Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Earthwork excavation quantity take-off (measurement): working space width, slope coefficients, and haulage (disposal of surplus excavated material) quantities

Earthwork excavation quantity take-off (measurement) follows the three-level priority "design → project execution plan (construction methodology and site organization) → default values in standard appendix tables"; excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation, backfill in the as-completed volume; working space widths and slope coefficients are taken from tables by foundation material, soil class, and machine working position, and no slope is calculated where shoring boards are placed; the quantity for disposal of surplus (excavated) material = excavated volume − backfill reuse volume, haulage being measured in the natural-state volume with no additional bulking factor.

Applicable Codes

  • GB/T 50854-2024
  • TB/T 10831-2024
  • SJG 111.1-2022
  • SJG 84-2020
  • GB 50861-2013

Topic Positioning

The three cores of earthwork excavation measurement — determination methods and volume bases for working space width, slope, and haulage (disposal of surplus excavated material) quantities, applicable to earth and rock works for building works, municipal works, rail transit, utility tunnels, railways, and other sectors.

Core Conclusions

  • Volume basis: excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation; backfill in the as-completed volume after backfilling. Under the BOQ basis (GB/T 50854-2024) no density-state conversion applies between excavation and backfill; under the quota-norm rate build-up basis, conversion factors apply (natural in-situ 1.0 ≈ loose 1.3, compacted fill 0.87, loose fill 1.08).
  • Priority: where design documents specify, follow the design → where not, follow the approved project execution plan (construction methodology and site organization) → where neither, follow the default values in the standard/quota-norm appendix tables.
  • Working space width (per face): formwork for concrete foundations 400 mm, formwork for blinding 150 mm, brick foundations 200 mm, rubble/dressed-stone foundations 250 mm, vertical mortar damp-proof courses 400 mm, waterproof/anti-corrosion layers 1000 mm, plus 100 mm where shoring boards are placed; strip foundations with scaffolding 1500 mm on one side, isolated foundations 450 mm on each of the four sides; large open excavation of the pit with slope support or piling inside the pit 2000 mm. Pipe-trench working space is taken in bands by pipe structural width (outer edge of the base where a pipe cradle exists, otherwise the pipe outer diameter).
  • Sloping: slope is calculated only where the excavation depth exceeds the slope starting point (Class 1–2 soils 1.20 m, Class 3 soil 1.50 m, Class 4 soil 2.00 m); manual excavation 1:0.50–1:0.25; machine excavation by working position — in the pit / on the pit / in the trench (e.g., Class 1–2 soils 1:0.33 / 1:0.75 / 1:0.50 respectively); where shoring boards are placed, no slope is calculated; mixed soils are weighted by depth percentage; sloping starts from the bottom level of the foundation (including blinding); overlapping quantities at slope intersections are not deducted.
  • Haulage: for backfill with native soil, the quantity for disposal of surplus (excavated) material = excavated volume − backfill volume; for replacement fill, = excavated volume; haulage is measured in the natural-state volume before excavation, with the bulking factor already included in the quota norms and not counted again.

Applicable Boundaries

Applies to earth/rock measurement across industries, but specific appendix values follow the regional/industry quota norms applicable to the project (GB national, SJG, and TB railway systems differ only slightly); distinguish the BOQ measurement basis from the quota-norm rate build-up basis; an approved project execution plan prevails over standard defaults; shoring and sloping are mutually exclusive and cannot both be counted.

Further Reading

See GB/T 50854-2024 Appendix A Earth and Rock Works A.4.6 (working space width Tables A.4.6-1/2); TB/T 10831-2024 Railway Works Budget Quota Manual (China Railway), Vol. 10 Building Works, volume notes XI (Table 4 volume conversion, Table 5 working space, Table 6 slopes); SJG 111.1-2022 Consumption Standard for Urban Utility Tunnels Vol. 1, 1.2.3 (sloping, shoring boards, working space); SJG 84-2020 Municipal Maintenance Consumption Standard Vol. 2, 7.2.9 (haulage quantities and slope rules).

Keywords

Cited By