The three regimes of project initiation: the approval regime for government-invested projects and the verification and filing regimes for enterprise-invested projects - applicable conditions, submission documents and review points
Initiation splits into three regimes by investor and project nature. (1) Projects invested by government directly or by capital injection (government-invested projects) follow approval - the project unit compiles the project proposal, feasibility study report and preliminary design for approval by the investment authority or other departments (Regulation on Government Investment, Order No. 712, Article 9), reviewed on necessity, techno-economic feasibility and social benefit with funding, conformity of the preliminary design and estimate with the feasibility approval and national standards, and other statutory matters (Article 11). (2) Enterprise projects listed in the Catalogue of Investment Projects Subject to Government Verification follow verification - an application covering the enterprise's particulars, the project, resource use and ecological impact, and economic and social impact (Regulation on Verification and Filing of Enterprise Investment Projects, Order No. 673, Article 6). (3) Projects outside the Catalogue follow filing - before starting, the enterprise informs the platform of its particulars, project name / location / scale / content, total investment and a statement of policy conformity; receipt of the full information completes the filing (Article 13). Per HG/T 20705-2009 term 2.0.16, approval of the project proposal is "initiation", admitting the project into pre-construction planning for the feasibility study.
Applicable Codes
- 《政府投资条例》(国务院令第712号)第九条、第十一条
- 《企业投资项目核准和备案管理条例》(国务院令第673号)第六条、第十三条
- HG/T 20705-2009《石油和化学工业工程建设项目管理规范》第2.0.16条
- 计资〔1983〕116号《关于建设项目进行可行性研究的试行管理办法》第二条
- T/CNAEC 0601-2024《全过程工程咨询服务指南(建筑与城乡规划领域)》第6.3.1条
Topic Positioning
This card answers "how does a project get initiated": initiation is not an isolated act but the key node of the investment-decision stage of the capital construction sequence - obtaining the investment authority's approval (or completing verification or filing) through statutory procedure. Which route applies turns on the investor and the project's nature: approval, verification and filing.
Core Conclusions
1. Government-invested projects: approval (government money goes through approval) Regulation on Government Investment (Order No. 712), Article 9, original: "For projects invested by government directly or by capital injection (government-invested projects), the project unit shall compile the project proposal, feasibility study report and preliminary design and submit them, per the government investment mandates and procedures, to the investment authority or other departments for approval." The same article: "The project unit shall strengthen the pre-construction work, ensure it reaches the required depth, and be responsible for the truthfulness of the proposal, the feasibility report, the preliminary design and the other documents required by law."
Article 11, review content, original: "The investment authority or other departments shall review government-invested projects against the national economic and social development plans, the special plans of the sector, industrial policy and the like, and decide whether to approve: (1) the necessity of construction stated in the proposal; (2) the techno-economic feasibility, social benefit and availability of main construction conditions including funding, analysed in the feasibility report; (3) whether the preliminary design and its estimate conform to the feasibility approval and to national standards and codes; (4) other matters required by law, administrative regulations and State provisions." Where refused, "written notice with reasons shall be given"; "for projects with major impact on the economy, society and the public, or of large scale, the decision shall rest on intermediary assessment, public participation, expert review and risk assessment."
2. Enterprise-invested projects: verification and filing (enterprise money - inside or outside the Catalogue) Regulation on Verification and Filing of Enterprise Investment Projects (Order No. 673), Article 6: for verification the enterprise submits the application to the verifying authority (State Council projects to its investment department); the application covers four classes, original: "(1) the enterprise's basic particulars; (2) the project - name, location, scale, content and the like; (3) analysis of resource use and of ecological impact; (4) analysis of economic and social impact." Also "the enterprise is responsible for the truthfulness of the application" and "where laws or regulations make other procedures preconditions, the enterprise shall submit proof of completion".
Article 13 (filing): before starting construction the enterprise informs the filing authority through the online platform of (1) its basic particulars; (2) the project name, location, scale and content; (3) the total investment; (4) a statement that the project conforms to industrial policy. "The enterprise is responsible for the truthfulness of the information filed." "Receipt of the full information completes the filing; where incomplete, the authority shall guide completion." "A certificate may be issued or printed from the platform on request."
3. "Initiation" as a node, and stage linkage HG/T 20705-2009 (petrochemical project management) term 2.0.16 (project proposal), original: the proposal is compiled "under the current capital construction procedure, for government-invested projects, on the basis of investigation, analysis and forecast of national and local development goals and plans, sector plans, resources and market demand", "further justifying the grounds for the project. Approval of the proposal is 'initiation'. The project enters the pre-construction work plan and feasibility study begins. Foreign-funded projects may open external work."
JJZi [1983] No. 116 (trial measures for feasibility studies), Article 2: "Decision and implementation of construction projects shall strictly follow the State's capital construction procedure. Feasibility study is an important part of pre-construction work and a component of the procedure."
T/CNAEC 0601-2024 (whole-process consultancy guide), 6.3.1 (investment-decision services): "government-invested projects compile the proposal and feasibility study per the rules; enterprise projects compile the application report on the feasibility findings per the rules and the investor's requirements."
Applicability Boundaries
- The regimes split by investor and nature: government direct-investment and capital-injection projects - approval; enterprise projects - verification inside the Catalogue, filing outside.
- Under approval, proposal approval is "initiation"; verification and filing (issuing the verification document, completing the filing) are not fully equivalent - the follow-on procedures for feasibility, preliminary design and annual plans have their own rules.
- This card is bounded by the original texts of Articles 9 and 11 of Order No. 712 and Articles 6 and 13 of Order No. 673; estimate overruns beyond the feasibility estimate, simplified approval, online project codes and the like lie outside the evidence gathered - verify against the regulations.
- Sectors (petrochemical, highway, railway, building) may add pre-construction depth requirements - apply in stack.
Further Reading
- Regulation on Government Investment (Order No. 712), Articles 9 (submission documents) and 11 (review and approval); other articles (estimate control, simplified approval, project codes) - verify from the original texts.
- Regulation on Verification and Filing of Enterprise Investment Projects (Order No. 673), Article 6 (application content) and Article 13 (filing information; "receipt completes filing").
- HG/T 20705-2009, term 2.0.16 (project proposal).
- JJZi [1983] No. 116, Article 2.
- T/CNAEC 0601-2024, clause 6.3.1 (investment-decision services).