Earthwork excavation quantity take-off (measurement): working space width, slope coefficients, and haulage (disposal of surplus excavated material) quantities
Earthwork excavation quantity take-off (measurement) follows the three-level priority "design → project execution plan (construction methodology and site organization) → default values in standard appendix tables"; excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation, backfill in the as-completed volume; working space widths and slope coefficients are taken from tables by foundation material, soil class, and machine working position, and no slope is calculated where shoring boards are placed; the quantity for disposal of surplus (excavated) material = excavated volume − backfill reuse volume, haulage being measured in the natural-state volume with no additional bulking factor.
Applicable Codes
- GB/T 50854-2024
- TB/T 10831-2024
- SJG 111.1-2022
- SJG 84-2020
- GB 50861-2013
Topic Positioning
The three cores of earthwork excavation measurement — determination methods and volume bases for working space width, slope, and haulage (disposal of surplus excavated material) quantities, applicable to earth and rock works for building works, municipal works, rail transit, utility tunnels, railways, and other sectors.
Core Conclusions
- Volume basis: excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation; backfill in the as-completed volume after backfilling. Under the BOQ basis (GB/T 50854-2024) no density-state conversion applies between excavation and backfill; under the quota-norm rate build-up basis, conversion factors apply (natural in-situ 1.0 ≈ loose 1.3, compacted fill 0.87, loose fill 1.08).
- Priority: where design documents specify, follow the design → where not, follow the approved project execution plan (construction methodology and site organization) → where neither, follow the default values in the standard/quota-norm appendix tables.
- Working space width (per face): formwork for concrete foundations 400 mm, formwork for blinding 150 mm, brick foundations 200 mm, rubble/dressed-stone foundations 250 mm, vertical mortar damp-proof courses 400 mm, waterproof/anti-corrosion layers 1000 mm, plus 100 mm where shoring boards are placed; strip foundations with scaffolding 1500 mm on one side, isolated foundations 450 mm on each of the four sides; large open excavation of the pit with slope support or piling inside the pit 2000 mm. Pipe-trench working space is taken in bands by pipe structural width (outer edge of the base where a pipe cradle exists, otherwise the pipe outer diameter).
- Sloping: slope is calculated only where the excavation depth exceeds the slope starting point (Class 1–2 soils 1.20 m, Class 3 soil 1.50 m, Class 4 soil 2.00 m); manual excavation 1:0.50–1:0.25; machine excavation by working position — in the pit / on the pit / in the trench (e.g., Class 1–2 soils 1:0.33 / 1:0.75 / 1:0.50 respectively); where shoring boards are placed, no slope is calculated; mixed soils are weighted by depth percentage; sloping starts from the bottom level of the foundation (including blinding); overlapping quantities at slope intersections are not deducted.
- Haulage: for backfill with native soil, the quantity for disposal of surplus (excavated) material = excavated volume − backfill volume; for replacement fill, = excavated volume; haulage is measured in the natural-state volume before excavation, with the bulking factor already included in the quota norms and not counted again.
Applicable Boundaries
Applies to earth/rock measurement across industries, but specific appendix values follow the regional/industry quota norms applicable to the project (GB national, SJG, and TB railway systems differ only slightly); distinguish the BOQ measurement basis from the quota-norm rate build-up basis; an approved project execution plan prevails over standard defaults; shoring and sloping are mutually exclusive and cannot both be counted.
Further Reading
See GB/T 50854-2024 Appendix A Earth and Rock Works A.4.6 (working space width Tables A.4.6-1/2); TB/T 10831-2024 Railway Works Budget Quota Manual (China Railway), Vol. 10 Building Works, volume notes XI (Table 4 volume conversion, Table 5 working space, Table 6 slopes); SJG 111.1-2022 Consumption Standard for Urban Utility Tunnels Vol. 1, 1.2.3 (sloping, shoring boards, working space); SJG 84-2020 Municipal Maintenance Consumption Standard Vol. 2, 7.2.9 (haulage quantities and slope rules).
Keywords
- 土方开挖
- 工作面宽度
- 放坡系数
- 放坡起点
- disposal of surplus (excavated) material
- 余土外运
- natural in-situ (undisturbed) volume
- 体积折算系数
- quantity take-off (measurement)
Cited By
- ←
Data-taking rules of earthwork and rockwork budget quotas: classifying trenches and pits against general earthwork, classifying dry and wet soil, muck and frozen soil, items already comprehensively included in the quota and not adjustable, determination and successive-multiplication rules for efficiency-reduction conversion coefficients (wet soil, excavation within shoring, excavation between piles, local deepening, deep excavation, vertical soil transport, dynamically compacted ground, etc.), uphill-haul efficiency reduction and allowable over-excavation, and dewatering and shoring to be calculated separately
Earthwork quota data-taking starts with three preliminary steps: (1) classify trench or pit (base width up to 7 m and base length over 3 times the base width, or base length up to 3 times the base width and base area up to 150 m2 - beyond these limits, and not being site levelling, it is general earthwork); (2) split dry and wet soil at the normal groundwater level given in the geological survey data - where dewatering is adopted, the post-dewatering level is the normal water level and dewatering costs are calculated separately; (3) first remove items already comprehensively included and not adjustable (machine excavation already includes manual cleaning of residual layers up to 0.30 m thick on base and slopes, efficiency reduction for loaded uphill hauls at gradients up to 15%, and pipe laying already includes ordinary trench-side shoring). Efficiency reductions then follow the quota coefficients: wet soil by hand labour x1.18; wet soil by machine labour and machines x1.15; hand-dug trenches and pits within shoring x1.43 on labour; soil between piles x1.25 on labour under hand quotas (x1.10 on labour and machines under machine quotas); locally deepened trenches and pits x1.25 on labour and machines; vertical soil transport by hand x1.50; excavation on dynamically compacted ground x1.15; hand excavation beyond 6 m x1.15 per additional metre; where two coefficients coexist they are multiplied successively. Coefficients are taken from the notes of the quota volume actually applied and must not be mixed across volumes.
- ←
The grid method for earthwork balance sheets - the step formulas, cut-and-fill closure checks, and the terrain contrast with the cross-section method (grid spacing, volume-state conversion, and the source of the economic haul distance)
Three passes complete the sheet: grid at 10~40m (20m preferred), corner natural and design levels with the working height h = design - natural ('+' fill, '-' cut), zero points by interpolation joined into the zero line, cell-by-cell net cut and fill listed apart; convert all to one volume state (fill compacted / 0.87 = about x 1.15 to natural dense) and close on 'cut - fill = spoil - borrow', the in-sheet closure being 0 (rounding residue only); computation by one and checking by another, a difference within 3% of the original submits the original, beyond 3% the cause is traced and recomputation follows; the cross-section method, less precise, suits ribbon ground of stronger relief (off-site roads, rail subgrades, trench runs) with sections at 50m (scheme / preliminary) and 20m (construction drawings).
- ←
Classifying divergence between the design earthwork balance and the actual site balance, allocating responsibility among the four parties, and the cost adjustment pathway (with the chain of evidence and the normative basis)
GB 50201-2012 clause 4.1.3 sets the division-of-duty baseline: the balance figures are 'basic balance data put forward by the designer, on which the contractor then performs balance calculations according to the actual situation ... with multiple balance adjustments further made during construction'; hence divergence between the actual and the design table does not of itself constitute a variation or ground a claim. The divergence must first be characterised into three types - measurement-basis type (conversion factors not unified; whoever miscalculated corrects it), factual type (original ground levels / geology / design omissions; allocated by cause) and fault type (the defaulting party bears it, including enlarged losses) - and responsibility then allocated item by item by cause: erroneous original data from the employer, adverse physical conditions, instructed variations and insufficient design documents are borne externally by the employer (which may recover from the investigator or designer), while the contractor bears its own method adjustments, over-excavation and what it should have foreseen.
- ←
Earthwork volume conversion coefficients and spoil haul-off disposal estimation (loose / loose-fill / natural-dense / compacted conversion)
Excavation and haul are measured by the pre-excavation natural in-situ (undisturbed) volume, backfill by the post-backfill volume, and different states are converted by coefficients (natural in-situ (undisturbed) 1.00 <-> loose 1.30 <-> loose fill 1.08 <-> compacted 0.87); total spoil disposal Ve = lambda-c x Vc - lambda-f x Vf (JGJ/T 498-2024), with lambda-c soil 1.30 / rock 1.54 / sand-rock mixture 1.07.
- ←
Preventing double counting of earthworks where trench, manhole pit and spread foundation pit overlap: physical overlap versus intersection of battered faces, assigning the manhole-length section by the larger cross-section, the pit deepening increment, pipe-joint working pits already included, and one trench width taken once for multi-pipe runs
Three tests prevent double counting: (1) physical overlap (the same space excavated twice) is counted once, and battered-face intersections are expressly 'not deducted' by most quota manuals (Hunan 2025 IV.4; SJG 111.1-2022 table 1.2.3-1 note 2; SJG 84-2020 table 7.2.9 note 1); (2) the BOQ quantity (GB/T 50857-2024, drawn dimensions plus working space, no batter) and the quota quantity (working space plus batter) are computed independently - never mix then deduct; (3) the manhole-length section is assigned by section size: if A-pit is no less than A-trench the section counts as pit and the trench length is reduced by that section, if A-pit is smaller the manhole length merges into the trench and no pit is listed, the total taking the max, not the sum; where the pit floor lies below the trench floor, the deepening increment delta V = A-pit x (H-pit - H-trench) is added; pipe-joint working pits and manholes along the line are covered by 2.5% of the trench earth and rock quantity (1.5% for wells and joint pits in the railway volume 12), not listed separately.
- ←
Earth and rock haulage pricing: haul distance measured as the nearest distance from the excavation centroid to the fill or spoil centroid, on-site transport already included in excavation line items, off-site transport listed separately as disposal of surplus material and banded as basic haul plus increments, the loading charge taken only once, and hoisting soil from deep excavations charged separately as vertical transport
Earth and rock haul distance is measured as the shortest and nearest distance between the centroid of the excavated (or demolished) material and the centroid of the fill area or the spoil (stockpile) area, the centroid positions being fixed by the approved project execution plan; it means the shortest distance along a traversable haul route, not the straight line between two points. The work content of excavation BOQ items includes only on-site transport; off-site haul must be listed separately as 'disposal of surplus material' (covering loading and haul from the site to the disposal point), and the quota bands it as 'basic haul + increments' (manual cartage with a 20m basic band plus 10m/20m increments; mechanical cartage with a basic band within 1km plus 1km per increment; loader loading and carting of loose soil applying only within 20m). Loading and haul may be split into processes, but the loading charge may be taken only once, in either the excavation or the haul item (excavation 'without loading' line items are converted from the loading line item by coefficient 0.80). Hoisting soil from deep excavations beyond the set depth (commonly 2m) is charged separately as vertical transport at 7m of horizontal haul per metre of depth, but dedicated line items such as large strutted excavations and excavation within bracing already include vertical hoisting and take no further charge.
- ←
Measurement rules for earthworks backfill, haulage and special-case excavation: foundation / room / basement-interior / site backfill, the enlargement zone for excavation between piles, and off-site slurry ratios (per DB11/T 2382-2024 section 4.2)
Excavation and haulage are measured by the natural in-situ volume before excavation; backfill by the as-completed volume after backfilling. Foundation backfill = excavation volume - the volumes of foundations, buildings, structures and blinding buried below the designed exterior ground level; room backfill = area between main walls (less heating trenches, cable trenches, drainage trenches and equipment foundations) x (height from the designed exterior ground level to the underside of the first-floor blinding); site backfill = backfill area x backfill thickness; haulage quantity = total excavated volume - total backfill volume. Excavation between piles covers all soil within 1.20m beyond the outer edges of piles / anti-floating anchors / pile caps, or within zones where adjacent outer edges are no more than 4m apart, between the pile-top level (effective pile length plus the design over-cast length) and the underside of the blinding (or cushion), less the volumes of pile bodies and empty bores. Slurry hauled off site: mixing piles, grouting piles, anchors, anchor cables and soil nails at 10% of the formed pile or bore volume; diaphragm walls, trench-cutting cement-soil walls and cast-in-place piles at 50% of the formed pile volume.
- ←
Divergent classification of trench, foundation pit and general earthwork: the BOQ measurement standard treats an excavation with bottom width no more than 3m and bottom length over 3 times the bottom width as a trench and anything beyond as a foundation pit (bottom width and bottom length both exclude working space); the consumption quota treats bottom width no more than 7m with bottom length over 3 times the bottom width as a trench, bottom length no more than 3 times the bottom width with bottom area no more than 150m2 as a foundation pit, and anything beyond as general earthwork. The two criteria run on separate tracks and must not be cross-inferred
BOQ itemisation follows the measurement standard: GB/T 50854-2024 Annex A, A.4.5 'Classification of trench and foundation pit earthwork: within foundation earthwork, a bottom width of no more than 3m with a bottom length over 3 times the bottom width is a trench, and anything beyond that range is a foundation pit. Bottom width and bottom length shall not include working space dimensions'; foundation earthwork (010102) is split into only two items, trench excavation and foundation pit excavation. Quota application follows the quota's own classification (e.g. local consumption standards and the railway buildings quota: bottom width no more than 7m and bottom length over 3 times the bottom width is a trench; bottom length no more than 3 times the bottom width and bottom area no more than 150m2 is a foundation pit; anything beyond is general earthwork). One and the same foundation excavation may be classed as a 'foundation pit' in the BOQ yet remain a 'trench' under the quota; the two criteria are applied on separate tracks and must not be cross-inferred. Classify trench versus foundation pit on the net dimensions shown on the design drawings (no working space added); never add working space first and then test the 3m threshold.
- ←
BOQ itemisation and measurement wording for earthworks under GB/T 50854-2024 Appendix A: item setting and codes for excavation, backfill, disposal of surplus material, borrowed-soil backfill and site levelling; the two ledgers of natural in-situ volume versus compacted volume; the balance formula; pricing splits; and the listing boundary of vertical cut-and-fill
GB/T 50854-2024 Appendix A splits earthworks into three sections: standalone earthworks (010101), foundation earthworks (010102), and site levelling plus others (010103), with disposal of surplus material and site levelling sitting in 010103. A.4.10 provides that excavation and backfill quantities take no account of conversion between compaction states, so excavation is the natural in-situ geometric volume before cutting and backfill is the compacted (as-formed) volume shown on the design, both in m3, and the two can be subtracted directly - disposal of surplus material = excavation BOQ quantity - reusable backfill BOQ quantity; the backfill quantity must deduct the volumes of buried members such as foundations, bedding and pipes; borrowed-soil backfill still lists a single backfill item, with its pricing split into borrowing (soil purchase) + off-site haulage + placement and compaction; A.4.13 makes disposal of surplus material cover loading, haulage and disposal-compliance requirements to the designated tip, with the haul distance and tipping fees inside its all-in unit rate; A.4.12 defines site levelling as in-place cut, fill, haul and level within +/-300 mm of the site datum, measured in m2 (first-floor gross floor area), while vertical cut-and-fill beyond +/-300 mm is listed under standalone earthworks in m3.
- ←
Attribution of quantity gaps between BOQ quantities and quota quantities, and the rate conversion: all-in unit rate P = Sum(Tn) / Q, four destinations of quantity gaps (into the BOQ quantity / into the rate / into quota consumption / into the risk allowance), and conversion points for typical work items
BOQ quantities and quota quantities must be kept on two separate tracks and never swapped: first attribute each quantity gap to one of four classes - content already built into the measurement rules (working space for earthworks) goes into the BOQ quantity; content listed under 'work content' but given no quantity (battering, shoring boards, base trimming and clearing) goes only into the ancillary-works cost or risk allowance inside the all-in unit rate; content carried by the quota through wastage rates or contents (material wastage, rebar wastage plus construction bars at 5%, permissible overbreak in rock works, 0.50m over-concreting of bored piles) goes into the numerator, the quota line-item totals; whatever neither the BOQ nor the quota provides can only go into the rate risk allowance. The conversion formula is P = Sum(Tn) / Q (P rounded to 2 decimal places, Tn kept at full precision without rounding, Q rounded to 3 decimal places). Quoting with quota quantities passed off as BOQ quantities is an explicit error: the dimensional bases differ, the all-in unit rate is understated (omission ratio = 1 - quota rate / all-in rate), and it blurs the parties' respective responsibilities for BOQ accuracy.
- ←
Multi-basis volume conversion for earthworks in practice: truck trips in loose (bulked) volume, BOQ and final account quantities in natural in-situ volume, backfill in compacted volume - basis analysis and conversion rules
Four volume bases must be kept apart: BOQ and quota quantities for excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation (GB/T 50854-2024 Annex A clause A.4.10: quantities of earth and rock excavation and backfill take no account of conversion between compaction states, so BOQ quantities must not be multiplied by further compaction factors); backfill and placed fill as products are measured in the compacted (completed) volume after placing; on-site haulage truck trips are counted in loose (bulked) volume; spoil disposal declarations are made in loose volume. Conversion rules: total truck volume divided by the loose-volume factor (soil 1.30 / rock 1.54 / sand-gravel mixture 1.07) = natural in-situ volume (the settlement quantity), and multiply the same factor in reverse; compacted volume / 0.87 (about x1.15) = natural volume; railway subgrade takes its factors from TB/T 10822-2024 Table 2 by design speed class and soil class, not the generic 1.15.
- ←
The loose-laying coefficient of earthworks: standard definition, formulas and how it is fixed - trial sections, back-calcculating loose thickness from the degree of compaction, and converting stockpile quantities
Loose-laying coefficient K = loose thickness / compacted thickness = compacted dry density / loose dry density (GB 51254-2017 clause 2.1.4; CJJ 4-97 Appendix F formula F.0.3); earthworks have no code value table - K must be fixed by compaction trials (trial sections) per the fill-material x compaction-equipment pair, codes giving values only for specific materials (graded crushed stone 1.4~1.45 hand-mixed, 1.3~1.35 grader-spread); back-calculation: loose dry density = max dry density x degree of compaction / K, and loose / stockpile volume = compacted volume x K.
- ←
Defining the scope of bridge abutment backfill (fill behind abutments): longitudinal backfill length, full-width transverse placing, whether fill under the approach slab belongs, plus fill material, compaction requirements, measurement by volume and quota application
Abutment backfill is the filling of the gap between the rear face of the abutment stem (back wall) and the original ground/subgrade, including the areas behind the wing walls, the backfill under the approach slab and the abutment drainage layer; it excludes pile-cap excavation backfill and conical-slope surface protection. The longitudinal length follows CJJ 2-2008 clause 11.5.7 item 3: not less than the abutment height plus 2m at the top of the stem and not less than 2m at the bottom, and for arch bridges not less than 3 to 4 times the abutment height (the design governs where specified); transversely it is placed to the full designed width in one operation, simultaneously with the conical slopes. Backfilling may start only when the abutment/retaining-wall concrete has reached 75% of the design strength, and the degree of compaction of the transition zone behind the abutment must exceed 96%. The backfill is measured by volume (m3) and priced by quota line item according to fill class; the approach slab itself is a separate line item.
- ←
Deciding between earthwork and rockwork quotas in excavation, and the three soil / rock classification systems with the route to quota items
The test is excavation difficulty, not the geological name: soil dug with shovels, picks and mattocks and fully loaded by machines direct takes earthwork quotas; ground needing ripping, prying, pneumatic breakers or blasting takes rockwork quotas, the line falling between hard soil (class 4) and soft rock (class 5); the class is fixed from the geological survey report against the classification table of the quota volume in use. Building and municipal works use classes 1-2 / 3 / 4 soils and extremely soft to extremely hard rock in five grades; highways use loose / ordinary / hard soil and soft / moderately hard / hard rock (mapping to the 6- and 16-grade I-XVI systems); the Protodyakonov system counts I-IV as soil and V-XVI as rock; then the item follows the method, excavation form (trench / pit / general), depth and dry / wet soil.
- ←
Adjusting haul-distance changes in quota transport items: items are compiled as a base-haul band plus increment bands; cost is not proportional to distance, so scaling by distance ratio is forbidden
Quota transport items come in a banded ladder of a base haul band plus an increment band; each band's cost carries distance-independent fixed consumptions - loading and unloading, waiting, empty returns - so cost is not proportional to distance: a shortened haul must not be scaled by ratio (1 km cut to 200 m is not x 0.2); where a first band up to 200 m exists, apply that band directly; where the first band is 1 km or more, 200 m still falls within it and the base item applies without reduction; only beyond the first band does base item + increment item x number of increments stack, the count rounding at the half (a remainder under half an increment unit is dropped, at half or more it counts as one); adjusted items must carry a conversion mark on the item number.
- ←
When site levelling may be charged as a bill / quota item: in-place grading within plus/minus 300 mm qualifies; vertical-layout excavation (earth or rock) is excluded and measures as general earthworks
Site levelling is an "area-basis yard grading" item, not an earthwork: defined as the in-place cut, fill, haul and grading within plus/minus 300 mm of the building's site level before foundation earthworks (GB/T 50854-2024 clause A.4.12), measured on the building's first-floor floor area at design-shown dimensions, the area of basement structure projecting beyond the first floor merging in (table A.3.1, code 010103). Within plus/minus 30 cm, list as site levelling; vertical-layout excavation (or hillside cutting) beyond plus/minus 30 cm lists as excavation; rock likewise - vertical rock cuts or hillside hewing over 300 mm execute as general rock excavation - plus/minus 300 mm is the mutually exclusive line between "site levelling" and "general earth (rock) works"; one section takes one only.
- ←
Pricing归属 of foundation probing (rod probing/tamping) in Beijing: already综合 in the manual-excavation item work contents, not itemized separately
Beijing DB11/T 2382-2024, 4.2.2: "manual excavation consumption is determined by soil class and shall include rod probing and bottom tamping" — foundation probing has no separate item; it is priced with the manual digging/pit items by soil class; with machine digging, hand trimming of the base (300mm where design is silent) uses the manual items, probing included (4.2.2(3), 4.2.15(2)). On the BOQ side, GB/T 50854-2024 makes base probing a "base treatment method" characteristic description, not a standalone code. Genuine separate listing (e.g., subcontract caliber) is a missing item — compile a supplementary unit-price estimate and guard against double pricing with the manual digging items.
- ←
Locating quota sub-items for earth backfill, replacement-subgrade, and muck loading/hauling in Beijing DB11/T 2382-2024
Replacement fill is priced under the ground-treatment chapter Table A.2.1-1 replacement subgrade (A-2-1 manual sand-gravel fill, A-2-3 sand (stone-chip) spreading; work content: layered spreading, leveling, compaction); indoor backfill under the earthworks chapter A.1.3-1 foundation backfill A-1-42 (backfill, leveling, compaction); site backfill and surplus-soil loading/hauling under A.1.3-2 / A.1.4-1 (A-1-51 soil loading, haul within 1 km; A-1-52 rock (muck) and spoil loading; work content includes haul, unloading, disposal, including spoil or muck disposal material).
- ←
Classifying earthworks: separate earthworks (010101) versus foundation earthworks (010102) split by the "preset level", and how large-area replacement fill is classified (GB/T 50854-2024 Annexes A / B)
The single dividing line of earthworks classes is the "preset level" (design outdoor level / soffit level of the external ground build-up / level nominated by the client), regardless of how large the replacement area is: above the line, separate earthworks (010101) bringing the site to the preset level; below the line, foundation earthworks (010102) executed for the foundations. Large-area replacement fill sorts three ways: site-fill type - separate earthworks backfill (010101003, by volume on the cut-and-fill dimensions between the original ground and the preset level, table A.1.1); replacement cushions at or within pits for ground improvement - Annex B ground treatment (010201001, by volume at design-shown dimensions); if counted merely as earthworks, foundation earthworks; site levelling within plus/minus 300 mm of the level - by area.
- ←
Overview of quantity take-off for construction works: basis, general rules and per-trade calculation methods
Quantity take-off rests on the four-tier basis "contract agreement -> design drawings -> approved project execution plan (construction methodology and site organization) -> appendix rules of the quota norms/measurement standards"; except where rules provide otherwise, all quantities are computed from the dimensions shown on the design drawings. General rules include: calculation per appendix rules (mandatory provisions of codes); the no-deduction threshold of single holes <=0.3 m2; significant figures of units of measurement (t/km three decimals; m/m2/m3/kg two; counts integer); and dual-track BOQ vs quota-norm quantities. Earthwork, concrete, reinforcement, formwork, masonry, waterproofing, finishes etc. each have standard algorithms.
- ←
Quantity take-off (measurement) follows design-drawn dimensions (measurement per drawings): general principle, rule exceptions, and final account linkage
Quantities are in principle calculated from design-drawn dimensions (measurement per drawings), not from actual site dimensions; only items where the method of measurement "provides otherwise" (e.g. earthwork by natural in-situ (undisturbed) volume, depth taken from surveyed elevation) and site instruction / variation record items not specified in the design (flowing sand and silt provisionally estimated, concealed works) are measured per actual conditions / site instruction / variation record. Parts constructed beyond design dimensions without variation or site instruction / variation record support are generally not measured in the final account.
- ←
Beijing 2024 consumption-quota earthwork measurement basis: excavation/fill/haul by drawing volume without bulkage factors — factors used only for disposal estimation and earthwork balance
When compiling budgets under the Beijing 2024 quota (DB11/T 2382-2024), excavation (Clause 4.2.11, by natural in-situ (undisturbed) volume before excavation), backfill (Clause 4.2.21), and haulage (Clause 4.2.25 = total excavation volume - total backfill volume) are all measured directly by drawing volume with no bulkage/conversion factor; GB/T 50854-2024 likewise provides that excavation and backfill quantities involve no compaction-state conversion. Conversion factors are used only for: total muck-disposal estimation (JGJ/T 498-2024, Ve = λc·Vc - λf·Vf, in loose volume), earthwork balance (1 m³ of compacted fill needs about 0.87 m³ of natural in-situ (undisturbed) soil), and purchased soil/truck dispatching (loose = solid x 1.30).
- ←
Whether pipe-trench backfill quantities deduct the pipe volume: the 500 mm diameter demarcation rule and comparison of standards' calibers
Whether trench backfill deducts the pipe volume is demarcated at (nominal) diameter / pipe structural width 500 mm in most systems: <=500 mm no deduction; >500 mm deduct per the quota appendix table (m3/m) or the actual volume of pipe and base/cushion, with some systems (Shenzhen) also including chambers and other auxiliary structures; Hunan 2025 requires deducting the full pipe volume when backfilled with purchased sand/gravel; Beijing DB11/T 2382-2024 municipal/landscape caliber is "minus pipes and structures" with no 500 mm exemption. The text of the standard volume adopted governs.
- ←
Preventing base over-excavation in machine-excavated pits: reserved protection layer + manual bottom cleaning (comparison of DB11/T 1832.1-2021, GB 51004-2015, DB11 489-2016, DBJ 11-501-2009 protection-layer thickness rules)
The core anti-over-excavation process is "reserve a protection layer + manual bottom cleaning": machines stop near design level, leaving a protection layer above design level, which is surveyed and then dug out by hand. Thickness rules: DB11/T 1832.1-2021 Clause 34.3.9 - not less than 300mm in soil strata; GB 51004-2015 Clause 8.1.9 - 200-300mm above pit bottom trimmed manually (slopes trimmed by hand); DB11 489-2016 Clause 8.2.8 - reserve 150-300mm for manual trimming; DBJ 11-501-2009 Appendix Q Q.0.3 - keep 300-500mm removed manually. Baseline: backfilling local over-cuts with loose soil is strictly prohibited.
- ←
Determining quantities where drawing dimensions are incomplete: three-tier fallback plus provisional quantities at the tender/preparation stage; re-measurement plus five-tier progressive determination at the settlement stage
Where drawings are incomplete, quantities are determined along two tracks. At the preparation stage, values are taken by the three-tier fallback "design documents -> approved project execution plan (construction methodology and site organization) -> code/quota norm measurement rules"; where accurate measurement remains impossible, the item description (work item specification) notes "provisional quantities" and an estimated quantity is provided (GB/T 50500-2024 clauses 4.1.4, 4.1.6). At the settlement/dispute stage, re-measurable (unit-rate) contracts are re-measured against the final construction drawings (not the as-built drawings); where the drawings cannot reflect the work, determination follows the five-tier progression from certification and sign-off to site inspection (T/ZBD 100.4-2023 clauses 4.3.5, 4.3.6).
- ←
Intermediate processes to retain in AI quantity takeoff: a five-layer trace framework (input basis, calculation derivation, result mapping, AI traces, archiving)
AI takeoff traces fall into five layers: (1) input basis (drawing version / calculation-rule version / construction-organization parameters / data sources); (2) calculation derivation (formulas + formula sources + intermediate-quantity chains + deduction/inclusion records + significant digits); (3) result mapping (formula <-> BOQ code <-> item-characteristic correspondence, aggregation paths, cross-footing verification); (4) AI generation traces (model version + intermediate expression chains + manual review of at least 10% + differences between draft and final); (5) archiving (working papers archived as process documents). Goal: every final figure can be traced back through derivation to the drawings — traceable, re-checkable, auditable.
- ←
Railway building-works quota TB/T 10831-2024 earthworks: trench-pit vs general earthworks division, manual/mechanical boundary (depth >6 m mechanical), and the <=0.30 m manual bottom-cleaning included in mechanical excavation
Building pit excavation first tests "trench-pit" or "general earth-rock" per volume note 2: trench-pit means trenches with bottom width (design bedding or foundation width) <=7 m and length >3 x width, or pits with length <=3 x width and bottom area <=150 m2; beyond these, unless site grading, it is general earth-rock. Depth <=6 m: manual (FY-1~FY-12) or mechanical (FY-31~FY-42) per the actual method; depth >6 m "shall be treated as mechanical excavation". Mechanical earthwork already comprehends manual cleaning and trimming of the <=0.30 m left at base and slopes — "must not be adjusted in use"; no separate manual bottom-cleaning item.
- ←
Confirming spoil haul distance in municipal earthwork: centroid method, confirmation priority, and quota norms structure
Spoil haul distance = the shortest distance along the actual transport route from the excavation centroid to the spoil centroid, with positions determined in accordance with the approved project execution plan (construction methodology and site organization); confirmation priority: contract/BOQ stipulation > approved project execution plan (construction methodology and site organization) (centroid method) > site instruction / variation record and measurement; the quota norms (prescribed resource consumption standards) are structured as 'base haul <= 1 km + each additional 1 km' stacked, with less than 1 km counted as 1 km; outward haul quantity is measured by natural in-situ (undisturbed) volume with no separate loose coefficient, and on-site transport is not double charged.
- ←
Rock blasting quantity take-off: by pre-blasting natural in-situ (undisturbed) volume (bank measure), and itemization linkage with GB/T 50854-2024 earthworks
Rock blasting BOQ quantities are measured in bank measure (pre-blasting natural in-situ (undisturbed) volume), not loose volume; rock that is not naturally dense converts per GB/T 50862-2024 Table A.5.3 (rock loose 1.54, block stone 1.75, sand-stone mix 1.07). Blasted rock in building BOQs is itemized per GB/T 50862-2024 code 090101 series (GB/T 50854-2024 Appendix A, A.4.14), and per A.4.10 both excavation and backfill ignore densification-state conversion — loose/compacted differences are absorbed by all-in unit rates.
- ←
Measurement unit for earthwork filling items: compacted volume (as-completed backfill / post-rolling volume); excavation, haul, and surplus disposal by natural in-situ (undisturbed) volume; loose volume only for loose-fill items and bulking estimates of waste haul
Filling (backfill/rolling/compaction) is measured in compacted volume: railway subgrade by design fill section as compacted volume (TB/T 10822-2024); building/water backfill by as-completed backfill volume and post-rolling volume (TB/T 10831/10832-2024) — neither loose nor natural volume; excavation, haul, and surplus disposal by pre-excavation natural in-situ (undisturbed) volume. Conversion baseline: loose 1.30 = loose-filled 1.08 = natural in-situ 1.00 = compacted 0.87 — i.e., 1 m3 compacted needs about 1.15 m3 natural in-situ soil or about 1.5 m3 loose volume; so filling items lock the compacted-product basis — quantity by design compacted volume with no bulking factor.
- ←
Disallowance grounds on final-account review for double counting of earthwork haul distance: the all-in unit rate cost envelope under GB/T 50500-2024 + the "disposal of surplus (excavated) material" itemisation basis in the measurement standards
Earthwork loading and haulage costs are already included in the corresponding billed (BOQ) items' all-in unit rates (GB/T 50500-2024 2.0.9, 3.1.6); haul distance is an item description (work item specification) — where the description states a distance, the contract unit rate has locked the corresponding transport cost, and without a variation or BOQ error no separate charge is allowed (8.9.1 item 1, 7.2.1); duplicated haul costs fall within none of the 13 final-account adjustment categories (10.3.2) and shall be disallowed. Off-site haulage can only be itemised as "disposal of surplus (excavated) material" (GB/T 50854-2024 A.4.13, GB/T 50857-2024 A.4.6); excavation work content covers on-site haulage only.
- ←
Item-selection determination for graded-gravel replacement fill in excavation pits: the distinction among replacement-fill ground treatment (A-2-4 gravel spreading), foundation backfill and bedding layers, and quantity calculation (Beijing DB11/T 2382-2024 basis)
Under the Beijing DB11/T 2382-2024 "Construction Consumption Standard": the strengthening of soft or non-uniform soil layers after pit excavation is itemized as "replacement-fill ground treatment" (Appendix A, Table A.2.1-1); graded gravel uses A-2-4 "spreading, gravel" (m3; work content: spreading in layers, leveling, compaction), and sand/stone-chip replacement uses A-2-3. The replacement-fill sub-items exclude excavation of the in-situ soil (executed separately under Clauses 4.2.1 to 4.2.27); quantities are calculated by volume per the design dimensions (4.3.16). The distinction from backfill and bedding lies in position and design intent, not in material: foundation/room backfill uses backfill sub-items (e.g. A-1-38 graded sand-gravel; quantities calculated under 4.2.21/4.2.22), and bedding layers are itemized under the bedding tables A.4.5 and A.5.1-1 - the three must not be interchanged.
- ←
Masonry (brick masonry/block wall) quantity calculation rules: volume caliber, deductions and merges, wall length and height determination
Brick masonry and block walls are calculated by volume (m3) per design-drawn dimensions: deduct door/window openings, reinforced concrete columns/beams/ring beams/cantilever beams/lintels embedded in walls, and wall-recessed niches/duct grooves/heating grooves/fire-hose cabinets; do not deduct beam ends, slab ends, wood bricks, iron parts, steel pipes, or holes with individual area <= 0.3 sqm; waistlines, overhanging eaves, copings, windowsill lines, tiger-head bricks, and door/window casings protruding from the wall face are not added; brick pilasters are merged into the wall; exterior walls take the centerline, interior walls the net length; hollow bond walls by outer-profile volume, openwork walls do not deduct the openwork, and brick columns deduct beam pads, beam ends, and slab ends.
- ←
TB/T 10824-2024 railway tunnel excavation quota: clearance-section step selection and the pricing caliber for overbreak and reserved deformation allowance (Railway works budget quota, Volume 3: tunnel works)
The mining-method excavation quotas of TB/T 10824-2024 "Railway works budget quota, Volume 3: tunnel works" step by clearance section area (minimum clearance cross-section above rail level, taken from the design), all intervals left-closed right-open — a section exactly on a step boundary (42/76/92 m2) takes the next step up. Excavation quantities are computed per the design excavation sections of each surrounding-rock class, including design-allowed overbreak and the reserved deformation allowance (included and priced); construction error and indiscriminate overbreak beyond that envelope are not priced. The quota consumptions are compiled for smooth controlled blasting of rock and exclude design-allowed overbreak and reserved deformation.
- ←
Road structural-layer quantity calculation: BOQ and quota dual calibers, deduction rules, and compacted-volume algorithm
Road structural-layer quantities split into two calibers — BOQ quantities (GB/T 50857-2024 Appendix B) and quota quantities (local consumption quotas, e.g., Shenzhen SJG 181.1-2024) — with different deduction rules that must not be mixed: the BOQ base course is by top surface area without deducting chambers; the surface course deducts no chambers but deducts flat stones when present; the Shenzhen quota base course deducts chambers whose single internal area is > 0.6 m2, and the surface course additionally deducts flat stones, curbs, and edge stones; base-course mixed-material mixing and transport are measured in m3 by compacted volume.
- ←
Composition, charging and cost attribution of spoil-site costs and residue disposal fees (tipping fees)
Spoil-site costs are costs arising around the "site" (temporary land occupation, site protection, reclamation); under the railway approach they are booked as temporary land use costs within project costs other than the works, and are usually borne by the employer. The residue disposal fee (tipping fee) is a paid disposal charge levied for dumping surplus mud and residue at government-designated reception sites, under a charging system, charged per local price documents in yuan/m³, and is included by the contractor in the all-in unit rate for surplus-spoil disposal. The two are different in nature and must not be mixed.
- ←
GB/T 50854-2024 "Standard for Calculation of Quantities of Building and Decoration Works": positioning and revision highlights, and its distinction from GB/T 50353-2013 "Code for Calculation of Gross Floor Area"
GB/T 50854-2024 is the "Standard for Calculation of Quantities of Building and Decoration Works" (replacing GB 50854-2013), governing the method of measurement and the preparation of the bill of quantities; the correct number of the "Code for Calculation of Gross Floor Area" is GB/T 50353-2013 (current) — the two names and numbers must not be mixed. Main revisions of 50854-2024: item descriptions (work item specifications), units of measurement and methods of measurement, and work contents; deletion of demolition works; formwork moved into the work-item BOQ while other preliminary items are priced per item.
- ←
Vertical transportation quantity calculation: buildings by floor area (incl. basements) x eave-height steps, structures by count/volume, rules for height-increase fees
Vertical transportation is a preliminaries (measures) item; the BOQ covers only large vertical-transport plant (tower cranes, construction hoists, material hoists etc.) — hoisting plant and manual assistance are already included in the work content of trade items and must not be double-counted. Buildings apply quota items by floor area (incl. basements) with structural type and eave-height steps; single-storey buildings with eaves <=3.6 m are excluded; structures (chimneys, water towers, silos, elevator shafts etc.) are counted per unit; foundations without basements with embedment depth >=4 m and underground water pools are measured by volume per design dimensions; the height-increase fee is computed on the floor area of the super-height portion, with eave height stepped per additional 10 m — remainders over 5 m (but under 10 m) count as 10 m, and 5 m or under is not counted.
- ←
Concrete quantity calculation rules: cast-in-place and precast members measured by volume per design-drawn dimensions
Concrete quantities are calculated by volume (m3) per design-drawn dimensions: for cast-in-place members, the volumes of rebar, steel wire, iron parts, bolts, and reserved grouting ducts are not deducted, and for walls and slabs, holes with individual area <= 0.3 sqm are not deducted (> 0.3 sqm shall be deducted); precast members are measured by solid volume (excluding hollow parts), without deducting rebar, iron parts, or prestressing reserved ducts. Columns, beams, walls, slabs, foundations, and stairs each have interface-attribution and deduction rules; all specialty quota norms apply the same measurement basis.
- ←
GB/T 50854-2024 foundation earthwork BOQ quantity rules: pit/trench excavation includes working space, excludes sloping; trench-vs-pit division and excavation depth
Per GB/T 50854-2024 Appendix A Table A.2.1, the BOQ quantity of pit/trench excavation = the foundation (including bedding) bottom area per design drawings plus working-space area, multiplied by excavation depth: working-space width enters the BOQ quantity (per Tables A.4.6-1/2 where no design value is given), while the sloping increment does not (sloping is listed in the work content "excavation, sloping (if any)" and is to be allowed for by bidders in the all-in unit rate). Trench = bottom width <= 3 m and bottom length > 3 x bottom width (neither includes working space, A.4.5); excavation depth runs from the preset elevation to the foundation (including bedding) bottom elevation, or to the soil-rock boundary where rock lies below (A.4.7). GB/T 50500-2024 has no "re-measure only beyond some percentage" rule — re-measurable (unit-rate) contracts are re-measured on an item-by-item basis per 7.2.1 (except items priced per lump item); 15% is the boundary for re-rating of unit rates (8.2.1: <= 15% inclusive per 8.9.1, > 15% per 8.9.2).