Valid drafting of "overdue non-reply deemed acceptance" clauses: six elements, invalidity red lines, and a reference template
Civil Code Article 140(2) is the legal basis for "overdue non-reply deemed acceptance" clauses; in construction, supported by Fa Shi [2020] No. 25 Article 21, the current MOHURD Order No. 16 Article 18 (succeeding repealed Order 107 Article 16), and GB/T 50500-2024 Articles 10.3.5/10.3.8/10.3.9/10.3.16/10.5.8. Six elements for validity: written consensus, specified object, clear deadline (from receipt), clear consequence, complete service mechanism, and a paired objection procedure; avoid four red lines—invalid standard-clause effects, exclusion of mandatory duties, restricting litigation rights, and conflict with "per audit" clauses.
Applicable Codes
- 《民法典》第140条第2款
- 法释〔2020〕25号第21条
- 住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条、第二十七条
- GB/T 50500-2024 第10.3.5、10.3.8、10.3.9、10.3.16、10.5.8条
- 建设部令第107号(2001年发布,已废止)
Topic Positioning
How to draft a valid "overdue non-reply deemed acceptance" clause in contracts: legal basis, six elements for validity, invalidity red lines, and a reference template, for drafting and reviewing owner-contractor contracts.
Core Conclusions
Civil Code Article 140(2) (silence may be deemed a manifestation of intent when so agreed) is the legal basis; in construction, specifically supported by Fa Shi [2020] No. 25 Article 21, the current Measures for Pricing of Construction Contracting (MOHURD Order No. 16, effective Feb 1, 2014) Article 18, and GB/T 50500-2024 Articles 10.3.5/10.3.8/10.3.9/10.3.16/10.5.8. Note: the former MOHURD Order 107 Article 16 was repealed by Order No. 16 Article 27—cite the current Order 16 Article 18 (overdue non-reply: first per the contract; absent contract terms, deemed accepted; deadlines: first per state regulations; absent those, agreed deadlines may be deemed 28 days). Six elements for validity: written consensus, specified object, clear deadline (counted from receipt), clear consequence, complete service mechanism, and a paired objection procedure; avoid four red lines—invalidity as a standard clause, exclusion of mandatory statutory duties, restriction of litigation rights, and conflict with "per audit" clauses.
Applicable Boundaries
Applies to drafting and validity judgment of "overdue non-reply deemed acceptance" clauses in owner-contractor construction contracts. For state-funded projects under Order 16 Article 18, the letting party must engage a cost consultant to review—such clauses must not exclude the statutory review procedure; clause terms must not violate mandatory law or exclude the other party's main rights. Case validity still depends on the contract text and judicial practice.
Further Reading
Civil Code Article 140(2); Fa Shi [2020] No. 25 Article 21; MOHURD Order No. 16 Measures for Pricing of Construction Contracting, Articles 18 and 27 (former Order 107 Article 16 repealed); GB/T 50500-2024, Articles 10.3.5, 10.3.8, 10.3.9, 10.3.16, 10.5.8.
Keywords
- 逾期不回复视为认可
- 沉默视为意思表示
- 合同条款
- final account
- MOHURD Decree No. 16
- 民法典第140条