Railway 2024 quota norms, building works volume (TB/T 10831-2024 Volume 10): site leveling vs cut-and-fill earthwork boundary (±30 cm) and measurement rules
Under the railway 2024 quota norms system, cut-and-fill leveling within a thickness of ±30 cm uses "site leveling" (FY-65 manual 442.89 yuan/100 m2, FY-66 mechanical 97.43 yuan/100 m2, base-period prices); cut and fill beyond ±30 cm is treated as foundation-pit or general earth/rock work and measured by volume. Site-leveling quantity is computed from the building's (structure's) first-floor gross floor area (GFA) (the area enclosed by the structural perimeter) per the design drawings, with the portions where the basement structure projects beyond the first-floor perimeter merged into the calculation.
Applicable Codes
- TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works)
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects
Topic Positioning
Within the railway 2024 quota norms system (TB/T 10831-2024 "Railway works budget quota manual (China Railway), Volume 10: building works"): the boundary criterion (±30 cm) between "site leveling" and "cut-and-fill earthwork", the quantity measurement rules (first-floor gross floor area (GFA)), and the companion earth/rock measurement provisions — for pricing and auditing earthworks of railway buildings, station buildings and similar works.
Core Conclusions
- Boundary criterion ±30 cm: Section 1 "site leveling and site rolling" quota norms work content, as written — "manual site leveling, including cut-and-fill leveling within elevation ±30 cm" and "mechanical site leveling, including grading". Cut-and-fill leveling within ±30 cm -> FY-65 manual site leveling (100 m2, base-period base price 442.89 yuan, all labour) or FY-66 mechanical site leveling (100 m2, base-period base price 97.43 yuan, of which labour 8.69 yuan and plant 88.74 yuan); cut/fill thickness beyond ±30 cm -> not site leveling; apply foundation-pit earth/rock or general earth/rock items by cut/fill and measure by volume.
- Quantity area caliber: volume notes (11) item 1, as written — "Site leveling is computed from the design drawings as the first-floor gross floor area (GFA) (the area enclosed by the structural perimeter) of the building (structure). Where the outer edge line of the basement structure projects beyond the outer edge line of the first-floor structure, the gross floor area (GFA) of the projecting portion is merged into the calculation." That is, measurement is by first-floor gross floor area (GFA) (area enclosed by the structural perimeter), not the ground-area projection of the site; basement projections are merged in. Unit of measurement 100 m2.
- Companion earth/rock measurement rules (volume notes (6)-(13), all by volume):
- Foundation-pit / general earth/rock: per the design dimensions of the foundation (including bedding), plus working-space width, soil-slope width or the rock allowance for overbreak, multiplied by excavation depth, computed by volume; earth/rock of ramps for mechanical construction is merged into the corresponding quantities.
- Silt and flowing-sand excavation is computed by volume at the position and boundaries shown on the design drawings.
- Excavation between piles: excavation within 1.20 m outward from the edge of pile caps; where the distance between the edges of adjacent pile caps is <=4 m, all excavation between them is excavation between piles; it does not deduct the volumes occupied by pile bodies and empty bores.
- Manual excavation of frozen soil (including excavation after blasting): per design dimensions plus working-space width, by volume.
- Backfill: trench/pit backfill = excavated volume − volumes of the building and foundation (including bedding) below the design outdoor ground level; room backfill (including inside basements) = net area between main walls (deducting foundations etc. with individual base area over 2 m2) x backfill thickness; site-area backfill (including above basement roof slabs) = backfill area x average backfill thickness.
- Soil haulage: excavated volume minus backfill volume, computed in natural in-situ (undisturbed) volume.
- Earth-retaining boards are measured by the vertically supported area of trench/pit; width is the design width plus 0.10 m on one side, 0.20 m on two sides.
- Wellpoint sets: light wellpoint 50 tubes per set, ejector wellpoint 30 per set, large-diameter wellpoint 10 per set; where accumulated installed/removed tubes are fewer than one set, one set is counted; dewatering usage days count 24 hours per day-night, determined by the project execution plan (construction methodology and site organization); where the project execution plan (construction methodology and site organization) does not fix the well tube spacing, 0.8-1.6 m for light wellpoints, 2-3 m for ejector wellpoints and 8-10 m for large-diameter wellpoints may be used.
- Pump operation: 8 hours = one shift; under 4 hours counts as 0.5 shift, over 4 and under 8 hours counts as 1 shift; in continuous day-and-night operation one day-night counts as 3 shifts.
- Interface with piling: Section 2 "piles and foundation works" notes — "The items of this section do not cover, before pile works, site leveling, surface compaction, and treatment of underground obstructions; where incurred, compute separately", i.e. apply FY-65/FY-66 separately; pile-position probing is comprehensively considered in the various pile items and is not computed separately.
Applicable Boundaries
- These rules come from TB/T 10831-2024 Volume 10 building works and apply to building works of railway buildings, station buildings etc.; they do not apply to the subgrade volume (Volume 1, TB/T 10822-2024) — the corresponding concept there is "original-ground clearing" (within and below 30 cm of the original ground use the clearing items; where the design depth exceeds 30 cm, the portion below 30 cm is measured as cut); the boundary object differs from the building works volume, so distinguish the volumes when applying and never mix them.
- Base prices are 2024 quota norms base-period prices; actual pricing applies adjustments for price differentials (labour/materials/plant adjusted separately per the compilation measures).
- Site leveling covers only cut-and-fill leveling within ±30 cm; deep cut/fill and earth/rock requiring slopes/working space/support always go through foundation-pit / general earth/rock volume measurement and must not apply site leveling by area.
Further Reading
- Quota norms text: TB/T 10831-2024 "Railway works budget quota manual (China Railway), Volume 10: building works", Chapter 1 Section 1 "site leveling and site rolling" items FY-65/FY-66; volume notes (6)-(13) earth/rock measurement rules; Section 2 "piles and foundation works" notes.
- System context: TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects" (effective 1 January 2025, replacing TZJ 1001-2017); railway building works use this volume.
- Comparative references: the cross-volume boundary rule that bridge/culvert open-cut pits use the bridge volume's QY items rather than the subgrade volume's LY items; item use and haul-distance boundaries for subgrade earthwork excavation and haulage; GB/T 50854-2024 foundation earthwork BOQ measurement (BOQ quantity includes working space, excludes slopes — comparable with the railway quota norms caliber); earth/rock volume conversion factors (natural in-situ (undisturbed)/loose/compacted).