Confirmation of quantities added by design changes: basis, measurement rules, supervision certification and sign-off procedure, and dispute handling

The varied quantity = the difference portion identified by comparing the variation instruction issued or confirmed by the employer, together with the actual construction drawings, against the contract drawings; it is computed per the contractual measurement rules (or, absent agreement, per national/industry standards). Certification and sign-off procedure: the contractor submits for review -> the professional supervision engineer reviews (upon objection, joint re-check or sampling re-measurement) -> site survey and measurement before certification and sign-off, with records and photographs made as the work proceeds -> acceptance confirmation -> the chief supervision engineer certifies and signs off and reports to the employer for approval. Costs of foreseeable items not raised in advance, changes made without approval formalities, and costs attributable to the contractor itself may not be certified and signed off; incomplete submission documents, works not accepted as compliant, and quantities beyond the measurement standards are not measured. Once the quantity is confirmed, the all-in unit rate is adjusted on a linked basis at the 15% threshold.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准(通用篇)
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • GB/T 51262-2017 建设工程造价鉴定规范

Topic Positioning

How quantities added by design changes are confirmed: definition of the varied quantity, measurement rules, certification and sign-off procedure, situations in which confirmation is not permitted, and dispute handling.

Core Conclusions

  1. Definition: the varied quantity = the difference portion between the variation instruction issued or confirmed by the employer, together with the actual construction drawings, and the contract drawings (GB/T 50500-2024 Clauses 7.4.1, 7.4.2); a verbal instruction (to be confirmed in writing) is not a pricing voucher and must be confirmed in writing (Clause 12.2.2).
  2. Measurement: per the contractual rules; absent agreement, per the national measurement standards; where the state has not prescribed, per industry/local standards (T/ZBD 100.4-2023 Clause 4.3.1; GB/T 51262-2017 Clause 5.5.1).
  3. Procedure: the contractor submits for review -> the supervision engineer reviews (upon objection, joint re-check or sampling re-measurement) -> survey before certification and sign-off, with photographs recorded as the work proceeds -> acceptance confirmation -> the chief supervision engineer certifies and signs off and reports to the employer for approval (T/SDJZXH 004.1-2022 Clauses 7.3.2, 10.6.1, 10.6.3).
  4. Red lines: foreseeable items not raised in advance, foreseeable preliminaries, scheme changes made without approval formalities, and costs attributable to the contractor itself may not be certified and signed off; incomplete documents, works not accepted as compliant, and quantities beyond the measurement standards are not measured.
  5. Once the quantity is confirmed, unit rates are adjusted at the 15% threshold (<=15%: use the contract unit rate / conversion / negotiation; >15%: downward adjustment for increases and upward adjustment for decreases).

Applicable Boundaries

Applies to variation measurement and settlement at the construction-drawing bidding stage; BOQ errors / omissions in lump-sum contracts are not adjusted. Where certification and sign-off have not been obtained, tiered appraisal applies per Clauses 4.6.3, 4.6.6; specialized fields such as railway have separate variation classification and approval measures.

Further Reading

GB/T 50500-2024 Sections 7.4, 8.2, 8.9, 12.2.2; T/SDJZXH 004.1-2022 Sections 7.3, 10.6; T/ZBD 100.4-2023 Sections 4.3, 4.6; GB/T 51262-2017 Sections 5.5, 5.9.