Classifying BOQ items suited to high vs low pricing in unbalanced bidding, and the three-dimensional decision logic

Whether to bid high on an item turns on three dimensions: early-stage items, predicted quantity increases, and re-measured/provisional-quantity items suit high prices (capturing time value of money and quantity spreads); late-stage items, predicted quantity decreases, per-item lump sums, and bulk core items do not (no cashing channel or likely to trigger clarification). Three floor lines: total price unchanged, not below cost, unit rates locked as the settlement basis once submitted.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • 工程建设项目施工招标投标办法(30号令)
  • DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范

Topic Positioning

This card answers the selection question in unbalanced bidding—"which BOQ items suit high prices and which do not," giving the three-dimensional decision logic and item-by-item applicability classification for screening during bid preparation.

Core Conclusions

Whether an item merits a high price turns on three dimensions: (1) time value of money—early works (earth and rock, piling, excavation support, foundations) bid high to recover cash earlier, late works (finishing, M&E commissioning, landscaping) bid low to offset the total; (2) quantity change prediction—items expected to increase (earth/rock where drawing depth is insufficient, ground treatment with unclear geology, high-frequency change spots like utility relocation) bid high to capture the quantity spread; items expected to decrease (provisional works, inflated quantities) bid low; (3) settlement mode—re-measured/provisional-quantity items (daywork, provisional estimates, self-performed portions of specialty provisional sums) bid high to directly amplify the settlement amount; per-item lump sums are unadjusted at settlement—no cashing channel for high prices, must be priced realistically. Taboos: abnormally high bulk core items easily trigger price-reasonableness clarification (3.5.3); adjustable-price materials and installation of owner-supplied materials bid high are easily detected and not advantageous. Three floor lines: total price unchanged (high prices must be offset by low ones); never below cost; once submitted, unit rates prevail as the settlement basis per Article 53 of Order No. 30.

Applicable Boundaries

Applies to construction bid preparation under BOQ pricing (GB/T 50500-2024 system); quantity predictions rely on the bidder's judgment of drawings and geological data—wrong predictions backfire doubly ("should increase didn't, should decrease didn't"); extreme highs/lows may be adjusted at bid cleaning or deemed malicious unbalanced bidding; local refinements (e.g., Guangdong DBJ/T 15-153-2019) prevail; the strategy itself is lawful but must withstand bid-cleaning and audit scrutiny.

Further Reading

Classification basis in GB/T 50500-2024 Article 3.5.3 (price reasonableness clarification), Article 6.2.3 (per-item lump-sum pricing), Article 8.9.1 (unit-rate determination for changes); price correction principles in Article 53 of the Measures for Bidding of Construction Projects (Order No. 30); unbalanced bidding evaluation and adjustment in DBJ/T 15-153-2019 Article 6.10.3.