Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-29

Pricing归属 of foundation probing (rod probing/tamping) in Beijing: already综合 in the manual-excavation item work contents, not itemized separately

Beijing DB11/T 2382-2024, 4.2.2: "manual excavation consumption is determined by soil class and shall include rod probing and bottom tamping" — foundation probing has no separate item; it is priced with the manual digging/pit items by soil class; with machine digging, hand trimming of the base (300mm where design is silent) uses the manual items, probing included (4.2.2(3), 4.2.15(2)). On the BOQ side, GB/T 50854-2024 makes base probing a "base treatment method" characteristic description, not a standalone code. Genuine separate listing (e.g., subcontract caliber) is a missing item — compile a supplementary unit-price estimate and guard against double pricing with the manual digging items.

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) (北京)
  • GB/T 50854-2024 · Standard for measurement of building construction and fitting out works
  • 北京市2021版建设工程消耗量标准(对照)

Topic Positioning

The norm-pricing归属 and placement of foundation probing (rod probing and bottom tamping) in Beijing: no separate item — included in the manual-excavation item work contents and priced with foundation earthwork.

Core Conclusions

  1. Basis (DB11/T 2382-2024, 4.2.2):
  • (1) "Manual excavation consumption shall be determined by soil class and shall include rod probing and bottom tamping";
  • (3) "Machine-excavation items preferably exclude hand trimming of the trench/pit bottom; hand trimming consumption may use the manual excavation items". Hence probing (rod probing) is not a new item; its cost sits in the selected manual digging/pit items.
  1. Item evidence: building volume A-1-19 "manual pit excavation, soil class I-II" (m3) work content "dig, haul, trim edges, rod probing and tamping", consumption includes electric probing machine 0.0039 shifts; Beijing 2021 item 1-5 "manual excavation, soil class I-II" likewise includes 0.0039 shifts. Neither edition sets a standalone "probing" item — same caliber.
  2. Machine-dig projects: hand base trimming uses the manual items (4.2.2(3)); the reserved hand-trim depth is preferably 300mm where the drawings are silent (4.2.15(2)) — that manual item already includes probing/tamping.
  3. BOQ side (GB/T 50854-2024 Annex A): base probing is a characteristic of the earthwork BOQ item — "the 'base treatment method' characteristic may describe base compaction, base probing, etc." — not an independent code.
  4. If separate listing is unavoidable (subcontract caliber): Beijing has no standalone item — a missing-item case; analyze via a supplementary unit-price estimate and avoid double pricing with the manual items (which already include probing/tamping).

Applicable Boundaries

  • Beijing pricing caliber (DB11/T 2382-2024 consistent with 2021) for probing within building/decoration earthwork items.
  • Across volumes (municipal, landscape) or industries (railway, highway), check the specific item work contents — do not transplant this caliber.
  • Premise: probing per drawings and acceptance codes; special design/contract requirements govern.
  • No unit prices here — price per market at compilation.

Further Reading

  • DB11/T 2382-2024 Section 4.2: 4.2.2 (manual/machine item setup, probing/tamping), 4.2.15 (base areas, depths, slope increments; 300mm hand trim; Tables 4.2.15-1/-2).
  • Annex A item A-1-19 (Table A.1.1-3) work content and consumption.
  • GB/T 50854-2024 Annex A "base treatment method" characteristic provisions.
  • Beijing 2021 item 1-5 cross-check.

Keywords

  • 基础钎探
  • 打钎拍底
  • 基底钎探
  • 人工挖土方
  • DB11/T 2382-2024
  • 消耗量标准
  • 定额套项