Checklist of pre-construction approvals for government-invested projects with each formality's legal basis: establishment and estimates, land and planning, EIA and energy assessment, drawing review with quality-safety supervision, construction permit and start conditions
Pre-start formalities of government-invested projects fall into five groups by nature: 1 establishment and estimates - the Regulation on Government Investment, Article 9, requires the proposal, feasibility report and preliminary design to be compiled and submitted, the verified estimate controlling total investment, a preliminary-design estimate exceeding the approved feasibility estimate by 10% being reported to the approving authority (Article 12), and annual-plan listing requiring an approved feasibility report or verified estimate (Article 17); 2 land and planning - allocated-land projects apply for the site selection opinion before approval or verification (Urban and Rural Planning Law, Article 36) and for land pre-review (Measures for Examining and Approving Construction Land, Article 4), plus land-use / construction planning permits and expropriation approval; 3 EIA and energy - EIA documents submitted to the approving authority (Environmental Impact Assessment Law, Articles 22 and 25 - no approval, no start); projects failing mandatory energy standards may not start nor be approved (Energy Conservation Law, Article 15); 4 drawing review and supervision - drawings submitted for review before use (Quality Management Regulation, Article 11) and quality supervision formalities before the permit or start report (Article 13), safety-measure information with the permit application and safety measures filed within 15 days of an approved start report (Construction Safety Regulation, Article 10); 5 permit and start conditions - six conditions for the permit (Construction Law, 2019 revision, Article 8); projects not meeting construction conditions may not start, and material changes of location, scale or content require re-approval (Regulation on Government Investment, Articles 20 and 21).
Applicable Codes
- 《政府投资条例》(国务院令第712号)第九条、第十一条、第十二条、第十七条、第二十条、第二十一条、第三十四条
- 《城乡规划法》第三十六条
- 《建设用地审查报批管理办法》第四条
- 《环境影响评价法》第二十二条、第二十五条
- 《节约能源法》第十五条
- 《建设工程质量管理条例》第十一条、第十三条
- 《建设工程安全生产管理条例》第十条
- 《建筑法》(2019修正)第八条
Scope of the question
The checklist of pre-construction approvals (filings) for government-invested projects with their legal bases, covering establishment and estimates, land and planning, EIA and energy assessment, drawing review and quality-safety supervision, and the construction permit and start conditions - for compiling application lists, pre-review investigation and start-condition compliance checks.
Core conclusions
1. Establishment and estimate control
- Regulation on Government Investment, Article 9: the project unit compiles the proposal, feasibility report and preliminary design and submits them per authority and procedure.
- Article 11 (review content): necessity; technical-economic feasibility, social benefit and funding conditions analysed in the feasibility report; conformity of the preliminary design and its estimate with the feasibility approval and state standards and codes.
- Article 12: the verified estimate controls total investment; a preliminary-design estimate over 10% above the approved feasibility estimate must be reported to the approving authority.
- Article 17: annual-plan listing requires an approved feasibility report or a verified estimate, inter alia.
2. Land and planning
- Site selection opinion: Urban and Rural Planning Law, Article 36 - projects using allocated state land apply to the planning authority for the selection opinion before submitting for approval or verification.
- Land pre-review: Measures for the Examination and Approval of Construction Land, Article 4 - at approval, verification or filing, apply to the natural-resources authority at the same level, which issues the pre-review opinion.
- Others: land-use planning permit, construction-project planning permit, farmland conversion and expropriation approval (where new land is involved), pre-start setting-out verification.
3. EIA and energy
- Environmental Impact Assessment Law, Article 22: the EIA statement or form goes to the competent ecology authority for approval. Article 25: without reviewed-and-approved EIA documents, the approval authority may not approve construction and the project may not start.
- Energy Conservation Law, Article 15: fixed-asset investment projects carry energy assessment and review; projects failing mandatory energy standards may not start, and government projects failing them may not be approved.
- Other special approvals (by project): soil and water conservation, flood (river-related) impact assessment, fire design review / filing.
4. Drawing review and quality-safety supervision
- Quality Management Regulation, Article 11: construction drawings are submitted to the construction authority at or above county level for review; unreviewed drawings may not be used. Article 13: quality supervision formalities before the permit or start report.
- Construction Safety Regulation, Article 10: safety-measure information with the permit application; where a start report is approved, the safety measures are filed with the local construction authority within 15 days.
5. Construction permit, start conditions, changes
- Construction Law (2019 revision), Article 8 (permit conditions): land approval completed; planning permit obtained where required; demolition progress meeting construction needs; a builder engaged; funds, drawings and technical data adequate for construction; concrete quality and safety measures in place.
- Regulation on Government Investment, Article 20: projects start only when meeting the state construction conditions. Article 21: implementation follows the approved location, scale and content; material changes are re-submitted to the original approving authority.
- Article 34 sanctions unapproved changes of location, scale or content and starting without approval or against the construction conditions.
Applicability limits
- The list is generic; industries and localities add special approvals (water, transport, energy, fire, civil air defence); actual filing follows the current effective regulations of the project.
- Items may be done, pending, undone or inapplicable - judge applicability by construction nature, land allocation mode (allocated / granted) and whether new land is involved; do not apply blanketly.
- Time limits, parallel approval and commitment-based reforms vary locally; verify clause numbers and figures against current texts before citing.
- Building without approval, building while approving, inverted procedures and inconsistencies among approvals, feasibility, preliminary design and drawings are high audit and enforcement risks.
Further reading
Regulation on Government Investment (Order No. 712), Articles 9, 11, 12, 17, 20, 21, 34; Urban and Rural Planning Law, Article 36; Measures for the Examination and Approval of Construction Land, Article 4; Environmental Impact Assessment Law, Articles 22, 25; Energy Conservation Law, Article 15; Quality Management Regulation, Articles 11, 13; Construction Safety Regulation, Article 10; Construction Law (2019 revision), Article 8. When compiling the checklist, verify authority, document number and approval date per item.