Price adjustment rules for brand changes of decoration materials: three situations, adjusting the material cost only, and the certification of material quality and price procedure

Brand-change price adjustment = replace the original price with the confirmed pre-tax price → adjust the material cost only (other costs unchanged) → VAT counted separately. Provisional-sum materials are replaced by tender/market price enquiry prices; non-provisional-sum (contract-agreed brand) materials must undergo the employer's certification of material quality and price before procurement — unconfirmed prices are not adjusted; under the railway system the price differential is computed as norm resource consumption x the difference between preparation-period and base-period prices.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51262-2017 建设工程造价鉴定规范
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • DB11/T 382-2017 建设工程监理规程

Topic Positioning

How the contract price is adjusted after a material brand change in decoration works (including BOQ provisional-sum materials and contract-agreed brand materials): the handling paths of three situations, the "adjust the material cost only" calculation basis, the key points of pre-procurement certification of material quality and price, and the price-differential rules for decoration materials under the railway estimates and budgets system (China Railway system).

Core Conclusions

Three situations by material nature: (1) BOQ provisional-sum materials subject to mandatory tendering — replaced by the awarded pre-tax price of the procurement tender; (2) provisional-sum materials not subject to mandatory tendering — replaced by the pre-tax price after the contractor's market price enquiry/own quotation is confirmed by the employer (or joint enquiry confirmation by both parties); (3) non-provisional-sum materials (contract-agreed brands) — a change is a certification of material quality and price/variation; after the employer approves the price, adjust per the approved price; unapproved prices execute the contract-agreed price without adjustment. The core of the calculation is "adjust the material cost only": the material price differential is computed only as (confirmed pre-tax price − original price) x norm resource consumption x quantity; labour, machinery, management fee, profit and other costs are not adjusted, and the price differential carries VAT counted separately into the contract price. Procedurally, quantity and unit price must be submitted to the employer for verification and confirmation before procurement; failure to reply within the time limit is deemed approval upon lapse of the response period (China's deemed-approval rule at settlement); where the substitute brand lowers the grade, quality breach is involved in addition to price adjustment. Dispute appraisal is tiered by whether the employer signed approval before procurement: approved per the approved price; without certification of material quality and price, per the contract-agreed price.

Applicable Boundaries

Applies to BOQ-based pricing employer-contractor scenarios (GB/T 50500-2024) and railway estimates and budgets scenarios (TB 10801-2024). Prime cost (PC) sums for materials are pre-tax prices — do not confuse with provisional sums for nominated specialist subcontract works (wholly replaced at tax-inclusive prices) which follow different rules; where the contract expressly provides otherwise, its provisions prevail; price adjustment presupposes completed certification and sign-off of material quality and price — retrospective certification is easily challenged at settlement.

Further Reading

See GB/T 50500-2024 Clauses 8.4.1, 8.4.5, 8.4.6 and Appendix A.2.5 (pre-procurement submission, deemed approval upon lapse of the response period); GB/T 51262-2017 Clause 5.6.4 (three tiers of material price dispute appraisal); T/ZBD 100.4-2023 Clause 4.4.7 (unit-price adjustment of non-provisional-sum materials); TB 10801-2024 Clause 4.1.2 (decoration materials in the price adjustment (for fluctuation) list, differential = norm resource consumption x the difference between preparation-period and base-period prices), Clause 3.2.5 (norm-based material price for estimating = (original price + freight and handling included in the material price) x (1 + purchasing and custody charges percentage rate)); DB11/T 382-2017 Clause 5.3.3.