Choice criteria for re-measurable / lump-sum / cost-plus contracts under GB/T 50500-2024, the coverage of lump sums, and the precedence between contract drawings and the BOQ on inconsistency (Articles 3.4.2, 3.4.6)

Per GB/T 50500-2024 Article 3.4.2, the employer chooses the pricing mode per the design depth of tender drawings, technical difficulty, scale, implementation plan, BOQ compilation time and pricing risk: works with clear requirements, controllable measurement and pricing and low fluctuation risk suit lump-sum contracts; unclear requirements, high difficulty and many uncontrollables suit re-measurable (unit-rate) contracts; particularly urgent or complex, high-risk works suit cost-plus. Article 3.4.6: the lump sum covers all costs of completing the contract works per the drawings and specification under the tender documents; the priced BOQ merely reflects the price build-up, BOQ-defect prices deemed included, its unit rates usable for pricing variations and additional works, provisional-quantity items priced under re-measurable rules; on inconsistency during performance, the re-measurable contract follows the BOQ, the lump-sum contract the drawings and specification.

Applicable Codes

  • GB/T 50500-2024 第3.4.2条
  • GB/T 50500-2024 第3.4.6条
  • https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_6186304e164c4c4982904f8734983235.html

Scope of the question

GB/T 50500-2024 Articles 3.4.2 and 3.4.6: when lump-sum, re-measurable or cost-plus contracts suit, what the lump sum covers, and which prevails when contract drawings disagree with the priced BOQ. For choosing contract modes and judging lump-sum / unit-rate settlement disputes.

Core conclusions

  1. Choice basis (Article 3.4.2): the employer may choose re-measurable or lump-sum pricing per the design depth of the tender drawings, technical difficulty, scale, implementation plan, BOQ compilation time and pricing risk. The commentary: clear requirements, controllable measurement and pricing and low fluctuation risk suit lump-sum; unclear requirements, high difficulty, many uncontrollables and large risk suit re-measurable; especially urgent works without time for detailed planning and full negotiation, or especially complex, high pricing-risk works, suit cost-plus.

  2. Lump-sum coverage (Article 3.4.6): the contract total covers all costs of completing the contract works per the drawings and specification under the tender documents. The priced BOQ only reflects the build-up of the total; BOQ-defect prices are deemed included. The priced BOQ's unit rates form part of the contract documents, applied per contract to pricing variations and additional works. Provisional-quantity unit-priced items in a lump-sum BOQ price under the re-measurable rules.

  3. Precedence on inconsistency (Article 3.4.6): in a re-measurable contract, where drawings disagree with the tender work-item BOQ, the BOQ prevails; in a lump-sum contract, where the drawings and specification disagree with the priced BOQ, the drawings and specification prevail.

Applicability limits

Applies to choosing pricing modes at procurement and to interpreting and adjusting prices during performance. A lump-sum contract is not uncapped: though BOQ-defect prices are deemed included, the priced BOQ's unit rates still price variations and additional works, and provisional-quantity items follow re-measurable rules. The precedence rule settles only which document governs an inconsistency; it does not exclude other agreed precedence, and express terms prevail. EPC and other delivery modes do not follow this article.

Further reading

GB/T 50500-2024: Articles 3.4.2 (choice factors), 3.4.6 (lump-sum coverage, role of the priced BOQ, precedence); the matching rules on risk allocation and BOQ-defect liability: Articles 3.3.1-3.3.3 and 3.1.8. Publication notice: MOHURD https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2024/art_6186304e164c4c4982904f8734983235.html