Beijing 2024 consumption-quota earthwork measurement basis: excavation/fill/haul by drawing volume without bulkage factors — factors used only for disposal estimation and earthwork balance
When compiling budgets under the Beijing 2024 quota (DB11/T 2382-2024), excavation (Clause 4.2.11, by natural in-situ (undisturbed) volume before excavation), backfill (Clause 4.2.21), and haulage (Clause 4.2.25 = total excavation volume - total backfill volume) are all measured directly by drawing volume with no bulkage/conversion factor; GB/T 50854-2024 likewise provides that excavation and backfill quantities involve no compaction-state conversion. Conversion factors are used only for: total muck-disposal estimation (JGJ/T 498-2024, Ve = λc·Vc - λf·Vf, in loose volume), earthwork balance (1 m³ of compacted fill needs about 0.87 m³ of natural in-situ (undisturbed) soil), and purchased soil/truck dispatching (loose = solid x 1.30).
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
- JGJ/T 498-2024 施工现场建筑垃圾减量化技术标准
Topic Positioning
Under the Beijing 2024 consumption quota (DB11/T 2382-2024), whether bulkage factors are applied to the three quantities — excavation, backfill, and spoil haulage — when applying quota items, and the application scenarios of conversion factors.
Core Conclusions
All three quantities are taken without factors when applying items: excavation by natural in-situ (undisturbed) volume before excavation (Clause 4.2.11); backfill by volume after backfilling (Clause 4.2.21); earthwork haulage = total excavation volume - total backfill volume (Clause 4.2.25). GB/T 50854-2024 likewise provides that excavation and backfill quantities involve no compaction-state conversion. Factors are used for: muck-disposal estimation Ve = λc·Vc - λf·Vf (JGJ/T 498-2024; soil λc = 1.30; loose backfill λf = 1.20, compacted fill 1.45-1.58), in loose volume; earthwork balance, where 1 m³ of compacted fill needs about 0.87 m³ of natural in-situ (undisturbed) soil; purchased soil and truck loading at loose = solid x 1.30.
Applicable Boundaries
Applies to earthwork measurement in budgets/settlements compiled under DB11/T 2382-2024; "no factor" is confined to the quota-quantity basis — management scenarios such as muck-disposal declaration, spoil-site capacity, and truck organization must convert to loose volume. The reserved hand-trimming depth for machine excavation is taken as 300 mm where the design does not require otherwise (Clause 4.2.15), executed under the hand-excavation item.
Further Reading
DB11/T 2382-2024 Clauses 4.2.11, 4.2.15, 4.2.21, 4.2.25 and Table 4.2.15-2; GB/T 50854-2024 Appendix A Earthworks; JGJ/T 498-2024 Clause 4.0.2.
Keywords
- 北京2024定额
- DB11/T 2382-2024
- 土石方计量口径
- 松散系数
- 体积折算
- natural in-situ (undisturbed) volume
- 弃土排放估算
- 土方平衡