Loss handling for demolition of completed works caused by design changes: the three-way method (completed works paid as measured + demolition costs priced separately + losses claimed)

Demolishing completed works for a design change is itself a variation (GB/T 50500-2024 Clause 2.0.28 includes "demolition and removal from site of completed works"), with losses handled by the three-way method: (1) portions completed and of accepted quality before demolition are paid per the contractual measurement rules (Clause 7.4.1); (2) demolition and debris removal are re-measured and re-priced as new variation BOQ items per Clauses 8.9.1/8.9.2; (3) scrapped materials, direct rework/reconstruction costs, idle (standby) costs of labour and plant, plant standing time, and preliminaries for suspension and resumption are claimed per Clause 8.11.9, with profit additionally claimed per Clause 8.11.10 where the cause is the employer's responsibility. The 28-day claim procedure is the red line; demolition costs arising from the contractor's own causes (quality failing acceptance) are borne by the contractor (Clause 8.11.18).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • DB11/T 382-2017 建设工程监理规程

Topic Positioning

Handling of completed-work payments, demolition/removal, and loss compensation when completed works are demolished due to a design change (or employer instruction): characterization, the three-way cost method, claim procedures, and responsibility boundaries.

Core Conclusions

Demolishing completed works is itself a variation — the definition in GB/T 50500-2024 Clause 2.0.28 includes "demolition and removal from site of completed works", and it shall be handled by the variation procedure, not as quality rework. Three-way loss method: (1) portions completed and of accepted quality before demolition are paid per the contractual measurement rules (Clause 7.4.1), not invalidated by the demolition; (2) demolition and debris removal are new variation BOQ items re-priced per Clauses 8.9.1/8.9.2 (with a 15% increase/decrease in quantity as the threshold), and recovery of old materials is deducted as agreed; (3) scrapped materials, direct rework/reconstruction costs, idle (standby) costs of labour and plant, plant standing time, and preliminaries for suspension and resumption are claimed per Clause 8.11.9, with profit additionally claimable per Clause 8.11.10 where the cause is the employer's responsibility. Procedural red line: written notice of intention within 28 days, claim report within a further 28 days, continuing influence reported every 28 days, failing which the claim is deemed waived (Clause 8.11.3); verbal instructions do not constitute a basis for valuation.

Applicable Boundaries

Applies only to demolition not caused by the contractor; demolition-and-rebuild costs for contractor work failing quality acceptance are borne by the contractor (Clause 8.11.18). Contract provisions prevail. Keep photographic evidence before demolition, and fix the scope and old-material condition by site instruction / variation record.

Further Reading

GB/T 50500-2024 Clauses 2.0.28, 7.4.1-7.4.4, 8.9.1-8.9.7, 8.11.3, 8.11.9-8.11.10, 8.11.18; for the basis of construction cost expert assessment where there is no certified evidence see T/ZBD 100.4-2023 Section 4.6; variations proposed by the contractor for its own construction convenience are borne at its own cost (DB11/T 382-2017).