Engineering Knowledge Cards.
Confidence HighUpdated 2026-11-04

Earthwork volume conversion coefficients and spoil haul-off disposal estimation (loose / loose-fill / natural-dense / compacted conversion)

Excavation and haul are measured by the pre-excavation natural in-situ (undisturbed) volume, backfill by the post-backfill volume, and different states are converted by coefficients (natural in-situ (undisturbed) 1.00 <-> loose 1.30 <-> loose fill 1.08 <-> compacted 0.87); total spoil disposal Ve = lambda-c x Vc - lambda-f x Vf (JGJ/T 498-2024), with lambda-c soil 1.30 / rock 1.54 / sand-rock mixture 1.07.

Applicable Codes

  • TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) 册说明十一(一)表 4
  • TB/T 10832-2024 · Railway works budget quota manual: Water Supply and Drainage Works, Vol. 11 (2024 series) 册说明五(一)表 1
  • TB/T 10822-2024 · Budget Quota of Railway Engineering (Volume 1: Subgrade Works) 册说明表 2
  • JGJ/T 498-2024《施工现场建筑垃圾减量化技术标准》第 4.0.2 条及条文说明表 2
  • GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. A 第 A.4.10 条
  • GB 50842-2013《建材矿山工程施工与验收规范》附录 B 表 B.0.1、第 B.0.2 条
  • GB 50201-2012 · Code for Construction and Acceptance of Earthwork and Blasting Engineering 第 4.5.4 条
  • 陕西省新编房屋建筑与装饰工程消耗量定额 表 1-4(征求意见稿)
  • 湖南省房屋建筑与装饰工程消耗量标准 土石方说明
  • 江苏省建筑与装饰工程消耗量定额 土方章说明

Topic Positioning

Conversion coefficients among the four volume states of earth and rock work (loose, loose fill, natural in-situ (undisturbed), compacted), and the estimation method for the total haul-off disposal volume of engineering spoil.

Core Conclusions

(1) Measurement convention: excavation and haul quantities are calculated by the pre-excavation natural in-situ (undisturbed) volume, backfill by the post-backfill (completed/compacted) volume; different states are converted by the coefficient table. General earthwork coefficients with natural in-situ (undisturbed) = 1.00 as the base: loose fill 1.08, loose 1.30, compacted 0.87 (railway TB/T 10831-2024 Volume 10 Table 4; TB/T 10832-2024 Volume 11 Table 1); rock loose 1.54, sand-rock mixture loose 1.07, etc. (2) Building BOQ measurement (GB/T 50854-2024 Appendix A.4.10) stipulates: when calculating excavation and backfill quantities, no conversion between volumes of different compaction states is considered — BOQ quantities follow the design-drawn natural in-situ (undisturbed) convention, distinguished from conversions at the consumption/haul stages. (3) Spoil disposal estimation (JGJ/T 498-2024 Clause 4.0.2): Ve = lambda-c x Vc - lambda-f x Vf, where Ve is the estimated total spoil disposal volume (in loose volume); Vc is the excavation volume (natural in-situ (undisturbed)); Vf is the quantity reused as backfill in this project after excavation (post-backfill volume); lambda-c is the loose-volume haul-off conversion coefficient — soil 1.30, rock 1.54, sand-rock mixture 1.07; lambda-f is the backfill conversion coefficient — loose-fill soil 1.20, rock 1.18, sand-rock mixture 1.14, and compacted fill is interpolated in the 1.45-1.58 range per the compaction coefficient 0.90-0.98.

Applicable Boundaries

Conversion coefficients differ slightly among quotas/standards — the current industry or local quota table governs; the volume conventions of the preparation of the bill of quantities, norm resource consumption, and spoil haul stages differ, so do not mix them; working space and slope gradient are calculated separately as specified in each standard.

Further Reading

TB/T 10831-2024 Volume 10 Table 4; TB/T 10832-2024 Volume 11 Table 1; GB/T 50854-2024 Appendix A.4.10; JGJ/T 498-2024 Clause 4.0.2 and Table 2.

Keywords

Cited By