28 days
- 01
Splitting the remedy paths and procedural requisites when material prices rise: whether to go first for contract price adjustment (price adjustment for cost fluctuation) or for a works claim; the time limits, written requisites and negotiation sequence of each path; and the consequences of a missed or wrong procedure (GB/T 50500-2024 cl. 8.7, cl. 8.11 and Annex A; Civil Code art. 533; Fa Shi [2026] No. 12 art. 9)
The first path for a material price rise is contract price adjustment, n…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.7.2、8.7.3、8.7.4、8.7.6、8.1.3、8.1.6、8.11.2、8.11.3、8.11.5、11.1.1条及App. A(A.2.5)、App. GTable G.2.1GF-2017-0201 建设工程施工合同(示范文本)通用合同条款第11.1款、第11.2款中华人民共和国民法典 第五百三十三条2026-11-08 - 02
Distinguishing claims for extension of time from cost claims: an axis-by-axis comparison of the two independent remedies, time and money, on causation threshold (critical path), basis of calculation (delay duration / total float vs actual-cost method / total-cost method), whether profit is claimable, evidence and time limits, plus the rules of combined calculation and joint approval where both are claimed together
An EOT claim asks for time, a cost claim asks for money; both are econom…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.31条、第8.11.1~8.11.13条T ZBD 100.5-2023 建设工程结算审核作业指引 第3.1.9条T ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.7.3~4.7.5条2026-11-01 - 03
Whether an extension-of-time claim can succeed without a site instruction record confirming the extension from the employer or the supervising engineer: the two-limb rule of Fa Shi [2020] No. 25 Article 10, the treatment of contract terms deeming no extension where no application is made in time, the two exceptions, and the linked 28-day claim procedure milestones
Fa Shi [2020] No. 25 Article 10 paragraph 1: where the parties agree tha…
《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》法释〔2020〕25号 第十条《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》法释〔2026〕12号 第二十三条《建设工程工程量清单计价标准》GB/T 50500-2024 第8.11.3条2026-10-29 - 04
Whether acceleration cost (for earlier completion) can be claimed when the employer demands acceleration: allocation of responsibility, the claimable net amount (after deducting the mid-term running costs of preliminaries saved by the shortened duration), approval before implementation, and the 28-day claim procedure
Claimable, but only the net amount. GB/T 50500-2024 cl. 8.11.17: where t…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.32条、第7.4.4条、第6.2.13条、第8.9.4条、第8.9.5条、第8.9.6条、第8.11.3条、第8.11.5条、第8.11.17条GF-2017-0201《建设工程施工合同(示范文本)》第7.9.1条、第7.9.2条《中华人民共和国民法典》第七百九十三条第一款、第五百八十四条、第八百零四条2026-10-29 - 05
Contract price adjustment for changes in laws, regulations and policies: the base date (28 days before the tender deadline / 28 days before contract signature) and the rule for contractor-caused delay that 'upward adjustments are denied, downward adjustments are granted' (GB 50500-2013 Section 9.2; GB/T 50500-2024 Section 8.8)
GB 50500-2013 Clause 9.2.1: for tendered works the base date is 28 days…
GB 50500-2013 第9.2.1条GB 50500-2013 第9.2.2条GB 50500-2013 第3.4.2条2026-10-25 - 06
The end-to-end time-limit chain of the final account: submission -> checking/review -> signature and seal confirmation -> payment -> final closure after the defects period - nodes, day counts, clause numbers and documentary proof requirements (GB/T 50500-2024 section 10.3 + GF-2017-0201 clause 14 + MOHURD Order No. 16)
The final account time-limit chain = submission (within 28 days after th…
GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.6~10.3.12条、第10.5.5/10.5.8/10.5.9条、第10.1.9条、App. F Table F.5.1GF-2017-0201 建设工程施工合同(示范文本) 通用合同条款第14.1款、14.2款、14.4款住房和城乡建设部令第16号 建筑工程施工发包与承包计价管理办法 第十八条、第十九条、第二十条2026-10-25 - 07
GF-2017-0201 Model Construction Contract, General Conditions clause 19.1, the contractor claims procedure chain: Notice of Claim (short form, event grounds only) - claim report (detailed form: claim grounds + additional payment amounts and/or extension of time + supporting records) - continuing claim notice - final claim report; two separately running 28-day periods and the time-bar consequences of missing them
Under General Conditions clause 19.1 of GF-2017-0201: the Notice of Clai…
GF-2017-0201《建设工程施工合同(示范文本)》通用条款第19.1、19.2、19.5条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.13节〔索赔〕、第9.14节〔现场签证〕(已被GB/T 50500-2024替代)GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11节〔工程索赔〕2026-10-25 - 08
"Measures for the Administration of Pricing of Construction Contracting and Subcontracting" edition history: MOHURD Order No. 16 (current) vs. the repealed MOC Order No. 107 — final account rules compared
The current edition is MOHURD Order No. 16 (effective 2014-02-01), whose…
住房城乡建设部令第16号《建筑工程施工发包与承包计价管理办法》(2014年2月1日施行)建设部令第107号《建筑工程施工发包与承包计价管理办法》(2001年发布,已废止)2026-09-25 - 09
Loss handling for demolition of completed works caused by design changes: the three-way method (completed works paid as measured + demolition costs priced separately + losses claimed)
Demolishing completed works for a design change is itself a variation (G…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.4-2023 建设工程造价鉴定作业指引DB11/T 382-2017 建设工程监理规程2026-09-25 - 10
Delay claims for design changes: critical-path determination, the time/cost double ledger, and the 28-day procedure
Delay caused by events not attributable to the contractor, such as desig…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范TB 10402-2019 铁路建设工程监理规范2026-09-25 - 11
The 28-day source of "silence on final-account verification means acceptance" and the two-edition comparison: GB 50500-2013 (11.3.4, 28 days) -> GB/T 50500-2024 (10.3.8, agreed time)
"Employer silence on final-account verification means acceptance" appear…
GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第11.3.4条(已废止)GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第1.0.3、10.3.8条原建设部令第107号《建筑工程施工发包与承包计价管理办法》第十六条(已废止,内容由住建部令第16号第十八条承继)2026-09-25 - 12
FIDIC Red Book 2017 EOT (8.5/20.2) vs GB/T 50500-2024 Section 8.11 delay-claim regime: the 28-day cadence, cost-and-time in one case, three-way liability, and the critical-path causation threshold
FIDIC 2017 Red Book EOT (Sub-Clause 8.5; procedure per 20.2) and GB/T 50…
FIDIC Conditions of Contract for Construction, 2nd Edition 2017, Sub-Clause 8.5/8.7/20.2, Clause 18GB/T 50500-2024 建设工程工程量清单计价标准 第8.11节2026-09-25 - 13
The employer's duty to respond after a contractor's claim: 28-day response period (restarting after supplementary evidence), 14-day window to request evidence, and judicial attitude toward deemed acceptance on silence (GB/T 50500-2024 Clause 8.11.5)
The employer shall reply in writing with its handling opinion within the…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 8.11.3、8.11.4、8.11.5 条DBJ41 T 208-2018 · Standard for Construction Project Supervision Work (Henan) 第 9.4.4 条法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第 21 条2026-09-25 - 14
Re-work confirmation requirements and claim procedure deadlines for material scrap from variations/employer-risk events: notice of intent within 28 days, claim report, employer reply in 14/28 days, and deemed waiver/acceptance on default (GB/T 50500-2024, 7.6.1/8.11.3/8.11.5)
Material-scrap claims require a written re-work confirmation demand with…
GB/T 50500-2024 第7.6.1条GB/T 50500-2024 第8.11.3条GB/T 50500-2024 第8.11.5条2026-09-25 - 15
Claims under FIDIC 2017 (Red/Yellow Book Chapter 20) compared with construction claims under China's GB/T 50500-2024: institutional positioning, the hard/soft divide of the 28-day time bar, and the procedural nodes of claims in both directions
FIDIC 2017's Claim is a "procedure unifier" - clause 20.1 (a)(b)(c) cove…
FIDIC Conditions of Contract for Construction(红皮书 2017 第二版)第20章 20.1~20.2.7FIDIC Conditions of Contract for Plant and Design-Build(黄皮书 2017)第20章GB/T 50500-2024 建设工程工程量清单计价标准 第8.1.1、8.11.1~8.11.6条2026-09-25 - 16
Claim costs in the final account: settlement line item + 28-day procedure chain + review and determination rules
Claim costs enter the final account only where both procedural complianc…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范DBJ41/T 208-2018 建设工程监理工作标准2026-09-25 - 17
The contractual definition and form requirements of a Notice under FIDIC 2017 Red Book (1.1.56 + 1.3): formal compliance is constitutive - a non-compliant document is not a Notice
In FIDIC 2017 Red Book, Notice is a term of art: 1.1.56 defines "'Notice…
FIDIC Conditions of Contract for Construction (Red Book), 2nd ed. 2017 — Sub-Clause 1.1.56, 1.1.57, 1.3, 3.7.5, 20.1, 20.2.1, 20.2.4~20.2.7, 21.4.4FIDIC Conditions of Contract for Plant and Design-Build (Yellow Book), 2017 — 索赔通知条款(同 28 天规则)2026-09-25 - 18
Consequences of late submission of site instructions and certified records: claim-type forfeiture, fact-type degradation of proof, and remedy paths
Consequences of late site instructions and certified records are layered…
GB/T 50500-2024 建设工程工程量清单计价标准DBJ41/T 208-2018 建设工程监理工作标准T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 19
FIDIC 2017 Red/Yellow Book Notice of Claim: the 20.2.1 requirement, the 28-day hard time bar and the notice-lapse mechanism, compared with GB/T 50500-2024's claim-intention notice
Under FIDIC 2017 (Red Book 20.2.1) the claim-notice rule applies symmetr…
FIDIC Conditions of Contract for Construction(红皮书)2017 第二版 Sub-Clause 20.1/20.2、1.3、3.7.3、3.7.5、21.4FIDIC Conditions of Contract for Plant and Design-Build(黄皮书)2017 Sub-Clause 20.2.1GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.1~8.11.6条2026-09-25 - 20
Responding to an employer that long delays final account review: the deemed approval upon lapse of the response period and the escalating remedy ladder
Where the employer fails to check or respond to the final account docume…
建设部令第107号 建筑工程施工发包与承包计价管理办法GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51095-2015 建设工程造价咨询规范2026-09-25 - 21
Legal consequence chain when the employer fails to check the final account or pay on time: GB/T 50500-2024 cl. 10.3.8/10.3.16/10.3.17/10.5.8/10.5.9 “deemed acceptance + liability for breach of contract” and the 28-day fallback
The consequences of the employer failing to check the final account on t…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.3.8、10.3.16、10.3.17、10.5.8、10.5.9条原建设部令第107号《建筑工程施工发包与承包计价管理办法》第十六条(已被住建部令第16号废止,内容由第十八条承继)住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条(现行)2026-09-25