Earthwork volume conversion coefficients and spoil haul-off disposal estimation (loose / loose-fill / natural-dense / compacted conversion)
Excavation and haul are measured by the pre-excavation natural in-situ (undisturbed) volume, backfill by the post-backfill volume, and different states are converted by coefficients (natural in-situ (undisturbed) 1.00 <-> loose 1.30 <-> loose fill 1.08 <-> compacted 0.87); total spoil disposal Ve = lambda-c x Vc - lambda-f x Vf (JGJ/T 498-2024), with lambda-c soil 1.30 / rock 1.54 / sand-rock mixture 1.07.
Applicable Codes
- TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) 册说明十一(一)表 4
- TB/T 10832-2024 · Railway works budget quota manual: Water Supply and Drainage Works, Vol. 11 (2024 series) 册说明五(一)表 1
- TB/T 10822-2024 · Budget Quota of Railway Engineering (Volume 1: Subgrade Works) 册说明表 2
- JGJ/T 498-2024《施工现场建筑垃圾减量化技术标准》第 4.0.2 条及条文说明表 2
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. A 第 A.4.10 条
- GB 50842-2013《建材矿山工程施工与验收规范》附录 B 表 B.0.1、第 B.0.2 条
- GB 50201-2012 · Code for Construction and Acceptance of Earthwork and Blasting Engineering 第 4.5.4 条
- 陕西省新编房屋建筑与装饰工程消耗量定额 表 1-4(征求意见稿)
- 湖南省房屋建筑与装饰工程消耗量标准 土石方说明
- 江苏省建筑与装饰工程消耗量定额 土方章说明
Topic Positioning
Conversion coefficients among the four volume states of earth and rock work (loose, loose fill, natural in-situ (undisturbed), compacted), and the estimation method for the total haul-off disposal volume of engineering spoil.
Core Conclusions
(1) Measurement convention: excavation and haul quantities are calculated by the pre-excavation natural in-situ (undisturbed) volume, backfill by the post-backfill (completed/compacted) volume; different states are converted by the coefficient table. General earthwork coefficients with natural in-situ (undisturbed) = 1.00 as the base: loose fill 1.08, loose 1.30, compacted 0.87 (railway TB/T 10831-2024 Volume 10 Table 4; TB/T 10832-2024 Volume 11 Table 1); rock loose 1.54, sand-rock mixture loose 1.07, etc. (2) Building BOQ measurement (GB/T 50854-2024 Appendix A.4.10) stipulates: when calculating excavation and backfill quantities, no conversion between volumes of different compaction states is considered — BOQ quantities follow the design-drawn natural in-situ (undisturbed) convention, distinguished from conversions at the consumption/haul stages. (3) Spoil disposal estimation (JGJ/T 498-2024 Clause 4.0.2): Ve = lambda-c x Vc - lambda-f x Vf, where Ve is the estimated total spoil disposal volume (in loose volume); Vc is the excavation volume (natural in-situ (undisturbed)); Vf is the quantity reused as backfill in this project after excavation (post-backfill volume); lambda-c is the loose-volume haul-off conversion coefficient — soil 1.30, rock 1.54, sand-rock mixture 1.07; lambda-f is the backfill conversion coefficient — loose-fill soil 1.20, rock 1.18, sand-rock mixture 1.14, and compacted fill is interpolated in the 1.45-1.58 range per the compaction coefficient 0.90-0.98.
Applicable Boundaries
Conversion coefficients differ slightly among quotas/standards — the current industry or local quota table governs; the volume conventions of the preparation of the bill of quantities, norm resource consumption, and spoil haul stages differ, so do not mix them; working space and slope gradient are calculated separately as specified in each standard.
Further Reading
TB/T 10831-2024 Volume 10 Table 4; TB/T 10832-2024 Volume 11 Table 1; GB/T 50854-2024 Appendix A.4.10; JGJ/T 498-2024 Clause 4.0.2 and Table 2.
Keywords
- 土方体积换算
- natural in-situ (undisturbed) volume
- 虚方
- 松填
- 夯实后体积
- 可松性系数
- 压实系数
- 余土外运
Related Cards
- →
Beijing 2024 consumption-quota earthwork measurement basis: excavation/fill/haul by drawing volume without bulkage factors — factors used only for disposal estimation and earthwork balance
When compiling budgets under the Beijing 2024 quota (DB11/T 2382-2024), excavation (Clause 4.2.11, by natural in-situ (undisturbed) volume before excavation), backfill (Clause 4.2.21), and haulage (Clause 4.2.25 = total excavation volume - total backfill volume) are all measured directly by drawing volume with no bulkage/conversion factor; GB/T 50854-2024 likewise provides that excavation and backfill quantities involve no compaction-state conversion. Conversion factors are used only for: total muck-disposal estimation (JGJ/T 498-2024, Ve = λc·Vc - λf·Vf, in loose volume), earthwork balance (1 m³ of compacted fill needs about 0.87 m³ of natural in-situ (undisturbed) soil), and purchased soil/truck dispatching (loose = solid x 1.30).
- →
Earthwork excavation quantity take-off (measurement): working space width, slope coefficients, and haulage (disposal of surplus excavated material) quantities
Earthwork excavation quantity take-off (measurement) follows the three-level priority "design → project execution plan (construction methodology and site organization) → default values in standard appendix tables"; excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation, backfill in the as-completed volume; working space widths and slope coefficients are taken from tables by foundation material, soil class, and machine working position, and no slope is calculated where shoring boards are placed; the quantity for disposal of surplus (excavated) material = excavated volume − backfill reuse volume, haulage being measured in the natural-state volume with no additional bulking factor.
- →
Multi-basis volume conversion for earthworks in practice: truck trips in loose (bulked) volume, BOQ and final account quantities in natural in-situ volume, backfill in compacted volume - basis analysis and conversion rules
Four volume bases must be kept apart: BOQ and quota quantities for excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation (GB/T 50854-2024 Annex A clause A.4.10: quantities of earth and rock excavation and backfill take no account of conversion between compaction states, so BOQ quantities must not be multiplied by further compaction factors); backfill and placed fill as products are measured in the compacted (completed) volume after placing; on-site haulage truck trips are counted in loose (bulked) volume; spoil disposal declarations are made in loose volume. Conversion rules: total truck volume divided by the loose-volume factor (soil 1.30 / rock 1.54 / sand-gravel mixture 1.07) = natural in-situ volume (the settlement quantity), and multiply the same factor in reverse; compacted volume / 0.87 (about x1.15) = natural volume; railway subgrade takes its factors from TB/T 10822-2024 Table 2 by design speed class and soil class, not the generic 1.15.
- →
Measurement unit for earthwork filling items: compacted volume (as-completed backfill / post-rolling volume); excavation, haul, and surplus disposal by natural in-situ (undisturbed) volume; loose volume only for loose-fill items and bulking estimates of waste haul
Filling (backfill/rolling/compaction) is measured in compacted volume: railway subgrade by design fill section as compacted volume (TB/T 10822-2024); building/water backfill by as-completed backfill volume and post-rolling volume (TB/T 10831/10832-2024) — neither loose nor natural volume; excavation, haul, and surplus disposal by pre-excavation natural in-situ (undisturbed) volume. Conversion baseline: loose 1.30 = loose-filled 1.08 = natural in-situ 1.00 = compacted 0.87 — i.e., 1 m3 compacted needs about 1.15 m3 natural in-situ soil or about 1.5 m3 loose volume; so filling items lock the compacted-product basis — quantity by design compacted volume with no bulking factor.
- →
GB/T 50854-2024 foundation earthwork BOQ quantity rules: pit/trench excavation includes working space, excludes sloping; trench-vs-pit division and excavation depth
Per GB/T 50854-2024 Appendix A Table A.2.1, the BOQ quantity of pit/trench excavation = the foundation (including bedding) bottom area per design drawings plus working-space area, multiplied by excavation depth: working-space width enters the BOQ quantity (per Tables A.4.6-1/2 where no design value is given), while the sloping increment does not (sloping is listed in the work content "excavation, sloping (if any)" and is to be allowed for by bidders in the all-in unit rate). Trench = bottom width <= 3 m and bottom length > 3 x bottom width (neither includes working space, A.4.5); excavation depth runs from the preset elevation to the foundation (including bedding) bottom elevation, or to the soil-rock boundary where rock lies below (A.4.7). GB/T 50500-2024 has no "re-measure only beyond some percentage" rule — re-measurable (unit-rate) contracts are re-measured on an item-by-item basis per 7.2.1 (except items priced per lump item); 15% is the boundary for re-rating of unit rates (8.2.1: <= 15% inclusive per 8.9.1, > 15% per 8.9.2).
- →
Cut-and-fill balance calculation and allocation method for municipal road earthwork
The core of cut-and-fill balance: compute quantities by the cross-section method (average-end-area / prismoidal formula) or the grid method -> convert fill to natural in-situ (undisturbed) volume (compacted volume / 0.87 ~= 1.15x) -> compare and determine use/borrow/spoil -> allocate nearby with minimum haul distance. Code basis: GB 50201-2012, GB 50842-2013 Clause 5.1.3, CJJ 44-91 Clause 5.1.3.
Cited By
- ←
Data-taking rules of earthwork and rockwork budget quotas: classifying trenches and pits against general earthwork, classifying dry and wet soil, muck and frozen soil, items already comprehensively included in the quota and not adjustable, determination and successive-multiplication rules for efficiency-reduction conversion coefficients (wet soil, excavation within shoring, excavation between piles, local deepening, deep excavation, vertical soil transport, dynamically compacted ground, etc.), uphill-haul efficiency reduction and allowable over-excavation, and dewatering and shoring to be calculated separately
Earthwork quota data-taking starts with three preliminary steps: (1) classify trench or pit (base width up to 7 m and base length over 3 times the base width, or base length up to 3 times the base width and base area up to 150 m2 - beyond these limits, and not being site levelling, it is general earthwork); (2) split dry and wet soil at the normal groundwater level given in the geological survey data - where dewatering is adopted, the post-dewatering level is the normal water level and dewatering costs are calculated separately; (3) first remove items already comprehensively included and not adjustable (machine excavation already includes manual cleaning of residual layers up to 0.30 m thick on base and slopes, efficiency reduction for loaded uphill hauls at gradients up to 15%, and pipe laying already includes ordinary trench-side shoring). Efficiency reductions then follow the quota coefficients: wet soil by hand labour x1.18; wet soil by machine labour and machines x1.15; hand-dug trenches and pits within shoring x1.43 on labour; soil between piles x1.25 on labour under hand quotas (x1.10 on labour and machines under machine quotas); locally deepened trenches and pits x1.25 on labour and machines; vertical soil transport by hand x1.50; excavation on dynamically compacted ground x1.15; hand excavation beyond 6 m x1.15 per additional metre; where two coefficients coexist they are multiplied successively. Coefficients are taken from the notes of the quota volume actually applied and must not be mixed across volumes.
- ←
The grid method for earthwork balance sheets - the step formulas, cut-and-fill closure checks, and the terrain contrast with the cross-section method (grid spacing, volume-state conversion, and the source of the economic haul distance)
Three passes complete the sheet: grid at 10~40m (20m preferred), corner natural and design levels with the working height h = design - natural ('+' fill, '-' cut), zero points by interpolation joined into the zero line, cell-by-cell net cut and fill listed apart; convert all to one volume state (fill compacted / 0.87 = about x 1.15 to natural dense) and close on 'cut - fill = spoil - borrow', the in-sheet closure being 0 (rounding residue only); computation by one and checking by another, a difference within 3% of the original submits the original, beyond 3% the cause is traced and recomputation follows; the cross-section method, less precise, suits ribbon ground of stronger relief (off-site roads, rail subgrades, trench runs) with sections at 50m (scheme / preliminary) and 20m (construction drawings).
- ←
Classifying divergence between the design earthwork balance and the actual site balance, allocating responsibility among the four parties, and the cost adjustment pathway (with the chain of evidence and the normative basis)
GB 50201-2012 clause 4.1.3 sets the division-of-duty baseline: the balance figures are 'basic balance data put forward by the designer, on which the contractor then performs balance calculations according to the actual situation ... with multiple balance adjustments further made during construction'; hence divergence between the actual and the design table does not of itself constitute a variation or ground a claim. The divergence must first be characterised into three types - measurement-basis type (conversion factors not unified; whoever miscalculated corrects it), factual type (original ground levels / geology / design omissions; allocated by cause) and fault type (the defaulting party bears it, including enlarged losses) - and responsibility then allocated item by item by cause: erroneous original data from the employer, adverse physical conditions, instructed variations and insufficient design documents are borne externally by the employer (which may recover from the investigator or designer), while the contractor bears its own method adjustments, over-excavation and what it should have foreseen.
- ←
Earth and rock haulage pricing: haul distance measured as the nearest distance from the excavation centroid to the fill or spoil centroid, on-site transport already included in excavation line items, off-site transport listed separately as disposal of surplus material and banded as basic haul plus increments, the loading charge taken only once, and hoisting soil from deep excavations charged separately as vertical transport
Earth and rock haul distance is measured as the shortest and nearest distance between the centroid of the excavated (or demolished) material and the centroid of the fill area or the spoil (stockpile) area, the centroid positions being fixed by the approved project execution plan; it means the shortest distance along a traversable haul route, not the straight line between two points. The work content of excavation BOQ items includes only on-site transport; off-site haul must be listed separately as 'disposal of surplus material' (covering loading and haul from the site to the disposal point), and the quota bands it as 'basic haul + increments' (manual cartage with a 20m basic band plus 10m/20m increments; mechanical cartage with a basic band within 1km plus 1km per increment; loader loading and carting of loose soil applying only within 20m). Loading and haul may be split into processes, but the loading charge may be taken only once, in either the excavation or the haul item (excavation 'without loading' line items are converted from the loading line item by coefficient 0.80). Hoisting soil from deep excavations beyond the set depth (commonly 2m) is charged separately as vertical transport at 7m of horizontal haul per metre of depth, but dedicated line items such as large strutted excavations and excavation within bracing already include vertical hoisting and take no further charge.
- ←
Measurement rules for earthworks backfill, haulage and special-case excavation: foundation / room / basement-interior / site backfill, the enlargement zone for excavation between piles, and off-site slurry ratios (per DB11/T 2382-2024 section 4.2)
Excavation and haulage are measured by the natural in-situ volume before excavation; backfill by the as-completed volume after backfilling. Foundation backfill = excavation volume - the volumes of foundations, buildings, structures and blinding buried below the designed exterior ground level; room backfill = area between main walls (less heating trenches, cable trenches, drainage trenches and equipment foundations) x (height from the designed exterior ground level to the underside of the first-floor blinding); site backfill = backfill area x backfill thickness; haulage quantity = total excavated volume - total backfill volume. Excavation between piles covers all soil within 1.20m beyond the outer edges of piles / anti-floating anchors / pile caps, or within zones where adjacent outer edges are no more than 4m apart, between the pile-top level (effective pile length plus the design over-cast length) and the underside of the blinding (or cushion), less the volumes of pile bodies and empty bores. Slurry hauled off site: mixing piles, grouting piles, anchors, anchor cables and soil nails at 10% of the formed pile or bore volume; diaphragm walls, trench-cutting cement-soil walls and cast-in-place piles at 50% of the formed pile volume.
- ←
Selection conditions for earthwork quantity methods (cross-section method, square-grid method, triangular-network method), and rules for cross-section spacing, density, survey point layout and accuracy tolerances in cross-section surveying
Earthwork calculation should match the method to landform, area size and topographic-map accuracy, and should be checked with a second method: elongated strips such as roads, pipelines and channels with sharp relief or irregular cut and fill suit the (cross-)section method; site levelling suits the square-grid method (grid side 10~40 m, 20 m preferred) or the triangular-network method. Section spacing follows the works type - for the section method L should be 5~20 m; in elongated road and pipeline strips the spacing of section points and of adjacent sections should not exceed 5 m; railway subgrade cross-sections are usually at 20 m, with sections also taken at kilometre posts, hectometre posts and sharp terrain changes, and rebuilt railways need no fewer than 3 sections per 100 m; the smaller L, the higher the accuracy and the larger the computation load - a tension between accuracy and speed.
- ←
BOQ itemisation and measurement wording for earthworks under GB/T 50854-2024 Appendix A: item setting and codes for excavation, backfill, disposal of surplus material, borrowed-soil backfill and site levelling; the two ledgers of natural in-situ volume versus compacted volume; the balance formula; pricing splits; and the listing boundary of vertical cut-and-fill
GB/T 50854-2024 Appendix A splits earthworks into three sections: standalone earthworks (010101), foundation earthworks (010102), and site levelling plus others (010103), with disposal of surplus material and site levelling sitting in 010103. A.4.10 provides that excavation and backfill quantities take no account of conversion between compaction states, so excavation is the natural in-situ geometric volume before cutting and backfill is the compacted (as-formed) volume shown on the design, both in m3, and the two can be subtracted directly - disposal of surplus material = excavation BOQ quantity - reusable backfill BOQ quantity; the backfill quantity must deduct the volumes of buried members such as foundations, bedding and pipes; borrowed-soil backfill still lists a single backfill item, with its pricing split into borrowing (soil purchase) + off-site haulage + placement and compaction; A.4.13 makes disposal of surplus material cover loading, haulage and disposal-compliance requirements to the designated tip, with the haul distance and tipping fees inside its all-in unit rate; A.4.12 defines site levelling as in-place cut, fill, haul and level within +/-300 mm of the site datum, measured in m2 (first-floor gross floor area), while vertical cut-and-fill beyond +/-300 mm is listed under standalone earthworks in m3.
- ←
Multi-basis volume conversion for earthworks in practice: truck trips in loose (bulked) volume, BOQ and final account quantities in natural in-situ volume, backfill in compacted volume - basis analysis and conversion rules
Four volume bases must be kept apart: BOQ and quota quantities for excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation (GB/T 50854-2024 Annex A clause A.4.10: quantities of earth and rock excavation and backfill take no account of conversion between compaction states, so BOQ quantities must not be multiplied by further compaction factors); backfill and placed fill as products are measured in the compacted (completed) volume after placing; on-site haulage truck trips are counted in loose (bulked) volume; spoil disposal declarations are made in loose volume. Conversion rules: total truck volume divided by the loose-volume factor (soil 1.30 / rock 1.54 / sand-gravel mixture 1.07) = natural in-situ volume (the settlement quantity), and multiply the same factor in reverse; compacted volume / 0.87 (about x1.15) = natural volume; railway subgrade takes its factors from TB/T 10822-2024 Table 2 by design speed class and soil class, not the generic 1.15.
- ←
The loose-laying coefficient of earthworks: standard definition, formulas and how it is fixed - trial sections, back-calcculating loose thickness from the degree of compaction, and converting stockpile quantities
Loose-laying coefficient K = loose thickness / compacted thickness = compacted dry density / loose dry density (GB 51254-2017 clause 2.1.4; CJJ 4-97 Appendix F formula F.0.3); earthworks have no code value table - K must be fixed by compaction trials (trial sections) per the fill-material x compaction-equipment pair, codes giving values only for specific materials (graded crushed stone 1.4~1.45 hand-mixed, 1.3~1.35 grader-spread); back-calculation: loose dry density = max dry density x degree of compaction / K, and loose / stockpile volume = compacted volume x K.
- ←
Defining the scope of bridge abutment backfill (fill behind abutments): longitudinal backfill length, full-width transverse placing, whether fill under the approach slab belongs, plus fill material, compaction requirements, measurement by volume and quota application
Abutment backfill is the filling of the gap between the rear face of the abutment stem (back wall) and the original ground/subgrade, including the areas behind the wing walls, the backfill under the approach slab and the abutment drainage layer; it excludes pile-cap excavation backfill and conical-slope surface protection. The longitudinal length follows CJJ 2-2008 clause 11.5.7 item 3: not less than the abutment height plus 2m at the top of the stem and not less than 2m at the bottom, and for arch bridges not less than 3 to 4 times the abutment height (the design governs where specified); transversely it is placed to the full designed width in one operation, simultaneously with the conical slopes. Backfilling may start only when the abutment/retaining-wall concrete has reached 75% of the design strength, and the degree of compaction of the transition zone behind the abutment must exceed 96%. The backfill is measured by volume (m3) and priced by quota line item according to fill class; the approach slab itself is a separate line item.
- ←
Deciding between earthwork and rockwork quotas in excavation, and the three soil / rock classification systems with the route to quota items
The test is excavation difficulty, not the geological name: soil dug with shovels, picks and mattocks and fully loaded by machines direct takes earthwork quotas; ground needing ripping, prying, pneumatic breakers or blasting takes rockwork quotas, the line falling between hard soil (class 4) and soft rock (class 5); the class is fixed from the geological survey report against the classification table of the quota volume in use. Building and municipal works use classes 1-2 / 3 / 4 soils and extremely soft to extremely hard rock in five grades; highways use loose / ordinary / hard soil and soft / moderately hard / hard rock (mapping to the 6- and 16-grade I-XVI systems); the Protodyakonov system counts I-IV as soil and V-XVI as rock; then the item follows the method, excavation form (trench / pit / general), depth and dry / wet soil.
- ←
Pricing归属 of foundation probing (rod probing/tamping) in Beijing: already综合 in the manual-excavation item work contents, not itemized separately
Beijing DB11/T 2382-2024, 4.2.2: "manual excavation consumption is determined by soil class and shall include rod probing and bottom tamping" — foundation probing has no separate item; it is priced with the manual digging/pit items by soil class; with machine digging, hand trimming of the base (300mm where design is silent) uses the manual items, probing included (4.2.2(3), 4.2.15(2)). On the BOQ side, GB/T 50854-2024 makes base probing a "base treatment method" characteristic description, not a standalone code. Genuine separate listing (e.g., subcontract caliber) is a missing item — compile a supplementary unit-price estimate and guard against double pricing with the manual digging items.
- ←
Locating quota sub-items for earth backfill, replacement-subgrade, and muck loading/hauling in Beijing DB11/T 2382-2024
Replacement fill is priced under the ground-treatment chapter Table A.2.1-1 replacement subgrade (A-2-1 manual sand-gravel fill, A-2-3 sand (stone-chip) spreading; work content: layered spreading, leveling, compaction); indoor backfill under the earthworks chapter A.1.3-1 foundation backfill A-1-42 (backfill, leveling, compaction); site backfill and surplus-soil loading/hauling under A.1.3-2 / A.1.4-1 (A-1-51 soil loading, haul within 1 km; A-1-52 rock (muck) and spoil loading; work content includes haul, unloading, disposal, including spoil or muck disposal material).
- ←
Classifying earthworks: separate earthworks (010101) versus foundation earthworks (010102) split by the "preset level", and how large-area replacement fill is classified (GB/T 50854-2024 Annexes A / B)
The single dividing line of earthworks classes is the "preset level" (design outdoor level / soffit level of the external ground build-up / level nominated by the client), regardless of how large the replacement area is: above the line, separate earthworks (010101) bringing the site to the preset level; below the line, foundation earthworks (010102) executed for the foundations. Large-area replacement fill sorts three ways: site-fill type - separate earthworks backfill (010101003, by volume on the cut-and-fill dimensions between the original ground and the preset level, table A.1.1); replacement cushions at or within pits for ground improvement - Annex B ground treatment (010201001, by volume at design-shown dimensions); if counted merely as earthworks, foundation earthworks; site levelling within plus/minus 300 mm of the level - by area.
- ←
Overview of quantity take-off for construction works: basis, general rules and per-trade calculation methods
Quantity take-off rests on the four-tier basis "contract agreement -> design drawings -> approved project execution plan (construction methodology and site organization) -> appendix rules of the quota norms/measurement standards"; except where rules provide otherwise, all quantities are computed from the dimensions shown on the design drawings. General rules include: calculation per appendix rules (mandatory provisions of codes); the no-deduction threshold of single holes <=0.3 m2; significant figures of units of measurement (t/km three decimals; m/m2/m3/kg two; counts integer); and dual-track BOQ vs quota-norm quantities. Earthwork, concrete, reinforcement, formwork, masonry, waterproofing, finishes etc. each have standard algorithms.
- ←
Railway 2024 quota norms (prescribed resource consumption standards; TB/T 10822-2024): subgrade slope smooth (pre-split) blasting and deep-hole blasting — application of quota items and dual area/volume overlay measurement rules
In the Railway 2024 quota norms, smooth (pre-split) blasting is an independent quota item family LY-58/59/60 (hole diameter 70-120 mm, unit of measurement 100 m2, measured by design slope area) that must be applied separately and 'shall be used in addition to other rock-excavation quota norms'; the main deep-hole blasting LY-46~51 is measured per the natural in-situ (undisturbed) volume inside the design excavation line (100 m3). The two are priced cumulatively, with quantities mutually non-deducting and each listed independently.
- ←
Applying the railway subgrade controlled-blasting quota: class A/B/C judgment conditions and item selection (TB/T 10822-2024, Volume 1, Chapter 1)
The controlled-blasting quota applies only to rock excavation "near an existing railway where a second track is added and blasting must be controlled", classed A/B/C by construction conditions (A strictest: line spacing <=5 m, cut height >=8 m, cut thickness <=4 m, existing slope >1:0.5, sub-hard rock or harder; B: spacing <=10 m, thickness <=10 m, existing slope <=1:0.5; C: neither A nor B, but no natural screen within 50 m of the existing cut slope crest), judged in A->B->C order. The quota already includes possession-caused efficiency loss — no train-interference construction additional fee. Without an existing line (e.g., near villages only), controlled blasting does not apply: use deep/shallow-hole blasting (spoil or requiring crushing: LY-46/47/48/52/53/54; direct cut-to-fill: LY-49/50/51/55/56/57) or static blasting + rock breaking, plus the blast-coverage quota per the blast design.
- ←
Beijing 2024 consumption-quota earthwork measurement basis: excavation/fill/haul by drawing volume without bulkage factors — factors used only for disposal estimation and earthwork balance
When compiling budgets under the Beijing 2024 quota (DB11/T 2382-2024), excavation (Clause 4.2.11, by natural in-situ (undisturbed) volume before excavation), backfill (Clause 4.2.21), and haulage (Clause 4.2.25 = total excavation volume - total backfill volume) are all measured directly by drawing volume with no bulkage/conversion factor; GB/T 50854-2024 likewise provides that excavation and backfill quantities involve no compaction-state conversion. Conversion factors are used only for: total muck-disposal estimation (JGJ/T 498-2024, Ve = λc·Vc - λf·Vf, in loose volume), earthwork balance (1 m³ of compacted fill needs about 0.87 m³ of natural in-situ (undisturbed) soil), and purchased soil/truck dispatching (loose = solid x 1.30).
- ←
Whether pipe-trench backfill quantities deduct the pipe volume: the 500 mm diameter demarcation rule and comparison of standards' calibers
Whether trench backfill deducts the pipe volume is demarcated at (nominal) diameter / pipe structural width 500 mm in most systems: <=500 mm no deduction; >500 mm deduct per the quota appendix table (m3/m) or the actual volume of pipe and base/cushion, with some systems (Shenzhen) also including chambers and other auxiliary structures; Hunan 2025 requires deducting the full pipe volume when backfilled with purchased sand/gravel; Beijing DB11/T 2382-2024 municipal/landscape caliber is "minus pipes and structures" with no 500 mm exemption. The text of the standard volume adopted governs.
- ←
Railway 2024 quota norms, building works volume (TB/T 10831-2024 Volume 10): site leveling vs cut-and-fill earthwork boundary (±30 cm) and measurement rules
Under the railway 2024 quota norms system, cut-and-fill leveling within a thickness of ±30 cm uses "site leveling" (FY-65 manual 442.89 yuan/100 m2, FY-66 mechanical 97.43 yuan/100 m2, base-period prices); cut and fill beyond ±30 cm is treated as foundation-pit or general earth/rock work and measured by volume. Site-leveling quantity is computed from the building's (structure's) first-floor gross floor area (GFA) (the area enclosed by the structural perimeter) per the design drawings, with the portions where the basement structure projects beyond the first-floor perimeter merged into the calculation.
- ←
Railway building-works quota TB/T 10831-2024 earthworks: trench-pit vs general earthworks division, manual/mechanical boundary (depth >6 m mechanical), and the <=0.30 m manual bottom-cleaning included in mechanical excavation
Building pit excavation first tests "trench-pit" or "general earth-rock" per volume note 2: trench-pit means trenches with bottom width (design bedding or foundation width) <=7 m and length >3 x width, or pits with length <=3 x width and bottom area <=150 m2; beyond these, unless site grading, it is general earth-rock. Depth <=6 m: manual (FY-1~FY-12) or mechanical (FY-31~FY-42) per the actual method; depth >6 m "shall be treated as mechanical excavation". Mechanical earthwork already comprehends manual cleaning and trimming of the <=0.30 m left at base and slopes — "must not be adjusted in use"; no separate manual bottom-cleaning item.
- ←
Rock blasting quantity take-off: by pre-blasting natural in-situ (undisturbed) volume (bank measure), and itemization linkage with GB/T 50854-2024 earthworks
Rock blasting BOQ quantities are measured in bank measure (pre-blasting natural in-situ (undisturbed) volume), not loose volume; rock that is not naturally dense converts per GB/T 50862-2024 Table A.5.3 (rock loose 1.54, block stone 1.75, sand-stone mix 1.07). Blasted rock in building BOQs is itemized per GB/T 50862-2024 code 090101 series (GB/T 50854-2024 Appendix A, A.4.14), and per A.4.10 both excavation and backfill ignore densification-state conversion — loose/compacted differences are absorbed by all-in unit rates.
- ←
Measurement unit for earthwork filling items: compacted volume (as-completed backfill / post-rolling volume); excavation, haul, and surplus disposal by natural in-situ (undisturbed) volume; loose volume only for loose-fill items and bulking estimates of waste haul
Filling (backfill/rolling/compaction) is measured in compacted volume: railway subgrade by design fill section as compacted volume (TB/T 10822-2024); building/water backfill by as-completed backfill volume and post-rolling volume (TB/T 10831/10832-2024) — neither loose nor natural volume; excavation, haul, and surplus disposal by pre-excavation natural in-situ (undisturbed) volume. Conversion baseline: loose 1.30 = loose-filled 1.08 = natural in-situ 1.00 = compacted 0.87 — i.e., 1 m3 compacted needs about 1.15 m3 natural in-situ soil or about 1.5 m3 loose volume; so filling items lock the compacted-product basis — quantity by design compacted volume with no bulking factor.
- ←
TB/T 10822-2024 subgrade earthworks: excavator self-dig-self-dump vs excavator loading + dump-truck haul — haul-distance boundaries (20 m / 1 km / 10 km x 0.85)
One criterion: does the excavated soil enter the truck-haulage stage? Soil cast in place within the excavator's working radius -> book "excavator self-dig-self-dump" (LY-1~3, work content "position, dig, dump", no haul); soil requiring dump-truck transfer -> split into "excavator loading" (LY-4~15, by bucket capacity 0.6~2.5 m3 + soil class) + "dump-truck soil haul" (LY-20~25, 8/15/25 t, base item for haul <=1 km plus (actual haul - 1) km of "incremental 1 km" items). Distance boundaries per the chapter notes: loader haul of loose soil applies only within 20 m (beyond that, use dump trucks); truck incremental-haul items apply only within 10 km (the part beyond 10 km x 0.85). The split combination costs roughly 2.8x self-dig-self-dump at base-period prices — book according to the real soil-allocation flow.
- ←
Railway 2024 quota subgrade purchased-fill material fee: when chargeable, how the fill price is built up, and the caliber distinction from material costs (TB 10801-2024 clause 3.5 / TB 10811-2024 clause 2.5.1)
The fill-material fee is charged only for filling materials obtained by **purchase** (soil, rock, permeable material, mineral material etc. not treated as materials), built up as "fill fee = sum(fill consumptions x fill price)" (TB 10801-2024 clause 3.5.2); the fill price is exclusive of deductible input VAT and is determined by investigation and analysis by the design organization (TB 10811-2024 clause 2.5.1) — it does not enter the material library, carries no purchasing and custody charges, and is not subject to price adjustment (for fluctuation). Self-excavated reuse (cut-to-fill) carries no fill fee; land-related costs of borrowing from temporarily occupied land go under Chapter 1 temporary land-use fees. This differs sharply from the clause-3.2 works material cost (norm-based material price for estimating = (material price at source + freight and handling included in the material price) x (1 + purchasing and custody rate)); in practice the test is "whether it appears in the quota consumption table".