Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Cost confirmation after a design change to seismic supports: the four-step rule of qualification → measurement → rate build-up → certification and sign-off

A seismic-support design change (designer-issued variation / employer's instruction) constitutes a variation and the price is adjustable; finished supports are measured in sets under code 031301004, and quantities must be recalculated per Chapter 8 of GB 50981-2014; rate build-up follows GB/T 50500-2024 Clause 8.9.1: identical item descriptions take the contract unit rate, analogous items take a conversion of contract unit rates, and items neither identical nor analogous are determined by negotiation; a quantity difference exceeding 15% triggers adjustment of the unit rate per Clause 8.9.2, and additions beyond the contract scope are treated as additional works per Clause 8.10; differences arising from the contractor's own detailed layout are not adjusted (Clause 3.3.9); after the supervisor's certification and sign-off and the signing of the deliverables by both parties, payment is made together with the interim payment.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB 50981-2014 建筑机电工程抗震设计规范
  • GB/T 50856-2024 通用安装工程工程量计算标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • T/CAEC 006-2024 建筑工程监理文件资料管理标准

Topic Positioning

The complete path for qualifying, measuring, building up rates for, and certifying and signing off the cost of seismic supports (finished supports) after they are added, reduced, re-specified, or changed in form as a result of a design change.

Core Conclusions

Four steps: ① Qualification — a design change order, the employer's instruction, or an adjustment to the design documents constitutes a variation, and the price is adjustable; differences arising from the contractor's own detailed layout (e.g. self-initiated reduction of spacing) are generally not adjusted (GB/T 50500-2024, Clause 3.3.9). ② Measurement — per GB/T 50856-2024 Appendix N, finished supports (code 031301004) are measured in "sets"; the quantity of the variation is calculated by comparing the variation instruction and the actual construction drawings with the contract drawings (Clause 7.4.1); the post-variation quantity must be recalculated per Chapter 8 of GB 50981-2014: lateral supports at both ends of each horizontal straight pipe run, at least one longitudinal support, further supports added successively beyond the maximum spacing in Table 8.2.3 (for renovation works, half the spacing applies), and a lateral support within 0.6 m of a bend. ③ Rate build-up — Clause 8.9.1: where the item description is identical, the contract unit rate is adopted directly; for analogous items (e.g. a single-pipe lateral support changed to a portal type), the contract unit rate is converted and adjusted; where there is neither an identical nor an analogous item, a reasonable market all-in unit rate is determined by negotiation; where the quantity difference exceeds 15% (exclusive), the unit rate for the increased portion is reasonably reduced and that for the decreased portion reasonably increased (Clause 8.9.2); additions beyond the contract scope are additional works per Clause 8.10, for which a priced offer must be submitted for the employer's approval before implementation. ④ Certification and sign-off — the price certification is jointly signed off by the employer, the contractor, and the supervisor, reviewed by the cost supervision engineer and checked by the chief supervision engineer (T/CAEC 006-2024, Clause 7.2.9); both parties sign the measurement-and-pricing deliverables (Clause 8.1.6), and the confirmed amount is paid together with the interim payment / stage settlement during construction.

Applicable Boundaries

Applies to re-measurable (unit-rate) contracts and lump-sum contracts (lump-sum contracts are handled per Clause 8.9.3). Seismic-support spacing is mandatory under GB 50981-2014, so the varied quantity must be recalculated per the code and cannot be measured merely from the quantity stated in the variation order; the main materials of finished supports (including anchors) are priced per the certification of material quality and price. The method whereby lateral/longitudinal supports take the local quota's lateral sub-item labour × 1.05 is a local quota example (e.g. Beijing DB11T 2382-2024 C10-4-3/4); other regions follow their local quota norms. Not applicable: additions made by the contractor on its own initiative without any variation formalities or any trace of employer/supervisor confirmation.

Further Reading

GB/T 50500-2024 Clauses 3.3.9, 7.4.1, 8.1.6, 8.9.1, 8.9.2, 8.9.3, 8.10.1, 8.10.2; GB 50981-2014 Clauses 8.2.3, 8.3.1, 8.3.3, 8.3.6; GB/T 50856-2024 Appendix N (N.1.1, N.2.3); T/ZBD 100.5-2023 Clause 3.1.8; T/CAEC 006-2024 Clause 7.2.9.

Keywords

Cited By