Graded handling of whether a construction method statement may remain in use after a design change: briefing-only revision / revision and re-approval / re-compilation and re-verification by the expert panel for sub-divisional works involving significant hazards
One judgment criterion: whether the technical premises of the original scheme (construction method, process parameters, safety conditions) still hold after the change. Graded handling: (1) local changes not touching the construction method -> the original scheme remains valid; only revise and supplement the technical briefing and re-brief; (2) changes affecting the construction method/safety conditions -> revise the scheme and re-approve under the original approval authority, with the Engineer re-organizing review and sign-off before reporting to the employer; (3) where a dedicated method statement for sub-divisional works involving significant hazards genuinely requires adjustment due to design change -> after revision, it shall be re-reviewed and go through expert panel review as prescribed (T/XCIA 3-2023 Clause 4.1.6); major adjustments to works over the prescribed scale that were originally subject to expert panel review must undergo re-verification by the expert panel. Mandatory bottom line: no party may modify the design without authorization; where modification is genuinely needed, the design organization issues the change documents and the original approval procedure is followed (GB 55032-2022 Clause 2.0.5).
Applicable Codes
- GB/T 50502-2009 建筑施工组织设计规范
- GB 55032-2022 建筑与市政工程施工质量控制通用规范
- T/XCIA 3-2023 危险性较大的分部分项工程施工安全管理规程
- DB37/T 5028-2022 建设工程监理工作规程
- DB37/T 5164-2020 建筑施工现场管理标准
- DB11/T 1745-2020 建筑工程施工技术管理规程
- T/HAEC 003-2020 工程监理资料管理标准化与信息化工作指南(房屋建筑工程)
- GB 51114-2015 露天煤矿施工组织设计规范
- 住建部令第37号 危险性较大的分部分项工程安全管理规定
Topic Positioning
The compliance framework for whether the original construction method statement (project execution plan, construction method statement, dedicated method statement for sub-divisional works involving significant hazards) may continue to be used after a design change, and how to handle it in grades.
Core Conclusions
One criterion: whether the technical premises of the original scheme (construction method, process parameters, safety conditions) still hold after the change. (1) Local changes not touching the construction method — the original scheme remains valid; only revise and supplement the technical briefing and re-brief; (2) Changes affecting the construction method or safety conditions — revise the scheme and re-approve under the original approval authority; (3) Dedicated method statement for sub-divisional works involving significant hazards — where adjustment is genuinely needed due to a design change, re-review and expert panel review are carried out after revision; ordinary adjustments are re-submitted under the original dual sign-off procedure; major adjustments to schemes originally subject to expert panel review require re-compilation and re-verification by the expert panel, and construction must not proceed before they pass. Bottom line: the design must not be modified without authorization; where modification is genuinely needed, the design organization issues the change documents and the original approval procedure is followed; after the change takes effect, the content of the original scheme that conflicts with it lapses automatically.
Applicable Boundaries
Applies to building and municipal works; where local detailed rules are stricter, they govern; analogous requirements for mining works are set out in GB 51114-2015; where funds or duration change alongside, the employer shall adjust them synchronously per the contract. This card does not cover adjustment of the contract price.
Further Reading
GB/T 50502-2009 Clause 3.0.6 (dynamic management of the project execution plan); GB 55032-2022 Clause 2.0.5; T/XCIA 3-2023 Clause 4.1.6 (re-review and expert panel review of dedicated method statements); DB37/T 5028-2022 Clause 4.8.2; DB11/T 1745-2020 Clauses 6.2.5, 7.2.6; T/HAEC 003-2020 Clause 10.29.2; MOHURD Order No. 37.