The 28-day source of "silence on final-account verification means acceptance" and the two-edition comparison: GB 50500-2013 (11.3.4, 28 days) -> GB/T 50500-2024 (10.3.8, agreed time)
"Employer silence on final-account verification means acceptance" appears in both editions with different wording: GB 50500-2013 (repealed) Clause 11.3.4 fixes 28 days directly; GB/T 50500-2024 (current) Clause 10.3.8 changes to "within the agreed time ... deemed accepted". A 28-day fallback exists in regulations (former Ministry Order No. 107, Article 16: absent express agreement, 28 days - carried into current MOHURD Order No. 16, Article 18). But payment at the submitted price depends on the contract: Fa Shi [2020] No. 25 Article 21 supports only cases with express contractual agreement; without it, claims resting on the standard/order alone are generally rejected.
Applicable Codes
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第11.3.4条(已废止)
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第1.0.3、10.3.8条
- 原建设部令第107号《建筑工程施工发包与承包计价管理办法》第十六条(已废止,内容由住建部令第16号第十八条承继)
- 住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条
- 法释〔2020〕25号《建工司法解释(一)》第二十一条(沿袭法释〔2004〕14号第二十条)
- 财建〔2004〕369号《建设工程价款结算暂行办法》第十六条
- https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_6186304e164c4c4982904f8734983235.html
- https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2015/art_17339_224556.html
Topic Positioning
At the final-account stage, if the employer stalls verification, is it true that "28 days of silence means deemed acceptance"? Is the 28 days set by the standard or by the contract? Do the 2013 and 2024 editions of the BOQ pricing standard agree on this point? This card gives the texts of both national standard clauses side by side, the source hierarchy of "28 days" (standard -> regulation -> model text -> contract), and the conditions for the rule to deliver, for direct citation in final-account practice.
Core Conclusions
- The rule genuinely exists; the two clause texts side by side:
- GB 50500-2013 (repealed) 11.3.4: "If the employer, within 28 days of receiving the contractor's final-account documents, does not verify the account or offer verification comments, the documents shall be deemed accepted by the employer and the settlement completed."
- GB/T 50500-2024 (current, effective 1 Sep 2025, replacing 2013) 10.3.8: "If the employer, within the agreed time after receiving the contractor's final-account documents, does not verify the account per the contract or offer comments, the documents shall be deemed accepted by the employer and the settlement confirmed." The skeleton carries over (the employer's failure to respond within the prescribed time -> deemed acceptance of the contractor's final-account documents; the contractor's own failure to respond within the prescribed time to the employer's verification comments is likewise deemed acceptance, see 10.3.9), with two substantive differences: (1) the period moves from a hard-coded "28 days" in the body of the standard to "within the agreed time", returning the number to the contract; (2) the nature of the standard changes from mandatory GB to recommended GB/T.
- Source hierarchy of "28 days" (both ends exist; the indispensable link is writing it into the contract):
- Standard level: the 2013 edition fixed 28 days in its body; the 2024 edition no longer sets a number, deferring to "the agreed time".
- Regulation level: former Ministry Order No. 107, Article 16: "The employer shall respond within the agreed period after receiving the final-account documents; on failure to respond within the prescribed time, the final-account documents are deemed accepted ... where the parties have not expressly agreed on such periods in the contract, the agreed period is deemed to be 28 days." (The order is repealed; its content is carried forward by current MOHURD Order No. 16, Article 18 - the 28-day default where no period is agreed is unchanged.)
- Contract level: model conditions (GF-2017-0201 general conditions) commonly provide a 28-day verification period - a template that binds only when signed into the contract.
- Delivery (settlement at the submitted price) depends on the contract: SPC Interpretation (I) (Fa Shi [2020] No. 25) Article 21 (continuing Fa Shi [2004] No. 14 Article 20): "Where the parties agree that the employer's failure to respond within the agreed period after receiving the final-account documents is deemed acceptance of those documents, the agreed terms prevail, and the contractor's claim for payment per the final-account documents shall be supported." Three elements must concur: (1) an express agreement in the contract; (2) the documents were served and complete; (3) failure to respond within the agreed period. Without such an agreement, claims resting on the standard/order/model text alone are rejected by the SPC and most courts - the 2013 commentary itself states that the parties should agree in the contract both on the verification time and on silence meaning acceptance of the contractor's final-account documents. Per 2024 general principles Article 1.0.3, pricing activities follow the principles of "objectivity and fairness, equality and voluntariness, honesty and trustworthiness, statutory priority, agreed terms prevail" - where the contract contains an agreement, the agreed terms govern.
Applicable Boundaries
Applies at the final-account stage after taking-over (completion acceptance) to cases where the employer, having received the contractor's final-account documents, fails to verify them or respond within the prescribed time. Deemed acceptance presupposes that the contractor submitted complete final-account documents as agreed - incomplete documents restart the clock; without a "deemed acceptance" clause in the contract, the prospects of such a claim are low, and some courts do not grant it directly but turn to construction cost expert assessment (judicial appraisal); the 2024 edition, being a recommended GB/T, requires contractual incorporation (e.g., special conditions stating "final account per GB/T 50500-2024") before it becomes a contractual obligation; for state-funded projects, the employer must by law engage a cost consulting firm to review, and deemed acceptance cannot exclude the statutory review procedure; and this differs from deemed acceptance of a payment application where the payment certificate is not issued within the prescribed time (Article 10.3.16), which is a separate procedure.
Further Reading
GB 50500-2013 Article 11.3.4 and its commentary (repealed); GB/T 50500-2024 Articles 1.0.3, 10.3.5, 10.3.8, 10.3.9; former Ministry Order No. 107 Article 16 (repealed) -> current MOHURD Order No. 16, Article 18; Fa Shi [2020] No. 25 Article 21 (from Fa Shi [2004] No. 14 Article 20); Caijian [2004] No. 369 Article 16; rules on construction cost expert assessment in settlement disputes per GB/T 51262-2017. MOHURD pages: https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_6186304e164c4c4982904f8734983235.html , https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2015/art_17339_224556.html
Keywords
- final account
- deemed acceptance / deemed approval
- failure to respond within the prescribed time
- 28 days
- GB/T 50500-2024
- GB 50500-2013
- 结算核对期限