FIDIC 2017 Red/Yellow Book Notice of Claim: the 20.2.1 requirement, the 28-day hard time bar and the notice-lapse mechanism, compared with GB/T 50500-2024's claim-intention notice

Under FIDIC 2017 (Red Book 20.2.1) the claim-notice rule applies symmetrically: the claiming Party (contractor or employer) shall give the Engineer a Notice of Claim as soon as practicable and no later than 28 days after becoming aware (or should have become aware) of the event (in writing, identified as a Notice per 1.3, signed original via the designated system, describing the event). Failure is a hard time bar - Red Book: "shall not be entitled to any additional payment"; Yellow Book adds: no EOT and "the Employer shall be discharged from all liability in connection with the claim". The notice also hangs on the detailed-claim chain: failure to submit the fully detailed Claim within 20.2.4's period means the Notice "shall be deemed to have lapsed" (no longer valid), the Engineer notifying within 14 days after expiry. Contrast with GB/T 50500-2024 8.11.3/8.11.4's claim-intention notice (contractual period, 28-day default, running from the event, late claims "handled per contract" and caught by the soft "may be deemed waived" clause) - hard vs soft forfeiture.

Applicable Codes

  • FIDIC Conditions of Contract for Construction(红皮书)2017 第二版 Sub-Clause 20.1/20.2、1.3、3.7.3、3.7.5、21.4
  • FIDIC Conditions of Contract for Plant and Design-Build(黄皮书)2017 Sub-Clause 20.2.1
  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.1~8.11.6条

Topic Positioning

The complete procedural requirements of Sub-Clause 20.2 of the FIDIC 2017 second-edition conditions (Red Book Construction; Yellow Book Plant and Design-Build) for the Notice of Claim: who gives it to whom, how the 28 days run, consequences of lateness, the lapse mechanism - and the key points of comparison with the claim-intention notice of GB/T 50500-2024.

Core Conclusions

(1) Scope and symmetry (20.1): A Claim may arise where (a) the Employer considers itself entitled to additional payment from (or reduction of the Contract Price by) the Contractor and/or extension of the Defects Notification Period (DNP); (b) the Contractor considers itself entitled to additional payment and/or Extension of Time (EOT); (c) either Party claims other entitlement or relief. Employer deductions and DNP extensions equally follow 20.2 (20.2.7: the Employer shall only be entitled ... by complying with this Sub-Clause 20.2).

(2) The four elements of the 20.2.1 Notice of Claim:

  • From/to: the claiming Party gives it to the Engineer (neutral third party), not directly to the other side;
  • Time/trigger: after the claiming Party "became aware, or should have become aware" of the event or circumstance giving rise to cost, loss, delay, or DNP extension - "as soon as practicable, and no later than 28 days" - a subjective-objective combined trigger;
  • Content: "describing the event or circumstance" - light at the intention stage (locking the event); detail comes later;
  • Form: per Sub-Clause 1.3 [Notices and Other Communications]: in writing, identified as a Notice, a signed paper original or an electronic original generated from the system stated in the Contract Data, sent from the authorized representative's designated address, copied to the other Party/Engineer.

(3) Late consequence (hard bar): Red Book 20.2.1, original: "If the claiming Party fails to give a Notice of Claim within this period of 28 days, the claiming Party shall not be entitled to any additional payment, ...". Yellow Book, fullest wording: "If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim." - no "may", no saving tail.

(4) Notice-lapse mechanism (20.2.4): after the Notice, the claiming Party must submit the fully detailed Claim within the stated period (generally 42 days or as the Engineer agrees); failing that, "the Notice of Claim shall be deemed to have lapsed, it shall no longer be considered as a valid Notice", and the Engineer shall notify within 14 days after expiry; the Engineer's failure to so notify does not save the claiming Party. The notice is thus not valid forever once given - it hangs on the detailed-claim chain; break the chain and it lapses.

(5) Companion machinery: 20.2.3 contemporary records - the claiming Party keeps the records needed to substantiate the Claim, which the Engineer may inspect or direct to be completed (without admitting Employer liability); 20.2.5 - if the Engineer needs more particulars it shall so notify but must still respond on the contractual/legal basis within Sub-Clause 3.7.3 [Time limits]; 20.2.6 continuing claims - the first fully detailed Claim is interim, followed by monthly interim fully detailed Claims with accumulated amounts (reductions for employer claims); 20.2.7 - from notice until agreement, the Engineer includes reasonably substantiated amounts in each Payment Certificate. Dissatisfaction with the Engineer's determination triggers an NOD within 28 days per 3.7.5, with 21.4 DAAB proceedings a precondition to arbitration.

(6) Chinese comparison (see cited card): GB/T 50500-2024 8.11.3 (contractor->employer) and 8.11.4 (employer->contractor, delay damages excluded) use the "claim-intention notice", to be submitted in writing within the contractual period (default 28 days) after the event, stating cause and intention; late claims "may be handled per the contract", plus the general clause "where the aggrieved party fails to claim within the agreed time, it may be deemed to have waived the relevant claim unless the contract or laws provide otherwise" - a soft bar with three layers of escape (contract, law, "may"). FIDIC is stricter: subjective "aware or should have been aware" trigger, hard bar, and lapse on late detail; the Chinese standard runs objectively "after the event" with escapes. Both 28-day periods are procedural bars (FIDIC: no entitlement/discharged; China: deemed waiver), not limitation periods.

Keywords

  • 索赔通知
  • Notice of Claim
  • FIDIC 20.2.1
  • FIDIC 2017
  • 工程索赔意向通知书
  • 28 days
  • fully detailed claim
  • 逾期失权