Determining quantities where drawing dimensions are incomplete: three-tier fallback plus provisional quantities at the tender/preparation stage; re-measurement plus five-tier progressive determination at the settlement stage
Where drawings are incomplete, quantities are determined along two tracks. At the preparation stage, values are taken by the three-tier fallback "design documents -> approved project execution plan (construction methodology and site organization) -> code/quota norm measurement rules"; where accurate measurement remains impossible, the item description (work item specification) notes "provisional quantities" and an estimated quantity is provided (GB/T 50500-2024 clauses 4.1.4, 4.1.6). At the settlement/dispute stage, re-measurable (unit-rate) contracts are re-measured against the final construction drawings (not the as-built drawings); where the drawings cannot reflect the work, determination follows the five-tier progression from certification and sign-off to site inspection (T/ZBD 100.4-2023 clauses 4.3.5, 4.3.6).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB 50861-2013 城市轨道交通工程工程量计算规范
- T/ZBD 100.4-2023 建设工程造价鉴定作业指引
- T/ZBD 100.5-2023 建设工程结算审核作业指引
- DB11/T 638-2016 房屋修缮工程工程量计算规范
- SJG 111.1-2022 城市地下综合管廊工程消耗量标准
Topic Positioning
Determining quantities where drawing dimensions are incomplete: three-tier fallback plus provisional quantities at the preparation stage; re-measurement plus five-tier progressive determination at the settlement stage.
Core Conclusions
Preparation stage: values are taken by the three-tier fallback "design documents -> approved project execution plan (construction methodology and site organization) -> code/quota norm measurement rules"; where working-space width or slope coefficients have no design value, look them up in tables (SJG 111.1-2022 clause 1.2.3; TB/T 10831-2024 Tables 5/6). Where tender drawings do not support accurate measurement, the item description (work item specification) notes "provisional quantities" and an estimated quantity is provided, with the actual quantity adjusted per the rules of the re-measurable (unit-rate) contract (GB/T 50500-2024 clauses 4.1.4, 4.1.6); item descriptions may be completed with "see standard drawing collection/drawing no. xx" (GB 50861-2013 clause 4.2.4, mandatory); flowing sand, silt and the like not clarified by design may be estimated and confirmed at settlement by site instruction / variation record (DB11/T 638-2016 A.2.1 note 6). The measuring yardstick is always the BOQ/quota norm appendix rules plus the construction drawings (GB 50861-2013 clause 4.2.5, mandatory). Settlement/dispute stage: under re-measurable (unit-rate) contracts, the estimated quantities in the BOQ and the tender-issued quantities cannot serve as the basis for settlement authentication; re-measure against the final construction drawings (not the as-built drawings) (T/ZBD 100.4-2023 clause 4.3.5); where the drawings cannot reflect the work, determine by the five-tier progression "certification and sign-off by both parties -> certification and sign-off by one party plus the supervisor -> re-check or site inspection -> site-inspection measurement -> no measurement, noting the item as impossible to authenticate" (clause 4.3.6); final account review re-checks against the actually-constructed drawings and corrects missing or omitted items (T/ZBD 100.5-2023 clause 3.1.6).
Applicable Boundaries
Applies to employer-contractor measurement and settlement under national measurement standards or industry quota norms; does not apply to lump-sum contract package items (except provisional-quantity items). For disputes over rule versions, first follow the contract agreement, then the national standard matching the contract category (T/ZBD 100.4-2023 clauses 4.3.1, 4.3.2).
Further Reading
See GB/T 50500-2024 clauses 4.1.4-4.1.6, 8.3.2; GB 50861-2013 clauses 4.2.4, 4.2.5; T/ZBD 100.4-2023 clauses 4.3.1, 4.3.2, 4.3.5, 4.3.6; T/ZBD 100.5-2023 clause 3.1.6; DB11/T 638-2016 A.2.1; SJG 111.1-2022 clause 1.2.3 provides worked fallback tables.