lump-sum contract
- 01
Differences in final account adjustment between lump-sum contracts (fixed total price) and unit-rate contracts (fixed unit rates): treatment rules for quantity changes, BOQ errors, design changes and cost fluctuation, mapped to GB/T 50500-2024 clause numbers
GB/T 50500-2024 uses 'lump-sum contract / unit-rate contract' rather tha…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.6条、第2.0.7条GB/T 50500-2024 第3.3.5条、第3.4.6条GB/T 50500-2024 第4.1.4条、第4.1.6条、第6.1.7条2026-11-08 - 02
Checking order when pipe specifications on the drawings conflict with the BOQ description: the dimension figures on drawings govern and conflicts are clarified through drawing review; at pricing level, unit-rate contracts follow the bill of quantities and lump-sum contracts follow the contract drawings and specifications
The test runs on two levels. (1) Annotation level: dimensions on drawing…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.4.5条、第2.0.27条、第8.2节GB/T 50856-2024 通用安装工程工程量计算标准 第4.2.4条、App. K Table K.1.1GB/T 50106-2010 建筑给水排水制图标准 第2.4.2条2026-11-08 - 03
Whether the employer may refuse to pay for additional works when the actual investment in a government-funded project exceeds the approved estimate: the estimate as an administrative control instrument, who bears the duty to apply for an estimate adjustment, attribution of the causes of overruns, and risk allocation under an EPC lump-sum contract
In principle it may not. The verified investment estimate is an administ…
《政府投资条例》(国务院令第712号)第十二条、第二十二条、第二十三条、第三十四条《房屋建筑和市政基础设施项目工程总承包管理办法》(建市规〔2019〕12号)第十五条、第十六条、第二十六条《工程建设项目施工招标投标办法》(七部委第30号令)第六十四条2026-10-31 - 04
Deciding claims to adjust the contract price for omitted items in the tender BOQ (BOQ errors) during performance: risk is allocated by the contract pricing method and the BOQ section in which the omission falls - omission from the work-section bills under a unit-rate contract may rest with the employer and be adjusted under section 8.2; a lump-sum contract is in principle not adjusted (except provisional quantity items); the bill of preliminaries is always the contractor's responsibility - with judicial limits and points of procedure and proof
Whether adjustment is possible depends not on the omission itself but on…
《建设工程工程量清单计价标准》GB/T 50500-2024 第3.1.8、3.5.4、4.1.4、6.1.6、6.1.7、8.1.3、8.2.1、8.2.2、8.2.3、8.9.1、8.9.2条《中华人民共和国民法典》第五百一十条、第五百三十三条、第七百九十三条最高人民法院法释〔2020〕25号《关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十九条、第二十二条2026-10-29 - 05
Defining and selecting construction contract price forms: unit-rate, lump-sum and cost-plus contracts chosen by design depth, technical difficulty, time and pricing risk
GB/T 50500-2024 clause 3.4.1 fixes the selection: clear requirements, co…
GB/T 50500-2024 第2.0.6、2.0.7、2.0.8条GB/T 50500-2024 第3.1.8条GB/T 50500-2024 第3.3.1、3.3.2、3.3.3、3.3.5条2026-10-18 - 06
Choice criteria for re-measurable / lump-sum / cost-plus contracts under GB/T 50500-2024, the coverage of lump sums, and the precedence between contract drawings and the BOQ on inconsistency (Articles 3.4.2, 3.4.6)
Per GB/T 50500-2024 Article 3.4.2, the employer chooses the pricing mode…
GB/T 50500-2024 第3.4.2条GB/T 50500-2024 第3.4.6条https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_6186304e164c4c4982904f8734983235.html2026-10-11 - 07
Quantity basis for cost estimation when BOQ quantities are overstated: costs follow actual quantities (taken off from the drawings) rather than BOQ quantities, and the effect of overstated BOQ quantities on the contract price (re-measurement and adjustment under re-measurable contracts / no adjustment under lump-sum contracts)
Cost estimation must be based on actual quantities (the drawing-based qu…
GB/T 50500-2024 第4.1.5、4.1.6、7.2.1、7.2.2、7.4.1、8.2.1、8.2.3条《国营企业成本管理条例》(国发〔1984〕34号)第十七条DB14/T 1319—2021 App. A.1.32026-10-02 - 08
Deciding the pricing type of a contract silent on its price form (colloquially the "fully open contract") and the corresponding scope of quantity and price review
"Fully open contract" is not a legal concept; at normative level only fi…
建设部令第107号《建筑工程施工发包与承包计价管理办法》第十二条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.6、2.0.7、2.0.8、3.4.6条GB/T 51095-2015 · Code for construction cost consultation 第8.2.5条2026-09-26 - 09
Settlement where a design change reduces the quantities: adjustment rules for unit-rate and lump-sum contracts, compensation for outright cancellation of an item, and the linkage of preliminaries
The settlement principle for reduced quantities is "re-measure against t…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 10
Liability for errors or omissions in the tender BOQ: GB 50500-2013 vs GB/T 50500-2024 (2013 Clause 4.1.2 mandatory provision vs 2024 Clause 3.1.8 split by unit-rate/lump-sum contract)
GB 50500-2013, Clause 4.1.2 (mandatory provision): 'the tender BOQ must…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.1.8、4.1.4、6.1.6、8.2.1、8.2.3条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第4.1.2条(已废止)住房城乡建设部公告2024年第212号(2024-11-26,www.mohurd.gov.cn)2026-09-25 - 11
Handling tender document vs construction drawing inconsistencies in bidding: statutory objection/clarification deadlines and contractual pricing risk allocation
Objections to tender documents must be raised in writing at least 10 day…
中华人民共和国招标投标法(2017修正)第23条中华人民共和国招标投标法实施条例(2018修订)第21、22条GB/T 50500-2024 建设工程工程量清单计价标准 第3.4.5、3.4.6条2026-09-25 - 12
Checking drawing-BOQ contradictions (bill of quantities defects) before bid pricing, and responsibility boundaries (GB/T 50500-2024)
Drawing-BOQ contradictions are "BOQ defects" (extra items/omissions/mism…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 13
Material price adjustment channels under fixed lump-sum contracts: no adjustment within the agreed risk band, adjustment beyond the risk band, mandatory adjustment for statutory causes
Under a fixed lump-sum contract, cost fluctuations within the agreed ris…
GB/T 50500-2024 第3.3.1~3.3.3、3.3.5、8.7.1~8.7.6条GB/T 50500-2024 App. A、App. G.2建设部令第107号 第12条2026-09-25 - 14
Statutory boundaries of what a "lump-sum price" actually covers: dual quantity-and-price lump sums and non-lumpable events (GB/T 50500-2024 / GB/T 50875-2013)
In practice a "lump-sum price" corresponds to a fixed total price, whose…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准GB/T 51262-2017 建设工程造价鉴定规范2026-09-25 - 15
Deducting unexecuted (unbuilt) items from the contract price: disallowance rules at final account (re-measurable vs lump-sum contract bases, linked deductions, and contractor compensation)
Unexecuted work must be disallowed from the contract-price BOQ: under re…
T/ZBD 100.5-2023 第3.1.4~3.1.6条GB/T 50500-2024 第8.9.1/8.9.2/8.9.8条GB/T 50500-2024 第8.5.3/8.6.5条2026-09-25 - 16
Can a practice omitted from the BOQ (missing item) but mandatorily required by codes be deducted at the final account? - the judgment chain of contract type x pricing classification (GB/T 50500-2024) and the judicial approach to missing-item risk
A practice omitted from the BOQ but mandatorily required by codes is not…
GB/T 50500-2024 建设工程工程量清单计价标准(第3.1.8、4.1.4、6.1.5~6.1.7、8.2.1~8.2.3、8.9.1、10.3.13条)中华人民共和国建筑法(2019修正)第五十八条建设工程质量管理条例(2019修订)第二十八条2026-09-25 - 17
No price adjustment for BOQ defects in lump-sum contracts (BOQ quantities below drawings): the four-layer rule of GB/T 50500-2024 and the reversal of the 2013 edition's Clause 8.3.1 measure-and-value rule
Under GB/T 50500-2024 (effective 2025-09-01; GB 50500-2013 simultaneousl…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.7条/3.4.6条/4.1.6条/7.2.2条/7.4.1条/7.4.3条GB 50500-2013 建设工程工程量清单计价规范 第8.3.1条/8.3.2条(已废止)住建部发布公告:https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_6186304e164c4c4982904f8734983235.html2026-09-25