Splitting the remedy paths and procedural requisites when material prices rise: whether to go first for contract price adjustment (price adjustment for cost fluctuation) or for a works claim; the time limits, written requisites and negotiation sequence of each path; and the consequences of a missed or wrong procedure (GB/T 50500-2024 cl. 8.7, cl. 8.11 and Annex A; Civil Code art. 533; Fa Shi [2026] No. 12 art. 9)
The first path for a material price rise is contract price adjustment, not a claim: GB/T 50500-2024 cl. 8.11.2 states that where an event has already had its price adjustment calculated under the contract price adjustment provisions (excluding claims), no further works claim shall be calculated - duplicate claims will be disallowed. The adjustment path runs: report quantities and unit prices before procurement -> employer checks and confirms (no reply within the agreed period is deemed approval; GF-2017-0201 general conditions 11.1 gives 5 days) -> adjust under cl. 8.7.2 (fluctuation beyond 5% where the contract sets no band) per Annex A -> submit the price adjustment report, employer verifies and confirms (cl. 8.1.3) -> confirm, sign and pay together with the progress payments / interim settlement by construction stage payments (cl. 8.1.6). Only where the contract provides no adjustable price, for abnormal fluctuation of non-adjustable materials (cl. 8.7.3), or where the rise intertwines with delay losses does the claim path open: Notice of Claim (within the contract-agreed period after the event, 28 days where unspecified) -> claim report (28 days after the notice) -> employer 14 days to request further particulars, 28 days to reply -> confirm, sign and pay; a late notice 'may be treated as waived', and the other party's late reply 'may be deemed accepted'. For fixed-price settlement, requests to adjust solely for major changes in labour cost or key material prices within the construction period are not supported by the courts (Fa Shi [2026] No. 12 art. 9), unless otherwise agreed or qualifying as change of circumstances under Civil Code art. 533.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第8.7.2、8.7.3、8.7.4、8.7.6、8.1.3、8.1.6、8.11.2、8.11.3、8.11.5、11.1.1条及App. A(A.2.5)、App. GTable G.2.1
- GF-2017-0201 建设工程施工合同(示范文本)通用合同条款第11.1款、第11.2款
- 中华人民共和国民法典 第五百三十三条
- 法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第九条
- T/CAEC 006-2024 建筑工程监理文件资料管理标准 第7.3.8条
- GB/T 50319 建设工程监理规范 表C.0.3
- DB/T 29-131-2015 天津市建设工程监理规程 第7.4.3条
Topic positioning
When material prices rise, the contractor in fact holds two mutually exclusive remedy paths - contract price adjustment (price adjustment for cost fluctuation) and a works claim. This card sets out how the two split, the procedural requisites and time limits each must satisfy, and what follows when a step is missed or the wrong path taken. It applies to material price claims and their review during the performance of construction contracts.
Core conclusions
I. The hard line of path splitting (qualify first, then run the procedure)
Final sentence of GB/T 50500-2024 cl. 8.11.2: 'where an event has already had its price adjustment calculated under the contract price adjustment provisions (excluding claims), no further works claim shall be calculated.' The same clause also requires that when either party raises a works claim against the other, it shall do so within the period agreed in the contract, with reasonable claim grounds and valid bases and supporting documents, and in compliance with the contract and with laws and regulations; and it states the nature of a claim: 'a claim is an act by the employer and the contractor to protect their lawful contractual interests; its nature is economic compensation, not punishment'; 'works claims include compensation for economic loss or adjustment of the time for completion; where both occur they shall be raised together.'
So first test whether the rise falls inside the adjustable scope: yes -> take the cl. 8.7 price adjustment and raise no claim afterwards; no (fixed price / materials outside the agreed adjustment / short of the agreed band while the contractor alleges a major change) -> only then may the matter move to a claim, to negotiation for abnormal fluctuation under cl. 8.7.3, or to a change-of-circumstances claim under Civil Code art. 533.
II. Procedural requisites of the adjustment path
- Adjustable scope and band (cl. 8.7.2 verbatim): 'where the market prices of the labour costs, material costs, and fuel and power costs within the plant and tools cost agreed for adjustment fluctuate beyond the band agreed in the contract - where the contract sets no band or the agreement is unclear, where the market price fluctuation exceeds 5% - the contract price may be adjusted by one of the methods in Annex A of this standard'; adjustment may be made by the index-based (formula) adjustment method or by the adjustment method based on published price information; 'where the market price fluctuation does not exceed the band borne by the contractor as agreed in the contract, the prices of the billed items of the works in the relevant adjustment periods may remain unadjusted.'
- Fixing the material price (Annex A.2.5): 'where the employer-approved material procurement price is adopted as the market price for the measurement period, the contractor shall, before procuring materials, submit the procurement quantities and unit prices to the employer for checking; the employer shall check and confirm within the agreed time, prices shall be calculated at those confirmed by both parties, and batch procurements may be averaged by weights. Where the employer makes no reply within the agreed period after receiving the confirmation documents submitted by the contractor, the submission may be deemed approved and may serve as the basis for adjusting the contract price.'
- The model text's 5% banding and 5-day reply (GF-2017-0201 general conditions 11.1): against the base price given by the employer (in principle compiled from the published price information issued by provincial or sector construction authorities or their authorised cost agencies) - where the tendered rate is below the base price, rises are measured off the base price and falls off the tendered rate, each adjusted for the excess beyond 5%; where the tendered rate is above the base price, falls are measured off the base price and rises off the tendered rate, each adjusted beyond 5%; where equal, both directions are measured off the base price and the excess beyond +/-5% adjusted as incurred. 'Where the employer makes no reply within 5 days after receiving the confirmation documents submitted by the contractor, the submission is deemed approved and serves as the basis for adjusting the contract price. Where the contractor procures materials on its own without prior checking by the employer, the employer is entitled not to adjust the contract price.'
- Checking and signing the adjustment report (cl. 8.1.3): 'after receiving the contractor's contract price adjustment report and the related documents, the employer shall verify them within the agreed time; where it confirms, it shall notify the contractor in writing; where it does not confirm, it shall reply in writing with its checking opinions on the price adjustment; where it neither confirms nor raises checking opinions, the contract price adjustment report submitted by the contractor shall be deemed accepted by the employer.' The procedure runs 'submission, checking, re-checking, review and confirmation'.
- Confirmation and payment (cl. 8.1.6): the parties shall sign the determined measurement and pricing output documents as the basis for payment; 'the added (or deducted) contract price confirmed by the employer and the contractor shall be paid together with the progress payments and the interim settlement by construction stage payments.'
- Price basis under delay (cl. 8.7.4): where the employer causes the extension, the prices of the works after the planned progress date take 'the higher of the planned progress date and the actual progress date'; where the contractor causes it, 'the lower'; where neither party is at fault, adjust under cl. 8.7.2.
III. Procedural requisites of the claim path (fallback time limits where the contract is silent)
- Notice of Claim (cl. 8.11.3 para 1): 'the contractor shall, within the period agreed in the contract after the claim event occurs (28 days where none is agreed), submit to the employer a written Notice of Claim for the event, stating the cause of the event and the intention to claim. Where the contractor fails to issue the Notice of Claim in time, the matter may be handled as agreed in the contract.'
- Claim report (para 2): submitted within the contract-agreed period after the notice is issued (28 days where unspecified), 'stating in detail the cause of the claim event, the contract clauses the claim relies on, and the costs claimed and/or the days of extension of time, and providing the necessary records and supporting documents and a schedule of the claim calculation'.
- Raise together (para 3): 'where the claim event raised by the contractor involves both added cost and extension of time, they shall be raised together.'
- Continuing notices for continuing effect (para 4): at the contract-agreed interval (no more than 28 days where unspecified) or at reasonable intervals, keep submitting further Notices of Claim 'listing the accumulated claim costs and/or days of extension of time'.
- Final claim report (para 5): submitted within the contract-agreed period (28 days where unspecified) after the continuing event ends, stating the total costs and/or days of extension.
- Employer's handling (cl. 8.11.5): where further materials are needed, the employer 'shall, within the period agreed in the contract (14 days where none is agreed) after receiving the Notice of Claim, request in writing that the contractor submit further supporting materials'; after receiving the claim report or the supplementary materials it shall reply in writing within the agreed period (28 days where unspecified); 'where the employer replies late or makes no reply, the matter may be handled as agreed in the contract and, where the contract is silent, the works claim requested by the contractor may be deemed accepted'; cost and time are approved together; once determined, 'the employer shall pay the claim cost to the contractor at the contractual payment percentage within the current progress payment and interim settlement by construction stage payment, and pay the remainder with the final account payment'.
- The supervising engineer's intake step (T/CAEC 006-2024 cl. 7.3.8): the Notice of Claim should follow the format of Table C.0.3 of GB/T 50319 'Code for construction project supervision'; the project supervision agency, once it accepts a notice, shall reply with its acceptance opinion within the period agreed in the construction contract; the review focuses on 'compliance with the construction contract' and 'the validity of the claim event materials'; 'the project supervision agency may refuse claim applications raised beyond the period agreed in the construction contract'; 'the sign-off times of the Notice of Claim and of the reply mark the start of the handling period agreed in the construction contract.' DB/T 29-131-2015 cl. 7.4.3 adds three conditions for a cost claim notice: raised within the contract-agreed period; the event arises from causes not attributable to the contractor and complies with the contract; and it causes the contractor direct economic loss.
IV. Consequences of skipped or wrong steps
- Re-routing an adjustable matter into a claim (or double claiming both ways) -> breaches cl. 8.11.2 ('no further works claim shall be calculated'), constitutes double counting, and the employer may disallow it outright; procedural correctness of the claim itself cannot cure the wrong path.
- Claim report only, Notice of Claim skipped -> a missing link: the periods in cl. 8.11.3 run from the Notice of Claim; without it the report period cannot start, and the other party may refuse acceptance under the contract (the supervision rules likewise allow refusal of applications beyond the agreed period).
- Late raising -> final paragraphs of cl. 8.11.3 and cl. 8.11.5: 'where the aggrieved party fails to raise the claim within the agreed time after the claim event, the relevant works claim may be treated as waived, save as otherwise agreed in the contract or provided by laws and regulations.' (The wording is 'may be treated as' and carries a proviso, leaving room for other contractual or statutory arrangements.)
- The other party's late reply -> 'where the claiming party submits the claim report as agreed in the contract and the other party fails to reply within the agreed time or makes no reply, the relevant works claim requested by the claiming party may be deemed accepted.' (A fiction in the claimant's favour, but evidence of service and sign-off must be kept.)
- Splitting the cost and time claims -> contrary to the 'raise together' requirement; the later part risks being treated as out of time and must separately prove causation with the event.
- Continuing effect without timely further notices -> the accumulated costs and days lack process records, and the final report figure becomes hard to establish.
- Skipping the pre-procurement report-and-check step -> materials procured without the employer's prior checking entitle the employer to refuse price adjustment; conversely, where the employer fails to reply in time to the confirmation documents it is deemed to approve, and the contractor should keep the sign-off records.
- Re-pricing after the rise while delay responsibility is unsettled -> a wrong pricing basis under cl. 8.7.4 directly distorts the adjustment amount (employer cause takes the higher price, contractor cause the lower).
- Fixed-price contracts trying to bypass re-pricing -> art. 9 of the Supreme People's Court Interpretation (II) on the application of law to construction contract dispute cases (Fa Shi [2026] No. 12): 'where a construction contract stipulates settlement of the project price at a fixed price, and a party requests adjustment of the contract price on the ground of major changes in labour costs or principal building material prices within the agreed construction period, the people's court shall not support the request, save where the parties have agreed otherwise or the case falls under art. 533 of the Civil Code on change of circumstances.'
- Fallback for abnormal fluctuation of non-agreed materials (cl. 8.7.3): 'where the market price of material costs other than the labour, material, and fuel and power costs within the plant and tools cost agreed for adjustment fluctuates abnormally, and this is a major change that the employer and the contractor could not foresee at contracting, and continued performance of the contract is manifestly inequitable to the party adversely affected, the parties may, under the principle of equitable risk allocation, negotiate the contractual risk band or the cost-sharing ratio and bear the relevant part of the added (or reduced) price differentials or adjust the contract price as incurred.'
- Costs that must not move with prices (cl. 8.7.6): construction consumables, small and medium tools usage, preliminary items costs, plant and tools costs other than fuel and power, non-adjustable material costs other than the abnormal fluctuation under cl. 8.7.3, price changes beyond the agreed adjustable scope and band or fluctuations within the band, overheads and profit, and costs arising from the contractor's own causes must not adjust the total contract price or the contract rates on account of cost changes.
- Negotiation sequence (cl. 11.1.1): for disputes over contract price adjustment, variations, claims, extension of time and the like, 'the parties shall resolve them through amicable negotiation and, once agreement is reached, sign the relevant supplementary (settlement) agreement, which binds both parties. Where negotiation fails to reach agreement, the employer and the contractor shall handle the matter as agreed in the contract'; the ladder is 'negotiation first; failing agreement, dispute review or mediation; failing agreement there, arbitration or litigation'.
Applicable boundaries
- Applies to employer-contractor projects priced on a BOQ basis claiming price adjustments during performance for changes in material prices (including labour costs and fuel and power for construction plant); non-tendered works and other pricing regimes under main contracting must be checked against their own contract terms.
- GB/T 50500-2024 is a recommended national standard (GB/T); the procedural clauses of cl. 8.7 and cl. 8.11 are not mandatory in themselves and become contractual obligations only once incorporated through the general or special conditions; what the contract says prevails over what the standard says. The 5% band and the 28-day and 14-day limits are fallback values for 'where the contract is silent'.
- The 28-day and 14-day limits are procedural forfeiture periods, a mechanism distinct from the three-year limitation period under the Civil Code; lateness may be excused by other contractual or statutory provisions.
- The mutual exclusion of claim and adjustment applies where 'the price adjustment has been calculated under the contract price adjustment provisions'; actual losses intertwined with delay and suspension, or falling outside the adjustment formula (deferred procurement, storage, substitute material price differences), may still be claimed in addition to the adjustment, but each item must be shown not to duplicate the adjusted items.
- Price differential adjustment after provisional prices are fixed, the quantity and price risk boundaries of lump-sum contracts, and the adjustment formulas themselves are outside this card - see the neighbouring cards cited.
Further reading
- GB/T 50500-2024 'China national pricing standard for BOQ': cl. 8.11.2 (claim preconditions and the 'no double calculation' line), cl. 8.11.3 (five nodes of a contractor's claim), cl. 8.11.5 (employer's 14-day particulars / 28-day reply and payment), cl. 8.7.2 (5% fallback where no band is agreed), cl. 8.7.3 (negotiated sharing for abnormal fluctuation), cl. 8.7.4 (pricing basis under delay), cl. 8.7.6 (list of costs not adjustable), cl. 8.1.3 (verification of adjustment reports and deemed acceptance), cl. 8.1.6 (confirmation, signing and concurrent payment), cl. 11.1.1 (negotiation - review/mediation - arbitration/litigation ladder), Annex A (adjustment methods), Annex A.2.5 (pre-procurement reporting and deemed approval on late reply), Annex G Table G.2.1 (schedule of price-adjustable key materials, a contract attachment).
- GF-2017-0201 'Model text of the construction contract', general conditions cl. 11.1 (adjustment for market price fluctuation: labour cost per issued documents, materials in three cases banded at base price +/-5%, 5-day non-reply deemed approval, no adjustment for self-procurement without checking), cl. 11.2 (adjustment for changes in law).
- Civil Code of the PRC, art. 533 (change of circumstances: a major change unforeseeable and not a commercial risk, manifest inequity, re-negotiation; failing agreement, the court or arbitration institution may amend or terminate).
- Fa Shi [2026] No. 12, SPC Interpretation (II) on construction contract dispute cases, art. 9 (fixed-price settlement: requests to adjust for major changes in labour or principal material prices within the period not supported, save other agreement or Civil Code art. 533).
- T/CAEC 006-2024 'Standard for administration of construction supervision documents', cl. 7.3.8 (Notice of Claim format, supervision intake and review focus, refusal beyond the agreed period, sign-off time as the start of the period); GB/T 50319 'Code for construction project supervision', Table C.0.3; DB/T 29-131-2015 'Tianjin procedures for construction project supervision', cl. 7.4.3 (three conditions for cost claim notices).