Determining re-tendering of provisional-sum specialty works, organization modes, and tax-inclusive price confirmation rules (Implementation Regulations Article 29 + GB/T 50500-2024 Section 8.4)
Specialty works included in the general-contract scope as provisional sums that fall within mandatory-bidding scope and meet scale thresholds (construction single-contract estimate above RMB 4 million, etc.) must be re-tendered; the re-tendering entity and mode (joint tendering / owner tendering / general contractor tendering) should be agreed in the general contract. Price confirmation: where tendering is mandatory, the winning tax-inclusive specialty subcontract price wholly replaces the provisional sum; where not mandatory, per Section 8.10, joint tendering, or contractor inquiry confirmed by the owner. Specialty-work provisional sums are VAT-inclusive—unlike the pre-tax replacement rule for material provisional sums.
Applicable Codes
- 招标投标法实施条例(2018修订)第二十九条
- GB/T 50500-2024 建设工程工程量清单计价标准 第8.4节
- 必须招标的工程项目规定(发改委16号令)第五条
- DB22/T 5036-2020 第3.0.9条
- 交通运输部令2018年第13号 第十九条
Topic Positioning
This card covers re-tendering determination, organization modes, and price confirmation rules for "provisional-sum specialty works" within general-contract projects, connecting the Implementation Regulations of the Bidding Law with GB/T 50500-2024 Section 8.4 contract price adjustment.
Core Conclusions
(1) Determination (dual threshold): specialty works included in the general-contract scope as provisional sums that fall within the statutory mandatory-bidding scope and meet national scale thresholds (construction single-contract estimate above RMB 4 million; combinable purchases meeting thresholds together also require tendering) must be re-tendered by law; below the thresholds, the negotiated-confirmation path applies. (2) Organization: the re-tendering entity should be agreed in the general-contract terms—three practice modes: joint tendering by owner and general contractor; owner tendering (contractor with participation and information rights); contractor tendering (owner with participation and decision rights). (3) Price confirmation: where tendering is mandatory, the tendered tax-inclusive specialty subcontract price wholly replaces the provisional sum to adjust the contract price; where not mandatory, the tax-inclusive specialty price may be determined per Section 8.10, by joint tendering, or by contractor inquiry per contract with owner confirmation. (4) Basis difference: specialty-work provisional sums are VAT-inclusive, wholly replaced by the winning tax-inclusive price; material provisional sums are pre-tax—only the pre-tax material price difference within the all-in unit rate adjusts, not labor, equipment, management fee, or profit—different rules, do not confuse.
Applicable Boundaries
Applies to contract price adjustment for provisional-sum specialty works given in BOQ/general contracts; not applicable to material/equipment provisional sums (different rules). Whether tendering is mandatory depends on project nature (state-controlled funds etc.) and scale thresholds—non-state projects or those below thresholds are not compelled. Provisional sums are limited to cases where requirements were unclear at tendering, design depth insufficient, or specialty subcontracting prescribed—excluding specialty works directly awarded by the owner. Some local supervision rules require joint market price inquiry and negotiated pricing by owner, contractor, and supervisor before implementation.
Further Reading
See Implementation Regulations of the Bidding Law, Article 29 (provisional-sum definition and mandatory tendering); Regulations on Projects Subject to Mandatory Bidding (NDRC Order No. 16), Article 5 (scale thresholds); GB/T 50500-2024 Article 2.0.15 (terminology), Articles 8.4.1, 8.4.5, 8.4.7 (replacement rules and paths); DB22/T 5036-2020 Article 3.0.9 (three tendering modes); Measures for Bidding of Railway Construction Projects (MOT Order 2018 No. 13), Article 19 (agreement on implementing entity); DB11/T 382-2017 Article 5.3.3 (supervisor's price-control procedure for provisional sums).