lump-sum (fixed-inclusive) price
- 01
Checking drawing-BOQ contradictions (bill of quantities defects) before bid pricing, and responsibility boundaries (GB/T 50500-2024)
Drawing-BOQ contradictions are "BOQ defects" (extra items/omissions/mism…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 02
Preliminaries bid at zero - can an increase be claimed at final account? (principle-plus-exception framework, with clarification of Clause 10.3.3)
Ordinary preliminaries bid at zero constitute a lump-sum price and are n…
GB/T 50500-2024 建设工程工程量清单计价标准(第3.2.5、3.3.7、6.1.5、6.2.3、6.2.6、7.3.1、7.4.4、10.3.3条)TB 10801-2024(铁路口径安全生产费,第3.11.11条)2026-09-25 - 03
Classifying BOQ items suited to high vs low pricing in unbalanced bidding, and the three-dimensional decision logic
Whether to bid high on an item turns on three dimensions: early-stage it…
GB/T 50500-2024 建设工程工程量清单计价标准工程建设项目施工招标投标办法(30号令)DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范2026-09-25 - 04
Material price adjustment channels under fixed lump-sum contracts: no adjustment within the agreed risk band, adjustment beyond the risk band, mandatory adjustment for statutory causes
Under a fixed lump-sum contract, cost fluctuations within the agreed ris…
GB/T 50500-2024 第3.3.1~3.3.3、3.3.5、8.7.1~8.7.6条GB/T 50500-2024 App. A、App. G.2建设部令第107号 第12条2026-09-25 - 05
Statutory boundaries of what a "lump-sum price" actually covers: dual quantity-and-price lump sums and non-lumpable events (GB/T 50500-2024 / GB/T 50875-2013)
In practice a "lump-sum price" corresponds to a fixed total price, whose…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准GB/T 51262-2017 建设工程造价鉴定规范2026-09-25