Four-axis distinction among variations, additional works, dayworks and claims under GB/T 50500-2024 (triggering events / procedure / time limits / pricing basis) and the fallback positioning of claims

GB/T 50500-2024 clause 8.1.1 lists contract price adjustment matters in eleven categories (including dayworks, variations, additional works and claims) and does not list 'site instruction records' separately - matters signed and certified during construction must be priced through one of these four channels. Boundaries of the four channels: variation = a change of content or conditions within the scope of the contract works (term 2.0.28); additional works = physical works outside the contract scope (2.0.30); dayworks = minor work unsuited to pricing under the measurement and pricing rules (2.0.16; clause 7.5.2 lists ten situations); claim = the fallback channel - clause 8.11.1 provides that only events 'not within the adjustment scope of sections 8.2 to 8.10' are handled as claims, and 'where the price adjustment of an event has already been calculated under the contract price adjustment provisions (excluding claims), no further claim shall be calculated'.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 Ch. 2 术语 2.0.16、2.0.28、2.0.30
  • GB/T 50500-2024 Ch. 7 合同工程计量 7.4.1、7.5.1、7.5.2、7.5.5、7.6.1
  • GB/T 50500-2024 Ch. 8 合同价款调整 8.1.1、8.6.2、8.9.1、8.9.2、8.9.6、8.9.8、8.10.1、8.10.2、8.10.3、8.11.1、8.11.3、8.11.5、8.11.7、8.11.9、8.11.10

Topic positioning

This card explains, under the GB/T 50500-2024 system (China national pricing standard for BOQ), the dividing criteria and requirement differences of the four contract price adjustment channels - variations, additional works, dayworks and claims - answering the common misuse point of 'which channel a given event goes through, without double pricing'. It also explains where 'site instruction records' sit in this standard.

Core conclusions

1. Channel list: the eleven categories of clause 8.1.1 'During performance of the contract, the employer and the contractor may adjust the relevant contract price per chapter 7 and this chapter where the following matters occur: 1. errors and omissions in the BOQ; 2. provisional sums; 3. provisional prices; 4. main contractor's attendance and coordination provisions; 5. dayworks; 6. changes in costs; 7. changes in laws, regulations and policies; 8. variations; 9. additional works; 10. claims; 11. other adjustment matters agreed by the employer and the contractor.' This list does not set 'site instruction records' as a separate price adjustment channel; matters certified during construction must be carried and priced, by their nature, under dayworks, variations, additional works or claims.

2. Four-axis comparison table

Requirement axis Variation (section 8.9) Additional works (section 8.10) Dayworks (measurement 7.5 + pricing 8.6) Claims (section 8.11)
Triggering events Term 2.0.28: a change, approved by the employer, to the contract works in 'working content, contract drawings, contract specification, position and dimensions, construction sequence or timing, construction conditions, contract terms or other characteristics', including additions, omissions, cancellations, substitutions and changes of materials - within the scope of the contract works Term 2.0.30: physical works requested by the employer and accepted by the contractor that fall outside the scope of the works agreed in the contract and (or) its completion and delivery requirements - an independent physical work outside the scope Term 2.0.16: performing minor items or work raised by the employer that are 'not suitably priced under the measurement and pricing rules agreed in the contract', priced at contract rates on the basis of employer-confirmed actual consumption of labour days, material quantities and machine-shifts of construction plant; clause 7.5.2 lists ten applicable situations (added or substituted work that cannot be measured by drawings, variation or measurement rules; short-duration, sporadic, limited-scope, small-quantity work; abnormal operations caused by extreme changes in working conditions; repair of damage to other works caused by emergency works; opening up concealed works at the employer's request where testing proves compliance with the contract; repairing affected surrounding works after another contractor finishes its work; replacing materials made necessary by the delay caused when the employer suspends (stops) the works; cleaning and clearing outside the contract scope specially required by the employer; test runs required by the employer outside the contract scope; repair of minor works not caused by the contractor) Clause 8.11.1: events not due to a party's own fault that fall outside the adjustment scope of sections 8.2 to 8.10, cause it economic loss and cost increase and (or) delay (or extension) of duration, and for which the other party to the contract bears the obligation - the fallback channel
Procedure Clause 7.4.1: with variation instructions issued or confirmed by the employer, and comparing actual construction drawings against contract drawings, the differing parts are the variation items; clause 8.9.6: where changes of substance in scope, duration, quality or contract specification cause changes in preliminaries, the disadvantaged party proposing to adjust preliminaries submits, before implementation, the proposed scheme to the other party for review, detailing the comparison with the preliminary items of the original scheme, executed after confirmation by both parties; clause 7.6.1: where rework or material write-off is caused, a written rework confirmation request must be raised Clause 8.10.2: before implementation, submit the project execution plan or implementation scheme, the construction schedule, and the priced offer for the costs sought (including the divisional and sub-divisional BOQ and the preliminaries BOQ) to the employer for review and determination within a reasonable time Clause 7.5.1: where the contractor considers dayworks rather than measurement under sections 7.2 to 7.4 appropriate, it shall propose to the employer within the time agreed in the contract, and the employer shall reply within the agreed time; clause 7.5.5: the employer notifies the verified result in writing within the agreed time and reviews the dayworks certification report Clause 8.11.3, five steps: (1) Notice of Claim -> (2) claim report -> (3) costs and extension of time claimed together -> (4) for continuing effect, submit successive Notices of Claim at intervals or reasonable intervals listing cumulative claimed costs / duration -> (5) after the event ends, submit the final claim report; clause 8.11.5: the employer reviews the Notice of Claim, may request further documents, and replies in writing with its handling opinion
Time limits Clause 8.9.6 stresses submission of the scheme 'before implementation'; rework confirmation requests per the time agreed in the contract (7.6.1) Clause 8.10.2 stresses submission 'before implementation', with the employer determining 'within a reasonable time' Clause 7.5.1: if the contractor fails to propose within the agreed time, it is deemed to have waived the request for measurement on a dayworks basis; if the employer fails to reply within the agreed time, it is deemed to have agreed to the contractor's dayworks measurement As agreed in the contract; where the contract is silent: Notice of Claim 28 days, claim report 28 days, successive Notices of Claim no more than 28 days apart (or at reasonable intervals), final claim report 28 days (8.11.3); the employer may request further documents within 14 days and reply in writing within 28 days, failing which 'the matter may be handled per the contract, and where the contract is silent the contractor's claimed entitlement may be deemed accepted' (8.11.5); 'where the aggrieved party fails to give notice within the agreed time after the event, the relevant claim may be deemed waived except as otherwise agreed in the contract or provided by laws and regulations'
Pricing basis Clause 8.9.1: where item additions or quantity changes are no more than 15% (15% included), five bands fix the all-in unit rate - same construction conditions plus same item descriptions: the corresponding contract rate; same conditions plus similar descriptions, or similar conditions plus same descriptions: the all-in rate derived by converting and adjusting the contract rate of a similar item; same conditions plus different descriptions, or different conditions plus same descriptions: a market-reasonable all-in rate negotiated by reference to the pricing rules and tender pricing level of similar items; different conditions plus different descriptions: negotiated by reference to all-in rates of similar BOQ items of works of the same type; where reducing or cancelling items materially changes construction conditions, priced by negotiation on the specifics, market prices, the contract rate rules and the tender pricing level. Clause 8.9.2: where the quantity change exceeds 15% (15% excluded), for increases the contract rate and the new all-in rate may be reasonably reduced on the basis of 8.9.1 plus procurement price discounts on labour and materials; for decreases they may be reasonably increased in light of lost procurement discounts. Clause 8.9.8: where the employer cancels work not due to the contractor and the contractor's costs or profit are not covered in other paid or payable items or substitute work, the employer shall compensate the costs incurred and reasonable anticipated profit Clause 8.10.1: priced per the BOQ itemisation requirements, quantity take-off rules and supplementary rules of the national and industry quantity take-off standards agreed in the contract, the contract rates and the tender pricing level, or the measurement and pricing rules are renegotiated and a contract or supplementary agreement for the additional works is signed; preliminaries shall cover the cost of extended use of, or newly added, preliminary items. Clause 8.10.3: where the all-in rate of additional works is derived by converting contract rates of related BOQ items within the contract works, the adjustment is fixed by the price effect of the pricing-related differing factors Clause 8.6.2: measured per section 7.5 and priced at the all-in rates of the dayworks BOQ items in the contract BOQ, i.e. 'calculated quantity x the corresponding dayworks contract rate in the contract BOQ'; clause 7.5.5: the site labour, materials and construction plant quantities in the dayworks certification report are the measured quantities, excluding the contractor's own site management personnel and plant already on site, which are not measured Clause 8.11.9: losses cover the labour, material, construction plant and water and power consumption losses caused by suspension, standby, reduced output and duration extension; the direct cost of cost changes caused by contract duration adjustment (except where adjusted under 8.7.4); preliminaries for suspending, resuming and maintaining the site; direct costs of rework, demolition, alteration and repair and the loss of written-off materials; extra inspection and testing costs; losses from contract price not paid as agreed; effects of suspension, interruption or stoppage caused by unearthing cultural relics and historic sites; other provable losses and VAT; and the reasonable duration of delay; economic losses caused by government competent authorities are borne by each party itself with the duration extended accordingly; clause 8.11.10: for eight types of event due to the employer's fault (re-letting work to another contractor; late supply of drawings or site; employer-supplied materials off-standard, late or delivered to a changed place; causing setting-out errors and rework; extra site restrictions, late approvals or interference with the construction sequence; causing delay, suspension or failure to resume on time; occupying the works before completion; causing defect repair within the defects liability period), profit may be claimed in addition to the loss; clause 8.11.7: the work corresponding to a claim for extension of time must be work on the critical path or work that changes the critical path, each claim event is assessed independently and must not include cost claims for delay to later works caused by earlier delay

3. The most misused rule: no double pricing Clause 8.11.1 states that 'events within the adjustment scope of sections 8.2 to 8.10 of this standard shall be adjusted under the corresponding provisions, and events outside that scope may be handled under this section', and says outright: 'where the price adjustment of an event has already been calculated under the contract price adjustment provisions (excluding claims), no further claim shall be calculated.' That is, an event that qualifies as a variation, additional works or dayworks must not have a claim stacked on top; claims take only the events the previous nine sections do not reach. The clause also describes the nature of a claim as 'economic compensation, not punishment', and states that 'the contractor may claim against the employer, and the employer may also claim against the contractor' - a two-way right.

Applicability boundaries

  • The clauses above belong to GB/T 50500-2024 (a recommended standard); where the contract provides otherwise, the contract prevails; the 28-day and 14-day periods are fallback limits 'where the contract is silent' - where the contract has agreed periods, they govern.
  • The 15% boundary applies only to quantity changes under re-measurable (unit-rate) contracts (8.9.1 / 8.9.2); under lump-sum contracts, errors and omissions in the BOQ are not adjusted (7.4.1).
  • Dayworks apply to minor work 'not suitably priced under the agreed measurement and pricing rules' and must not be used to dodge normal BOQ measurement (routine work outside the ten situations of 7.5.2 is still measured under sections 7.2 to 7.4).
  • Profit within claims may be sought only in employer-fault situations (8.11.10); force majeure and causes attributable to government competent authorities do not qualify.
  • This card compares clauses; for a specific project, check the particular conditions of the contract for different periods and procedures.

Further reading

  • GB/T 50500-2024, chapter 2 terms: 2.0.16 (dayworks), 2.0.28 (variation), 2.0.30 (additional works)
  • Chapter 7, measurement of the contract works: 7.4.1 (variation measurement distinguished from BOQ errors), 7.5.1 / 7.5.2 / 7.5.5 (proposing dayworks, the ten situations, certification review), 7.6.1 (rework measurement)
  • Chapter 8, adjustment of the contract price: 8.1.1 (eleven adjustment matters), 8.6.2 (dayworks pricing), 8.9.1 / 8.9.2 (the 15% boundary and the five bands of all-in unit rates), 8.9.6 (preliminaries adjustment scheme submitted in advance), 8.9.8 (compensation for loss and anticipated profit on cancelled work), 8.10.1 / 8.10.2 / 8.10.3 (additional works pricing, review, rate conversion), 8.11.1 (claims as fallback and the bar on double calculation), 8.11.3 / 8.11.5 (claim procedure and the 28-day / 14-day periods), 8.11.7 (critical path and independent assessment for claims for extension of time), 8.11.9 / 8.11.10 (scope of loss and situations where profit is claimable)
  • Comparative reading: the corresponding clauses of chapter 9 of GB 50500-2013 (withdrawn) show the 2024 edition's orientation of channelling certified matters into the dayworks / variations / additional works / claims routes.