Statutory boundaries of what a "lump-sum price" actually covers: dual quantity-and-price lump sums and non-lumpable events (GB/T 50500-2024 / GB/T 50875-2013)

In practice a "lump-sum price" corresponds to a fixed total price, whose core is the "dual lump sum of quantities and price": quantity risk within the drawings, cost fluctuation within the agreed band (5% absent agreement), and the contractor's own management risks are self-borne; but variations, changes in laws and policies, fluctuation beyond the band, owner-caused events, force majeure and government-priced materials are not waived by the word "lump sum". The standard prohibits clauses imposing uncapped risk allocation to one party, such as "all risks" (GB/T 50500-2024 Article 3.3.1).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50875-2013 工程造价术语标准
  • GB/T 51262-2017 建设工程造价鉴定规范
  • 计基〔1984〕2008号 基本建设项目投资包干责任制办法

Topic Positioning

"Lump-sum price" is not a statutory term; in practice it usually corresponds to a fixed total price (closed price). This card delimits what a lump sum "covers and does not cover" and the legal floor against "uncapped lump-sum" clauses, for understanding risk allocation under lump-sum contracts and grounding price-adjustment claims.

Core Conclusions

Inside the lump sum (lump-sum contract): (1) quantity differences within the drawing scope—the contractor's own quantity takeoff is the final quantity, and no adjustment lies for differences (except variations); (2) BOQ errors / omissions under lump-sum contracts (omitted or missing items, mismatched characteristics) are borne by the contractor (except provisional quantities under unit pricing); (3) accuracy and completeness of the bill of preliminaries rest with the contractor—underpriced or zero-priced preliminaries are self-borne (except non-competitive costs such as mandatory health, safety and environmental (HSE) provisions); (4) cost fluctuation within the agreed band is borne by the contractor; absent agreement, fluctuation within 5% is deemed the contractor's risk; (5) the contractor's own management risks (scheme changes, equipment use, organisational level, self-caused acceleration or suspension). Outside the lump sum: variations; changes in laws, regulations and policies; fluctuation beyond the agreed band (beyond 5% absent agreement) (adjusted per Appendix A, with the price difference carrying value added tax (VAT) only, and no management fee or profit); owner-caused events; force majeure; and government-priced/guided materials—even if the contract provides for no adjustment, the statutory rules still govern (GB/T 51262-2017 Article 5.6.2). Legal floor: the scope of pricing risk must not be agreed by clauses imposing uncapped risk allocation to one party, such as "all risks" or similar wording; risks must be stated in the tender documents and the contract as to content, scope or band, reflecting reasonable sharing (GB/T 50500-2024 Article 3.3.1). Historical origin: the investment-responsibility regime under Ji Ji [1984] No. 2008—"lump-sum investment, programme, quality, main material quantities and formation of comprehensive production capacity"—shares the same core as today's lump sum.

Applicable Boundaries

Applies to understanding risk allocation and to dispute handling under owner-contractor lump-sum contracts. Distinguish a "total-price lump sum" (covering quantity differences) from a "unit-price lump sum" (only rates lumped, quantities re-measured); where the contract attaches a schedule of price-adjustable key materials (Appendix G.2), the materials listed therein are adjustable beyond the band and are not excluded by the word "lump sum". Lump-sum clauses cannot exclude statutory adjustment events—variations, changes in laws and regulations, owner fault, force majeure. In appraisal, the contractual agreement takes precedence; where the agreement is unclear, the matter is referred to the entrusting party for decision.

Further Reading

GB/T 50500-2024 Article 2.0.7 (definition of lump-sum contract), Article 3.3.1 (prohibition of uncapped risk allocation to one party), Article 3.3.3 (list of risks borne by the contractor), Article 3.3.5 and Section 8.7 (price adjustment for fluctuation and computation of the price difference), Appendix A (adjustment methods), Appendix G.2 (schedule of price-adjustable key materials); GB/T 50875-2013 Articles 3.3.4, 3.3.6–3.3.8 (contract price and the three contract types); GB/T 51262-2017 Article 5.6.2 (appraisal rules for price disputes); Ji Ji [1984] No. 2008 Article 9 (the "five lump sums" of investment responsibility).