BOQ itemisation and measurement wording for earthworks under GB/T 50854-2024 Appendix A: item setting and codes for excavation, backfill, disposal of surplus material, borrowed-soil backfill and site levelling; the two ledgers of natural in-situ volume versus compacted volume; the balance formula; pricing splits; and the listing boundary of vertical cut-and-fill
GB/T 50854-2024 Appendix A splits earthworks into three sections: standalone earthworks (010101), foundation earthworks (010102), and site levelling plus others (010103), with disposal of surplus material and site levelling sitting in 010103. A.4.10 provides that excavation and backfill quantities take no account of conversion between compaction states, so excavation is the natural in-situ geometric volume before cutting and backfill is the compacted (as-formed) volume shown on the design, both in m3, and the two can be subtracted directly - disposal of surplus material = excavation BOQ quantity - reusable backfill BOQ quantity; the backfill quantity must deduct the volumes of buried members such as foundations, bedding and pipes; borrowed-soil backfill still lists a single backfill item, with its pricing split into borrowing (soil purchase) + off-site haulage + placement and compaction; A.4.13 makes disposal of surplus material cover loading, haulage and disposal-compliance requirements to the designated tip, with the haul distance and tipping fees inside its all-in unit rate; A.4.12 defines site levelling as in-place cut, fill, haul and level within +/-300 mm of the site datum, measured in m2 (first-floor gross floor area), while vertical cut-and-fill beyond +/-300 mm is listed under standalone earthworks in m3.
Applicable Codes
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. A Table A.1.1(010101)、Table A.2.1(010102)、Table A.3.1(010103)及 A.4.10~A.4.13
- GB/T 50857-2024 · Standard for Measurement of Quantities of Municipal Works App. A Table A.3.1 回填方及余方弃置(040103)
- JGJ/T 498-2024《施工现场建筑垃圾减量化技术标准》第 4.0.2 条及表 2
- 京建发〔2021〕201号《2021 预算消耗量标准》房屋建筑与装饰工程(上册)第一章 土石方工程
Topic scope
Under the building and decoration works BOQ wording (GB/T 50854-2024 Appendix A, earthworks): item setting and codes for the five item types - excavation, backfill, disposal of surplus material, borrowed-soil backfill (off-site borrowing) and site levelling; measurement states (natural in-situ volume versus compacted volume); the surplus disposal balance formula; the pricing split of borrowed-soil backfill; and the listing boundary between site levelling and vertical cut-and-fill.
Core conclusions
I. Item setting and codes (GB/T 50854-2024 Appendix A)
- Table A.1.1 standalone earthworks (code 010101) - site vertical levelling, bulk excavation and other independent earthworks;
- Table A.2.1 foundation earthworks (code 010102) - trenches and pits attached to building (structure) foundations;
- Table A.3.1 site levelling and others (code 010103) - site levelling (010103001), disposal of surplus material (010103002) and the like are set in this section, the most easily mis-remembered home (surplus disposal sits in neither 010101 nor the excavation section). Municipal works correspond to GB/T 50857-2024 table A.3.1 backfill and disposal of surplus material (code 040103); the item division and coding systems of the two standards must not be interchanged.
II. Master measurement rule (the pivot of the two ledgers) A.4.10 verbatim: 'In calculating quantities of earthwork excavation and backfill, no conversion shall be made between volumes of soil and rock in different compaction states.' Hence:
- Excavation = the geometric volume of the cut per the design dimensions, i.e. the natural in-situ volume before cutting (m3), with no loose or bulk factor applied;
- Backfill = the backfill volume per the design dimensions, i.e. the geometric volume of the compacted fill body (in works terms the 'compacted volume', m3), with no factor of 1.15 (natural), 1.20 (loose fill) or 1.30 (bulk) applied;
- Precisely because neither end converts, at BOQ level excavation and backfill can be subtracted directly for the earthworks balance; while pricing, haulage and disposal declaration still need conversion factors (1 m3 of compacted fill takes about 1.15 m3 of natural soil or 1.50 m3 of bulk), where 'BOQ 1 m3 of backfill corresponds to quota borrowing of 1.15 m3' is a normal dual ledger and the BOQ quantity must not be adjusted in reverse.
III. Backfill itemisation and material types A.4.11: 'The material type of backfill may be described as on-site soil, plain soil, lime soil and the like. Where several materials are used for backfill, items shall be coded and listed separately.' - lime-soil backfill and plain-soil backfill at the same part must be split, not merged into one combined description. Borrowed-soil backfill (off-site borrowing): the BOQ still lists one 'backfill' item (m3) with the material described as purchased soil and the like; the cost of borrowing (purchase, winning and loading at the borrow pit) and off-site haulage is not inside the backfill line item's consumption, so pricing must split it into 'borrowing (purchase / winning and loading) + off-site haulage + placement and compaction' within the all-in unit rate (local consumption standards also state expressly that 'earth backfill does not include purchased soil'; the purchased-soil material cost is separate).
IV. Disposal of surplus material: balance formula and cost attribution
- BOQ formula: disposal of surplus material (m3) = excavation BOQ quantity - backfill BOQ quantity (reusable part), subtracted directly on the same unconverted basis as excavation, with no extra factor.
- Quota / pricing level balance test (earth haulage computed on natural in-situ volume): total excavation - backfill converted to natural in-situ volume > 0 means surplus out-haul; < 0 means borrowed soil in-haul; = 0 means balanced; the haul distance is the shortest distance between the centroid of the cut area and the centroid of the fill (or stockpile) area.
- The backfill quantity must deduct the volume occupied by buried members (including foundations and other structures) - the deduction most often missed in the 'excavation - backfill' formula:
- trench and pit backfill = excavation volume - volume of buried members below the designed exterior ground level (including foundation bedding, foundations and the like);
- pipeline trench backfill = excavation volume - volume of pipe and bedding (pipes of nominal diameter up to 500 mm are not deducted; above 500 mm, deduct per the pipe-to-backfill conversion table; where purchased sand and gravel is used for backfill, deduct the full pipe volume);
- room-core backfill (including inside basements) = net area between main walls (deducting equipment foundations and the like with a continuous footprint over 2 m2) x backfill thickness;
- site-area backfill (including above basement roof slabs) = backfill area x average backfill thickness.
- Attribution of haul distance and tipping fees: A.4.13 verbatim - 'Disposal of surplus material includes loading and haulage of earth and rock from the work site to the designated disposal point, and shall meet the national and local construction administration requirements on construction waste acceptance and disposal.' - loading, off-site haulage, haul distance and tipping and disposal fees are all endogenous to this item's all-in unit rate, with no separate 'earth out-haul', 'per-additional-haul' or 'disposal fee' BOQ items; the excavation item's work content covers on-site haulage only, off-site haulage being carried by surplus disposal.
- Out-haul volume of waste soil is measured in bulk volume (JGJ/T 498-2024 clause 4.0.2, conversion factor: soil 1.30, rock 1.54, sand-rock mix 1.07), used for disposal total estimates and truck counts - a different basis from the BOQ m3 of drawn volume; do not mix them.
V. Listing boundary between site levelling and vertical cut-and-fill
- A.4.12 verbatim: 'Site levelling means the in-place cutting, filling, hauling and levelling of the building site between levels within +/-300 mm, carried out before foundation earthworks.' Levelling within +/-300 mm belongs to site levelling, measured in m2 (the BOQ takes the building's first-floor gross floor area; where the basement outer edge projects beyond the first-floor structural edge, the projected area is added in).
- Vertical cut-and-fill beyond +/-300 mm is site vertical earthworks, listed as standalone earthworks (010101) in m3 under the general excavation / machine-cut independent earthworks line items, and must not be folded into site levelling (local wording is consistent: where the average thickness between the designed exterior ground and the natural ground is within +/-300 mm, site levelling applies; beyond that, the vertical earthworks executes the machine-cut independent earthworks line items).
- Wording difference alert: BOQ site levelling is measured on first-floor gross floor area (m2); some local consumption standards measure it in m2 on the building outline plus 2 m per side - the BOQ and quota quantities differ in basis and must not be mixed at settlement or pricing.
Applicable boundaries
- This card follows the building and decoration works BOQ wording (GB/T 50854-2024); municipal backfill and surplus disposal follow GB/T 50857-2024 (040103), whose excavation items generally include on-site haulage only, with out-haul listed as 'disposal of surplus material' - different codes and rules, not interchangeable across disciplines.
- Three ledgers must be kept apart: the BOQ quantity (drawn dimensions, unconverted, no batter increment), the quota quantity (with batter and working-space increments, with compaction-factor borrowing volume), and the disposal declaration / truck volume (bulk). Quota quantity exceeding BOQ quantity is normal; the BOQ quantity must not be rewritten backwards.
- Backfill deduction details (the DN500 pipe threshold, the 2 m2 continuous-footprint equipment foundation threshold, the pipe-to-backfill conversion table) come from local consumption standards; they are pricing-level detail rules that may be fine-tuned by region - the governing rules are the applicable current quota and the calculation rules agreed in the contract.
- The +/-300 mm boundary refers to the 'average thickness' between the natural and designed ground; whether locally deeper spots that do not amount to an overall vertical layout still count as site levelling needs judgement against the design vertical drawings.
Further reading
GB/T 50854-2024 'Quantity Take-off Standard for Building and Decoration Works', Appendix A: table A.1.1 standalone earthworks (010101), table A.2.1 foundation earthworks (010102), table A.3.1 site levelling and others (010103); clauses A.4.10 (no compaction-state conversion), A.4.11 (backfill material types and separate coding), A.4.12 (definition of site levelling), A.4.13 (work content of surplus disposal and disposal requirements); GB/T 50857-2024 'Quantity Take-off Standard for Municipal Works', Appendix A table A.3.1 backfill and disposal of surplus material (040103); JGJ/T 498-2024 'Technical Standard for Construction Waste Reduction on Site', clause 4.0.2 and table 2 (conversion factors among bulk / loose / natural in-situ / compacted volumes); pricing details in Jing Jian Fa [2021] No. 201 '2021 Budget Consumption Standard', building and decoration works (volume I), chapter 1 earthworks, sections 7-10 (the +/-300 mm demarcation, purchased soil excluded from backfill, earth haulage and per-additional-haul line items), and the provincial consumption standards' earthworks calculation rules (deduction rules for trenches and pits, pipeline trenches, room-core and site-area backfill, and the natural in-situ basis for earth haulage).
Keywords
- disposal of surplus (excavated) material
- 回填方
- 平整场地
- 借土回填
- 单独土石方
- natural in-situ (undisturbed) volume
- 夯实后体积
- GB/T 50854-2024