re-rating of unit rates
- 01
Trigger table for the +/-15% quantity deviation threshold: the three outcomes of retaining the original price, adjusting the rate and deriving new rates, and the dividing lines between them (GB/T 50500-2024 Articles 8.2.1, 8.9.1, 8.9.2 and 8.9.3)
Under GB/T 50500-2024 the 15% mark is only a threshold on quantity, and…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.2.1条、第8.9.1条、第8.9.2条、第8.9.3条、第7.1/7.2/7.4节GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.6.2条、第9.6.3条、第9.3.1条T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.4.4条2026-11-08 - 02
Pricing clash-detour increments of MEP services: the attribution boundary of detailing versus variation, the valuation entries (8.9.1 / 8.9.2 and 2013's 9.3.1), the material and labour increments of cable-tray extended metres, bends and supports, and the separate claim channel for stoppage and the site-record anchors
Three gates before pricing a detour: (1) difference nature - contract ve…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.2、3.3.3、7.1、7.2、7.4、8.9.1、8.9.2、8.9.3、8.9.6、8.9.7、8.11.3、8.11.9、8.11.10条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.3.1、9.14.1、9.14.2条(已废止,仅合同援引时参照)T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.4.4、4.4.6条2026-10-25 - 03
Bills of quantities errors (item description mismatches, wrong or missing items, quantity deviations): determination, attribution of responsibility and the quantity-then-price adjustment sequence, including the split between unit-rate and lump-sum contracts and the 15% threshold rule
Where the BOQ and the drawings are inconsistent, the sequence is 'decide…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.27、3.3.2、3.4.7、4.1.4、4.1.6、6.1.7、7.2.1、8.2.1、8.9.1条GB/T 50319-2013 建设工程监理规范 第6.3.3条T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.4.4条2026-10-25 - 04
Boundary determination and clause routing among quantity deviation, variation and omitted BOQ items: sections 9.4/9.5/9.6 of the 2013 edition are merged into 'BOQ errors' in GB/T 50500-2024, sorted by three comparison tests (contract drawings vs contract BOQ; contract drawings vs actual construction drawings; inside vs outside the contract works scope), with an anti-double-counting rule that one matter goes through one route only
The routing test is unique: a difference between the contract drawings (…
GB/T 50500-2024 第2.0.27条(工程量清单缺陷)GB/T 50500-2024 第2.0.28条(工程变更)GB/T 50500-2024 第2.0.30条(新增工程)2026-10-25 - 05
Adjusting all-in unit rates at the +/-15% quantity boundary: GB/T 50500-2024 Clauses 8.9.1-8.9.3 and the reading of the wording change from repealed GB 50500-2013 Clause 9.6.2's "tiered pricing"
Under GB/T 50500-2024 (unit-price contracts): within 15% (inclusive) per…
GB 50500-2013 第9.6.1条GB 50500-2013 第9.6.2条GB 50500-2013 第9.6.3条2026-10-25 - 06
Settlement where a design change reduces the quantities: adjustment rules for unit-rate and lump-sum contracts, compensation for outright cancellation of an item, and the linkage of preliminaries
The settlement principle for reduced quantities is "re-measure against t…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 07
Mechanism for material price changes under fixed unit-price contracts: unit price locked + quantities at actuals + beyond-band adjustment (GB/T 50500-2024)
Under unit-price contracts the all-in unit rate is fixed within the cont…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 08
Can final account review/audit adjust awarded all-in unit rates? — rate locking under re-measurable contracts, statutory exceptions, and the limits of audit authority
In principle, no. Under a re-measurable (unit-rate) contract, awarded al…
T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第1.1.7条、第3.1.6条GB/T 51095-2015 · Code for construction cost consultation 第8.2.5条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.1.1条、第8.2.1条、第8.9.1条、第8.9.2条、第10.3.10条、第10.3.12条2026-09-25 - 09
Cost confirmation after a design change to seismic supports: the four-step rule of qualification → measurement → rate build-up → certification and sign-off
A seismic-support design change (designer-issued variation / employer's…
GB/T 50500-2024 建设工程工程量清单计价标准GB 50981-2014 建筑机电工程抗震设计规范GB/T 50856-2024 通用安装工程工程量计算标准2026-09-25 - 10
Design change overview: authority to propose, classification and grading, approval and implementation, three-tier pricing, settlement and disputes across six links (with variation concept cross-links and FIDIC mapping)
The design-change full chain: any of four parties may propose; only the…
建设工程勘察设计管理条例(国务院令第687号)第二十八条GB/T 50500-2024 建设工程工程量清单计价标准(第7.6、8.9、8.11节)GB/T 50319-2013 建设工程监理规范2026-09-25 - 11
Price adjustment rules for brand changes of decoration materials: three situations, adjusting the material cost only, and the certification of material quality and price procedure
Brand-change price adjustment = replace the original price with the conf…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25