Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Three statutory time limits for bidding complaints: 10 days to file, 3 working days to accept, 30 working days for the written decision, and the objection-before-complaint procedure (Implementation Regulations Articles 60-61)

Bidders or interested parties complaining of tendering irregularities shall file with the competent administrative supervision department within 10 days of knowing or should have known (Regulations Article 60); the department decides acceptance within 3 working days of receipt and issues a written decision within 30 working days of acceptance (Article 61). Complaints on Articles 22 (prequalification/tender documents), 44 (bid opening), and 54 (publication of results) require a prior objection to the tenderer; the objection-response period does not count into the 10-day complaint period.

Applicable Codes

  • 《中华人民共和国招标投标法实施条例》(国务院令第709号,2019年修订)第六十条、第六十一条

Topic Positioning

The statutory time-limit framework for complaints by bidders and other interested parties against tendering: Implementation Regulations Article 60 (filing period + objection-first) and Article 61 (acceptance and written-decision periods, jurisdiction, rejection rules) - the nationwide cross-sector complaint procedure.

Core Conclusions

(1) Filing period (10 days) - Article 60: "Bidders or other interested parties who consider that tendering activities violate laws or administrative regulations may complain to the competent administrative supervision department within 10 days of knowing or should have known. Complaints shall state clear requests and necessary evidence." Objection first: for matters under Articles 22 (prequalification/tender documents), 44 (bid opening), and 54 (publication of evaluation results), an objection must first be raised with the tenderer; the objection-response period does not count into the 10 days (the objection window does not consume the complaint period). Complaints beyond the period may be refused acceptance. (2) Acceptance (3 working days) and written decision (30 working days) - Article 61:

  • Jurisdiction: where the complainant files the same matter with two or more competent departments, the first to receive handles it.
  • Acceptance: decide within 3 working days of receipt.
  • Decision: written decision within 30 working days of acceptance; time for inspection, testing, appraisal, or expert review is excluded.
  • Rejection: complaints based on fabricated facts, forged materials, or evidence obtained illegally shall be rejected. Units: 10 days are "days" (calendar, from knowing/should have known); 3 and 30 are "working days" (from receipt/acceptance), extended by testing/appraisal time.

Applicable Boundaries

  • Parties: bidders or other interested parties; receiving body: the administrative supervision department.
  • Complaints on Articles 22/44/54 matters require a prior objection to the tenderer - direct complaint is procedurally improper (objection-response time excluded from the 10 days).
  • Complaints need clear requests and necessary evidence; fabricated/forged/illegal-evidence complaints are rejected.
  • Nationwide rules (Implementation Regulations); sectoral departments (railway, water transport, building/municipal) apply the same framework - the specific department depends on project type.

Further Reading

  • Implementation Regulations (State Council Decree No. 709, 2019 revision) Articles 60-61 (identical in the 2018 edition).
  • Objection clauses: Article 22 (documents), 44 (opening), 54 (result publication) - each with different response periods, worth further reading.
  • Related penalties and procedure: Regulations Article 64 et seq. on complaint-handling violations.