Statutory minimum periods for tender-document sales and bid submission deadlines (sales period >=5 days; >=20 days from issue to deadline for mandatory-tender projects) and penalties for violation
The sale period of prequalification/tender documents shall not be less than 5 days (Implementation Regulations of the Bidding Law, Article 16 - applies to all tendering); for mandatory-tender projects, the period from issue of tender documents to the bid submission deadline shall not be less than 20 days (Bidding Law, Article 24). Violating the sales, clarification, modification, or submission periods: the administrative supervision department orders correction and may fine up to 100,000 yuan (Implementation Regulations, Article 64(2)).
Applicable Codes
- 《中华人民共和国招标投标法》第二十四条(主席令第21号)
- 《中华人民共和国招标投标法实施条例》第十六条、第六十四条(2018修订)
- 《必须招标的工程项目规定》(国家发展改革委令第16号)
Topic Positioning
Two incompressible statutory time limits in tender procedures - document sales period >=5 days and, for mandatory-tender projects, >=20 days from issue to bid deadline - plus the consequences of compressing them (correction + fine up to 100,000 yuan) and lawful speed-up paths. Directly reusable for questions like "can the sales period or deadline be squeezed to 3 days".
Core Conclusions
(1) Sales-period floor (Implementation Regulations, Article 16): "The tenderer shall sell prequalification or tender documents at the times and places stated in the announcements or invitations. The sale period shall not be less than 5 days." "Charges shall be limited to recovering printing and mailing costs and shall not be for profit." Key: the article is not limited to mandatory-tender projects - any project using tendering (including voluntary) must observe it, so a 3-day sale never works; 5 days are calendar days ("days", not "working days"); some localities add stricter rules (e.g., at least 1 working day within the period) - also comply. (2) Bid-deadline floor (Bidding Law, Article 24): "The tenderer shall allow bidders reasonable time to prepare bids; for projects subject to mandatory tendering, the period from the start of issue of tender documents to the bid submission deadline shall not be less than 20 days." The 20 days bind only mandatory-tender projects (Article 3 of the Law and NDRC Order No. 16 - state-funded projects, international loans, large infrastructure/public utilities, etc.); bid opening coincides with the deadline, so the deadline day is the opening day and cannot be compressed. (3) Penalty (Implementation Regulations, Article 64): "Where the tenderer... (2) sells, clarifies, or modifies documents, or sets submission deadlines for prequalification applications or bids inconsistently with the Law and these Regulations... the administrative supervision department shall order correction and may impose a fine of up to 100,000 yuan." In practice, short periods readily draw bidder complaints; after correction the procedure restarts; e-platform traces cannot be erased. (4) Lawful speed-up: start sales the day the notice is issued with the full 5 days; prepare and review documents, BOQs, and price caps in advance to avoid major post-sale changes (clarifications/modifications are also time-bound and may reset clocks); finish clarifications at least 10 days before the deadline (the statutory objection window).
Applicable Boundaries
- 5-day sales period: all tendered projects, mandatory or not; calendar days; some regions require working days within.
- 20-day deadline: mandatory-tender projects only; others are free of it but still bound by the 5-day sales rule.
- Covers these two limits only; adjacent limits (15-day clarification/modification, 10-day objections) are in cited cards (Regulations Articles 21-22).
- E-tendering leaves full traces; violations cannot be erased after the fact.
Further Reading
See the Bidding Law (Presidential Decree No. 21) Article 24; Implementation Regulations (State Council Decree No. 613, 2018 revision) Articles 16 and 64; scope of mandatory tendering in the "Provisions on Projects Subject to Mandatory Bidding" (NDRC Order No. 16) Article 5 (e.g., construction contracts >=4 million yuan). Statute texts verifiable at the national database (flk.npc.gov.cn); adjacent rules (written clarification/modification notice >=15 days before deadline; objections >=10 days before) in the cited cards.
Keywords
- 招标文件发售期
- 发售期不得少于5日
- 资格预审文件
- tender submission deadline
- 二十日
- 依法必须招标
- 招标投标法第二十四条
- 招标时限违规
- 招标投标法实施条例第六十四条