applies in litigation for expert assessment of the construction cost, the people's court shall not permit it.' This is the most substantive cost of the agreement 'binding the enterprise': once the agreement is effective against it, the enterprise can neither deny the amount nor recalculate it through assessment.

Validity of pricing vouchers: Article 12.2.1 of GB/T 50500-2024: 'The employer and the contractor shall agree in the contract the scope of duties of their respective on-site management personnel; written documents signed and confirmed by the on-site management personnel of both parties within their scope of duties are valid vouchers for construction pricing, except where other valid evidence exists or verification proves them to be false.' - Once the contract agrees the signer's scope of duties, voucher effect arises; the corollary is that the contract should clearly define the scope of duties and the boundaries of signing authority of on-site management personnel.

Defence and remedy points: To claim that the agreement does not bind the enterprise, allocate proof under Article 67 of the Civil Procedure Law ('a party has the duty to provide evidence for its own claims'), applying to the court to collect evidence where necessary; against an effective agreement only invalidity, revocation or a separate claim for damages lies, noting the three-year limitation of Article 188 of the Civil Code (running from when the party knew or should have known of the harm and of the obligor, twenty years at most). On dispute resolution, an arbitration agreement exists independently: whether the contract is formed, varied, ineffective, terminated, revoked or void does not affect the validity of the arbitration agreement (Article 30 of the Arbitration Law); an arbitration agreement must contain the intent to arbitrate, the matters to be arbitrated and the chosen arbitration institution (Article 27); objections to validity must be raised before the first hearing of the tribunal, and where one party asks the arbitration institution to decide and the other asks the court, the court decides (Article 31); an award is final (Article 10).

Payment-timing defences: The enterprise cannot fob off small and medium-sized enterprise (SME) counterparties with 'the internal payment process is unfinished', 'the legal representative has changed' or 'awaiting completion filing and the final-accounts audit' - Article 14 of the Regulation on Ensuring Payment to SMEs (State Council Decree No. 802, 2025 revision) prohibits refusing or delaying payment to SMEs on the grounds of a change of the legal representative or the principal person in charge, performance of internal payment procedures, or, absent contract agreement, awaiting completion filing or the final-accounts audit; Article 9: government organs and public institutions pay within 30 days of delivery, or at most 60 days where the contract provides otherwise; large enterprises pay within 60 days, and may not agree to condition payment on receipt of third-party payment or to pay in proportion to third-party payment progress. Article 15: where part is in dispute but performance of the other part is unaffected, the undisputed part must be paid promptly.

Applicable boundaries

  • This card covers only the effect of a project manager's signature on settlement agreements on the construction enterprise side; the effect of the signature of the employer's on-site representative is judged by separate rules.
  • 'Without authorisation' does not mean void on the office-agency path - the crux is whether the matter falls within the scope of authority and whether the counterparty is in good faith and without negligence, not the enterprise's unilateral statement.
  • Article 504 of the Civil Code does not apply: a project manager is not the legal representative. Only the legal representative or a person authorised by it affixing the enterprise seal engages the representation rules (representation effective unless the counterparty knew or should have known of the excess of authority).
  • Matters beyond 'the scope of authority' (disposing of rights outside the project, guaranteeing the enterprise's debts, blanket waiver of the priority right to payment and the like) are not automatically validated by apparent agency.
  • The no-assessment rule (Article 29 of Fa Shi [2020] No. 25) is confined to agreements 'reached before litigation' and presupposes the agreement's own validity; an agreement that is void, revocable, or only partly agreed does not qualify.
  • The payment-period rules (30/60 days) apply only to transactions between government organs, public institutions or large enterprises and SMEs; where laws, administrative regulations or other state provisions provide otherwise, those prevail; for settlement by construction stage or periodic settlement, the payment period runs from the date the parties confirm the settlement amount (Article 9 of the Regulation).
  • Article 15 of Cai Jian [2004] No. 369: site instruction records signed by the on-site representatives authorised by both parties, and claim costs agreed by negotiation, must be truthfully handled in the final account, and 'their validity must not be altered by a mid-course change of the on-site representatives of the two parties'; Article 16: where the employer raises no objection within the prescribed or agreed period after receiving the final-account report and the complete documents, it is deemed to have approved them.
  • Currency of rules: Fa Shi [2026] No. 12 (Interpretation II) takes effect on 30 June 2026; its Article 23 provides that first-instance cases newly accepted after that date apply it, and prior inconsistent judicial interpretations yield to it; confirm the temporal boundary applicable to the conduct before citing the older rules.

Further reading

  • Civil Code of the PRC (Presidential Decree No. 45), Article 170 (office agency), Article 171 (unauthorised agency / urging ratification / fault-based liability), Article 172 (apparent agency), Article 188 (three-year limitation), Article 504 (representation in excess of authority).
  • Fa Shi [2022] No. 6, SPC Interpretation on Several Issues Concerning the Application of the General Part of the Civil Code, Part VI Agency: Article 25 (concurrent agents), Article 27 (burden of proof in unauthorised agency), Article 28 (the two elements of apparent agency and allocation of proof), Article 29 (the effective time of ratification).
  • Fa [2019] No. 254, Minutes of the National Courts' Civil and Commercial Trial Work Conference, Article 41 [legal effect of affixing seals]: examine the signatory's power of representation or authority at the time of sealing.
  • Fa Shi [2020] No. 25 (Interpretation I), Article 29: a settlement agreement reached before suit bars construction cost expert assessment in litigation.
  • Fa Shi [2026] No. 12 (Interpretation II), Article 23 (effective 30 June 2026; handling of conflicts between old and new interpretations), original text at the SPC website: https://www.court.gov.cn/fabu/xiangqing/504221.html
  • GB/T 50500-2024 Standard for Bill of Quantities Pricing of Construction Works, Article 12.2.1 (signatures of both parties' on-site management personnel within their duties are valid pricing vouchers).
  • Jian Jian [1995] No. 1, Measures for the Administration of Project Manager Qualification of Construction Enterprises, Article 8 (the manager's management powers and representative status).
  • Regulation on Ensuring Payment to SMEs (State Council Decree No. 802, 2025 revision), Articles 9, 10, 14, 15 and 17 (interest on overdue payment: the agreed rate may be no lower than the 1-year LPR at the time of contracting; absent agreement, 0.05% per day).
  • Civil Procedure Law (2023 revision), Article 67 (burden of proof; court collection of evidence).
  • Arbitration Law (2025 revision), Articles 10, 27, 30 and 31 (finality of the award; requirements, independence and the objection period for arbitration agreements).
  • Cai Jian [2004] No. 369, Interim Measures for the Settlement of Construction Project Payments, Articles 15 and 16 (a mid-course change of on-site representatives does not alter the validity of site records; failure to object in time is deemed approval).

Keywords

  • 项目经理
  • 职务代理
  • 表见代理
  • 无权代理
  • 工程结算协议
  • 代理权外观
  • 追认
  • 越权代表