Multi-basis volume conversion for earthworks in practice: truck trips in loose (bulked) volume, BOQ and final account quantities in natural in-situ volume, backfill in compacted volume - basis analysis and conversion rules
Four volume bases must be kept apart: BOQ and quota quantities for excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation (GB/T 50854-2024 Annex A clause A.4.10: quantities of earth and rock excavation and backfill take no account of conversion between compaction states, so BOQ quantities must not be multiplied by further compaction factors); backfill and placed fill as products are measured in the compacted (completed) volume after placing; on-site haulage truck trips are counted in loose (bulked) volume; spoil disposal declarations are made in loose volume. Conversion rules: total truck volume divided by the loose-volume factor (soil 1.30 / rock 1.54 / sand-gravel mixture 1.07) = natural in-situ volume (the settlement quantity), and multiply the same factor in reverse; compacted volume / 0.87 (about x1.15) = natural volume; railway subgrade takes its factors from TB/T 10822-2024 Table 2 by design speed class and soil class, not the generic 1.15.
Applicable Codes
- GB/T 50854-2024 App. A 第A.4.10条
- GB 50854-2013 Table A.3 回填(010103)
- GB/T 50857-2024 Table A.3.1 回填方及余方弃置(040103)
- TB/T 10831-2024 册说明十一(一)表4
- TB/T 10832-2024 册说明五(一)表1
- TB/T 10822-2024 册说明表2、表3
- JGJ/T 498-2024 第4.0.2条
What this card covers
Answers the most confused line in earthworks measurement: one batch of soil passes through five stages - 'BOQ quantity - quota quantity - haulage truck trips - backfill product - spoil declaration' - each on a different volume basis. The card gives the code basis for each stage, unified conversion rules and common pitfalls, for budget compilation, earthworks balance, truck-volume reconciliation and settlement review.
Core conclusions
1. First fix the basis: who measures natural, who compacted, who loose
- Excavation, loading, haulage and surplus-soil removal - measured in the natural in-situ (bank) volume before excavation. Local consumption quota wording: 'Excavation and haulage of earth and rock are calculated in the natural in-situ volume (bank volume) before excavation. Backfill is calculated in the completed volume (compacted volume) after placing. Where the actual state does not match the principle of calculation, convert per the table.' The railway volumes use the same wording: TB/T 10831-2024 volume notes say 'excavation and haulage of earth and rock are calculated in the natural in-situ volume before excavation, and backfill in the completed volume after placing'; TB/T 10832-2024 volume notes say 'earth and rock volumes are calculated in natural in-situ volume, backfill in the rolled volume, and surplus and accumulated soil uses the loose-soil quota items'.
- Backfill, placing and rolling as products - measured in compacted volume (the completed volume after placing / the volume after rolling). Railway subgrade: 'fill production, fill haulage and placement-and-compaction quantities are measured by the design fill cross-section in compacted volume; fill crushing is measured in compacted volume', while 'spoil (rock) spreading and rolling is measured in the natural in-situ volume of the spoil'.
- On-site haulage truck trips - counted in loose (bulked, truck) volume; this is the naturally piled state, not the quota basis.
- Spoil (muck) disposal declarations - in loose volume (JGJ/T 498-2024 clause 4.0.2: Ve measured in loose volume).
2. BOQ quantities take no conversion between compaction states (current national standard, verbatim) GB/T 50854-2024 (Standard for Calculation of Quantities of Building and Decoration Works) Annex A clause A.4.10: 'In calculating quantities of earth and rock excavation and backfill, no conversion of earth and rock volumes between different compaction states is considered.' That is, BOQ quantities take the design shown dimensions directly (the finished cross-section is itself in the compacted state) and must not be multiplied by factors such as 1.15 / 0.87; the superseded 2013 edition (Code for Measurement of Building and Decoration Works) listed backfill under 'Table A.3 Backfilling (code 010103)', and the municipal basis is GB/T 50857-2024 'Table A.3.1 Backfilling and disposal of surplus material (code 040103)'. BOQ quantities, quota pricing quantities and haulage truck volumes are three different bases; mixing them directly causes duplicated or omitted quantities.
3. Conversion rules (rules only, no worked examples)
- Truck volume -> settlement volume (loose -> natural in-situ): natural in-situ volume = total truck volume divided by the loose-volume factor - soil 1.30, rock 1.54, sand-gravel mixture 1.07; in reverse, truck volume = natural volume x the same factor. Soil dug out and loaded inevitably expands (1 -> 1.30), so more truckloads than the design quantity is a physical certainty and must not be judged as short volume, over-haulage or double measurement.
- Compacted -> natural: natural volume = compacted volume / 0.87 (about 1.15 times); compacted -> loose: loose volume = compacted volume x 1.50.
- Haulage quota items are already compiled on natural in-situ volume; when building up rates, do not multiply a bulking factor onto the haulage line items (already allowed for in the quota).
- Surplus-soil test: total excavated volume minus backfill volume (the backfill first converted to natural in-situ volume); positive = surplus soil to remove, negative = borrow soil to haul in; haul distance is the shortest distance between the centre of gravity of the excavation area and that of the fill (stockpile) area.
- The spoil disposal declaration volume per Ve = lambda-c x Vc - lambda-f x Vf (loose basis) is a separate set of figures from the settlement volume (natural) and the two are not interchangeable.
4. Dedicated conversion factors for railway subgrade fill (the generic 1.15 does not apply) TB/T 10822-2024 Volume 1 Subgrade Works Table 2, 'conversion factors between natural in-situ and compacted volume of earth and rock', with values taken by design speed class and soil class (loose soil / common soil / hard soil / rock), separately for main-line sections and station yards: design speed above 200 km/h, sections 1.258 / 1.156 / 1.115 / 0.941, station yards 1.230 / 1.130 / 1.090 / 0.920; 160 km/h < design speed up to 200 km/h, sections 1.225 / 1.133 / 1.092 / 0.921, station yards 1.198 / 1.108 / 1.068 / 0.900; design speed up to 160 km/h, sections 1.125 / 1.064 / 1.023 / 0.859, station yards 1.100 / 1.040 / 1.000 / 0.840. Note: the factors already allow for the earthworks for the widening of both sides of the embankment required by construction. Where Group A or Group B fill is bought in, the fill weight is calculated per the fill density of Table 3 (tonnes per 1 m3 of compacted volume).
5. Deduction rules for backfill quantities (common detail in rate build-up and settlement) Local consumption quota rules on backfill can guide pricing: trench and pit backfill is calculated as excavated volume minus the volume of members buried below the design outdoor ground level (including blinding and foundations); pipeline trench backfill deducts the volume of the pipe and its bedding - pipes of nominal diameter up to 500 mm are not deducted, above 500 mm deduction follows the quota conversion table, and where bought-in sand, gravel or the like is used for backfill the full pipe volume is deducted and the actual backfill volume calculated; floor interior backfill (including within basements) is the net area between main walls (deducting equipment bases and the like with a continuous footprint of 2 m2 or more) x backfill thickness; site-area backfill (including above basement roofs) is backfill area x average backfill thickness.
Applicable boundaries
- The conversion factors in this card come from the 2024 railway budget quota manuals and the general tables of local consumption quotas; sector and regional quotas differ in detail - the version applicable to the project governs.
- 'No conversion in the BOQ' applies only to quantities compiled under GB/T 50854 / 50857, not to rate build-up consumption, truck-volume reconciliation or spoil declarations.
- Railway subgrade fill and bought-in fill must use the subgrade conversion table and the fill density table, not the generic building / municipal factors.
- Loose-volume factors presume unrolled, freshly piled soil; after long stockpiling and settlement the measured volume will drift from the factor table, and large disputes are better settled by measurement or certified records.
- Working space width, battering and the starting level for excavation depth follow the relevant standards and are outside this card.
Further reading
GB/T 50854-2024 Annex A clause A.4.10 (no conversion) and A.4 earthworks; GB 50854-2013 Table A.3 Backfilling (code 010103); GB/T 50857-2024 Table A.3.1 Backfilling and disposal of surplus material (code 040103); TB/T 10831-2024 volume notes 11 (1) Table 4; TB/T 10832-2024 volume notes 5 (1) Table 1; TB/T 10822-2024 Volume 1 Subgrade Works volume notes Table 2 (conversion factors), Table 3 (density of Group A and B fill) and the measurement rules; JGJ/T 498-2024 clause 4.0.2 (spoil disposal measured in loose volume); local consumption quota earthworks notes (backfill deductions; earth haulage calculated in natural in-situ volume).
Keywords
- 回填工程量按压实方
- 运输按天然密实体积
- 车方换算
- 余土外运
- 虚方外运
- 土方体积口径
- 松方结算
- 路基填筑换算系数