Design variations in construction works: definition, distinction from variation and site instruction / variation record, and the basic procedure

A design variation is the activity of the design organization modifying, perfecting or optimizing the original design content already approved (through construction-drawing design review); the preparing entity can only be the design organization — any of the employer, designer, contractor or supervisor may propose it, and after the employer's consent the design organization issues it as drawings or a designer's change instruction. A design variation is a subcategory of variation, distinct from the site instruction / variation record (a written confirmation record that does not change the design documents). Procedurally it must be organized and reviewed by the Engineer (chief supervising engineer under China's supervision regime); variations touching safety, environmental protection or energy efficiency require re-commissioning of construction-drawing review.

Applicable Codes

  • CJJ/T 91-2017 风景园林基本术语标准
  • DB37/T 5164-2020 建筑施工现场管理标准
  • DBJ41/T 208-2018 建设工程监理工作标准
  • DB23/T 3061-2021 住宅工程质量通病防控规范
  • GB/T 50358-2017 建设项目工程总承包管理规范
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引

Topic Positioning

This card answers "what is a design variation in construction works": the three definition elements, the conceptual boundaries versus variation / site instruction and variation record, and the basic procedure from proposal to issue. It applies to the general situation of variations proposed by any party before or during construction.

Core Conclusions

A design variation is the design organization's activity of modifying, perfecting or optimizing original design content already approved (through construction-drawing design review) (CJJ/T 91-2017 clause 8.2.4; DB37/T 5164-2020 clause 2.0.5). Three core elements: (1) the object is approved design documents; (2) the preparing entity can only be the design organization — any of the employer, designer, contractor or supervisor may propose, but after the employer's consent the design organization issues it as drawings or a designer's change instruction; (3) the deliverable is a designer's change instruction / variation drawings. Conceptual boundaries: a variation is any change of materials, process, function, construction, dimensions, technical indicators, quantities or construction methods (DBJ41/T 208-2018 clause 2.0.18), and design variations are only the class "originating from changes in design documents"; a site instruction / variation record is the written confirmation record by employer and contractor of actually occurring matters and does not change the design documents themselves — the two must not be conflated. Procedural points: variations the design organization proposes itself for original design defects are prepared directly; variations proposed by the employer/contractor must be submitted to the Engineer (chief supervising engineer under China's supervision regime) to organize review by professional supervising engineers, and after consent the employer transmits them to the original design organization for preparation (DB23/T 3061-2021 clause 5.1.4); those involving safety, environmental protection or energy efficiency must be re-submitted to the original construction-drawing review agency for review; the design team should assess technical feasibility, safety, applicability and cost/schedule impact, and the assessment should then be checked by the design manager and approved by the project manager (GB/T 50358-2017 clause 5.4.3). Once a variation is established (e.g. the employer changes baselines, levels, positions, dimensions or quality standards), the contract price is adjusted in accordance with the contract (T/ZBD 100.4-2023 clause 4.6.1).

Applicable Boundaries

This card is a general terminology and procedure framework. Specific variation classification, approval authority and price-adjustment margins follow industry-specific measures and the project contract (e.g. railway variation-design measures; GB/T 50500-2024 section 8.9's 15% threshold rule). It does not cover downstream topics: variation pricing details, disposal of construction schemes after variation, expert panel re-verification for sub-divisional works involving significant hazards, etc.

Further Reading

CJJ/T 91-2017 "Standard for basic terminology of landscape architecture" 8.2.4; DB37/T 5164-2020 "Standard for construction site management of buildings" 2.0.5; DBJ41/T 208-2018 "Standard for supervision of construction works" 2.0.18; DB23/T 3061-2021 "Code for prevention and control of common quality defects of housing works" 5.1.4; GB/T 50358-2017 "Code for management of engineering general contracting of construction projects" 5.4.3; T/ZBD 100.4-2023 "Guidelines for construction cost authentication practice" 4.6.1.