Handling tender document vs construction drawing inconsistencies in bidding: statutory objection/clarification deadlines and contractual pricing risk allocation

Objections to tender documents must be raised in writing at least 10 days before the bid deadline; the tenderer replies within 3 days, suspending the process until reply (Implementation Regulations Article 22); clarifications/modifications affecting bid preparation must be notified in writing at least 15 days before the deadline, or the deadline is extended (Article 21). On substance per GB/T 50500-2024 3.4.5/3.4.6: unit-rate contracts—BOQ prevails over drawings, BOQ defects on the tenderer, price adjusted per Section 8.2; lump-sum contracts—contract drawings and specifications prevail, defects borne by the contractor; preliminaries and per-item priced items are always the contractor's regardless of contract type. Not objecting before bidding does not change this allocation.

Applicable Codes

  • 中华人民共和国招标投标法(2017修正)第23条
  • 中华人民共和国招标投标法实施条例(2018修订)第21、22条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第3.4.5、3.4.6条

Topic Positioning

This card answers "how a bidder lawfully handles tender-document requirements inconsistent with construction drawings/BOQ": procedurally via written objection and clarification within statutory deadlines; substantively by determining which prevails and who bears the risk per the contract pricing type.

Core Conclusions

Procedural line (turn inconsistency into written certainty): objections to tender documents must be raised in writing at least 10 days before the bid deadline; the tenderer replies within 3 days of receipt and suspends the process until reply (Implementation Regulations of the Bidding Law, Article 22); clarifications or modifications that may affect bid preparation must be notified in writing to all prospective bidders at least 15 days before the deadline, failing which the deadline is extended (Article 21), and clarification content forms part of the tender documents (Bidding Law Article 23). Drawing/BOQ issues are answered with design or cost-consulting participation, subject to tenderer approval; where multiple clarifications conflict, the later-issued prevails. Substantive line (which prevails): per GB/T 50500-2024 Articles 3.4.5 and 3.4.6—under unit-rate contracts the BOQ prevails; work-item BOQ defects are the tenderer's, contract price adjusted per Section 8.2; under lump-sum contracts the contract drawings and specifications prevail, BOQ defects deemed included in the total price and borne by the contractor; preliminaries and per-item priced items are the contractor's under any contract type. Not objecting before bidding does not change this allocation: unit-rate settlement still adjusts; lump-sum quantity gaps are self-borne.

Applicable Boundaries

Applies to projects subject to mandatory bidding by law and those following bidding procedures by reference; some provinces/cities have local procedural standards (e.g., clarifications subject to tenderer approval) to be followed simultaneously. Substantive rules follow GB/T 50500-2024; under the 2013 edition the allocation is broadly the same with different article numbers. Where the tender document explicitly sets an order of precedence (e.g., "price per drawings"), follow it. Bid documents must not unilaterally correct BOQ quantities, change pricing bases, or add reservations—risking rejection for non-response to substantive requirements.

Further Reading

See Bidding Law of the PRC, Article 23; Implementation Regulations, Articles 21 and 22; GB/T 50500-2024, Articles 3.4.5, 3.4.6 and Section 8.2 (BOQ defect price adjustment); item-by-item defect checking and responsibility detail in the related established cards.