Recording quantities for site instructions and certified records: a three-stage closed-loop procedure, recording elements, and daywork daily reporting requirements

Quantity recording for site instructions and certified records follows the three-stage closed loop of "pre-work survey -> in-process measurement -> post-completion acceptance": before implementation, survey and record original conditions as the increment baseline; when occurring, measure and record promptly and preserve imagery; after completion, accept and confirm actual quantities. Each certified record must contain position, dimensions, quantity, materials, and a logically clear calculation formula; dayworks report daily details of personnel/materials/machinery and submit a daily summary after continuing work ends; certified records are archived one-to-one with original records, imagery, and acceptance proof.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准
  • DB37/T 5028-2022 建设工程监理工作规程
  • T/CAEC 006-2024 建筑工程监理文件资料管理标准

Topic Positioning

How quantities should be recorded for site instructions (variation records): the complete operational method from the three-stage procedure of "pre-work survey -> in-process measurement -> post-completion acceptance", site instruction recording elements, and the dayworks daily-reporting special case to evidence-chain archiving.

Core Conclusions

  1. Three-stage closed-loop recording: survey the site before implementation, measuring and recording original conditions as the increment baseline; when work occurs, measure and record quantities promptly and preserve imagery; after completion, participate in acceptance, confirm actual completed content and quantities, and compute the final cost of the site instruction (T/SDJZXH 004.1-2022, Clause 10.6.3).
  2. Site instruction recording elements: position, dimensions, quantity, materials, etc., with a logically clear calculation formula and photos/drawings; records giving only a result number without a calculation process will always be returned in review (DB37/T 5028-2022, Clause 6.3.3).
  3. Dayworks special case: report to the employer daily on work name/content/quantity, personnel name/trade/grade/hours, material name/category/specification/brand/quantity, and machinery model/quantity/shifts used; for continuing work not completed within a day, submit the daily-record summary within the agreed time after it ends; quantities exclude the contractor's own on-site management personnel and machinery already on site (GB/T 50500-2024, Clauses 7.5.3~7.5.6).
  4. Evidence-chain archiving: quantity site instructions attach quantity calculation details, approved change orders or claim documents, on-site measurement imagery, and acceptance certificates (T/CAEC 006-2024, Clause 7.2.8); settlement measures and prices per quantities confirmed by both parties (GB/T 50500-2024, Appendix E, Table E.4.4).

Applicable Boundaries

Applies to site instruction measurement related to contract price adjustment during construction. Out-of-scope site instructions (foreseeable by the contractor but unraised, work not per drawings, costs from violations) are excluded; site instruction measurement uses the "actually occurred" caliber, distinct from the normal "measure per drawings" principle — only site instruction items not defined in design (quicksand, concealed works, etc.) are measured by actual/site instruction.

Further Reading

See GB/T 50500-2024 "Standard for valuation of construction works by bill of quantities" Clauses 7.5.3~7.5.6 and Appendix E Table E.4.4; T/SDJZXH 004.1-2022 "Standard for supervision work of urban rail transit works" Clauses 10.6.1~10.6.3; DB37/T 5028-2022 "Rules for construction supervision work" Clauses 6.3.2~6.3.3; T/CAEC 006-2024 "Standard for management of supervision documents of building works" Clauses 7.2.8~7.2.9.