Checking drawing-BOQ contradictions (bill of quantities defects) before bid pricing, and responsibility boundaries (GB/T 50500-2024)

Drawing-BOQ contradictions are "BOQ defects" (extra items/omissions/mismatched characteristics/quantity deviations, Article 2.0.27). Responsibility by pricing mode: unit-rate contracts—work-item BOQ by the tenderer (Article 6.1.6, defects adjusted at settlement per Section 8.2); lump-sum contracts—by the bidder (Article 6.1.7, may supplement the priced BOQ and bears the difference); preliminaries always the bidder's (Article 6.1.5); per-item pricing is lump sum, unadjusted at settlement (Article 6.2.3). Check by risk order: item characteristics, quantities, completeness of items, units and measurement rules, work-content interfaces, drawing versions, preliminaries, provisional sums.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准

Topic Positioning

An operational framework for checking "drawing vs BOQ" contradictions before bid pricing: first allocate BOQ defect responsibility by contract pricing mode, then check key contradiction points in risk order with handling strategies, per GB/T 50500-2024 Standard for Measurement and Valuation of Construction Works by Bills of Quantities.

Core Conclusions

"Drawing-BOQ contradiction" is the term "BOQ defect" (Article 2.0.27): extra items, omissions/misdescriptions, mismatched item characteristics, and quantity deviations. Responsibility by pricing mode: under unit-rate contracts the completeness and accuracy of work-item BOQs rest with the tenderer (Article 6.1.6), defects adjusted at settlement per Section 8.2—the bidder still reviews to price reasonably and keep the adjustment channel open; under lump-sum contracts the bidder is responsible (Article 6.1.7)—may request written clarification, or supplement and price the priced BOQ itself, bearing quantity gaps and omissions; preliminaries are always the bidder's under either mode (Article 6.1.5); per-item priced items are lump sums, unadjusted at settlement (Article 6.2.3)—their work content must be checked item by item against drawings. Check in risk order: (1) item characteristics vs drawing details; (2) quantities vs recalculation (spot-check large-volume items like earthwork/concrete/rebar); (3) completeness of items (omissions/extra items); (4) units and measurement rules (per national and industry measurement standards); (5) work content and construction interfaces (embedded parts, additional layers, terminations); (6) drawing versions and changes (check version numbers against the drawing index, review opinions, Q&A minutes); (7) preliminaries supplemented per one's own construction scheme; (8) provisional sums/provisional totals copied unchanged—specialty work interfaces and coordination-fee basis.

Applicable Boundaries

Applies to pre-pricing review of BOQ tenders under the GB/T 50500-2024 system. Lump-sum review is the bidder's own risk defense line—the most urgent; unit-rate review serves reasonable pricing and the settlement adjustment channel. Exception: unit-priced items stated as "provisional quantities" (not adjusted for defects). Where tender documents or sector rules provide otherwise, those prevail.

Further Reading

See GB/T 50500-2024: Article 2.0.27 (terminology), Article 4.1.4 (BOQ compilation matching contract mode), Articles 6.1.5-6.1.7 (bidder review and responsibility), Article 6.2.3 (per-item lump-sum pricing), Section 8.2 (price adjustment for BOQ defects under unit-rate contracts); building measurement rules per GB/T 50854-2024.