Applicability relationship between comprehensive scaffolding and individual scaffolding and their quantity calculation rules (railway buildings quota TB/T 10831-2024)
Comprehensive scaffolding and individually priced scaffolds must not be double-counted on the same project: only items unsuitable for comprehensive scaffolding are executed under the corresponding individually priced scaffold items. Comprehensive scaffolding is calculated by gross floor area (GFA); exterior scaffolding by exterior wall face length × height (no deduction for door/window openings); birdcage (full-area) scaffold by clear indoor area split into a basic layer and additional layers; isolated columns and cast-in-place beams apply the double-row exterior scaffolding item × factor 0.30.
Applicable Codes
- TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) 册说明四、五、六
- TB/T 10831-2024 Ch. 1土建工程第四节 脚手架工程(FY-415~FY-442)
- 湖南 2025 版《房屋建筑与装饰工程消耗量标准》第十八章 脚手架工程
- 陕西《新编消耗量定额》(征求意见稿)脚手架工程量计算规则
- 江苏省 2026 版《建筑与装饰工程消耗量标准》脚手架章
Topic Positioning
This card covers the core rules of the scaffolding works of the railway buildings quota (TB/T 10831-2024 Vol. 10): the applicability relationship between comprehensive and individually priced scaffolds, and the quantity take-off (measurement) rules for each scaffolding type, for budget preparation, measurement and pricing, and compliance checking.
Core Conclusions
Comprehensive scaffolding and individually priced scaffolds must not be double-counted on the same project: only items unsuitable for comprehensive scaffolding are executed under the corresponding individually priced scaffold items. Comprehensive scaffolding is calculated by gross floor area (GFA), with eaves height taken from the design outdoor ground to the drip line of the eaves; stair rooms, lift rooms, water tank rooms, and skylights projecting above the roof are excluded. Exterior scaffolding is calculated by area as the exterior wall face length (including pilasters and attached shafts) × exterior wall height; where a parapet exists, measured to the parapet top; no deduction for door/window openings; where the same building has different heights, calculated separately. Birdcage (full-area) scaffold is calculated by clear indoor area: heights 3.60–5.20 m count as the basic layer, above 5.20 m each additional 1.20 m counts one additional layer, and remainders under 0.60 m count as one additional layer × factor 0.50. Interior scaffolding and interior wall finishing scaffolding are calculated by the vertical projected area of the wall face, without deducting door/window openings. Isolated columns: structural perimeter plus 3.60 m × height, applying the double-row exterior scaffolding item × factor 0.30; cast-in-place concrete beams: height from beam top to ground (floor) × clear beam span, likewise applying double-row exterior scaffolding × factor 0.30. Exterior scaffolding already includes ramps, loading platforms, and guard rails; where the story height exceeds 3.60 m and the ceiling requires plastering, painting, or suspended ceilings, birdcage (full-area) scaffold may be added, but wall finishing scaffolding is no longer calculated for that part.
Applicable Boundaries
Applies to the quota basis of railway building works (TB/T 10831-2024 Vol. 10). Local quotas (e.g., the Beijing 2021 building and decoration consumption standard) follow the same "no double counting" principle, but item divisions and factors (e.g., birdcage (full-area) scaffold height bands) may differ slightly — the current local quota notes govern. Where full steel-pipe staging quotas are used for over-height/over-weight beam-slab formwork, the over-height concrete placing surcharge is not counted again.
Further Reading
See TB/T 10831-2024, Railway Budget Quota Vol. 10 Buildings, Section 4 "Scaffolding Works", items "IV. Comprehensive scaffolding", "V. Individually priced scaffolds", "VI. Quantity take-off (measurement) rules"; the volume notes additionally govern interior wall finishing, addition of birdcage (full-area) scaffold, parapets over 1.20 m using interior scaffolding, and factors for members placed beyond 3.60 m indoors.
Keywords
- 脚手架工程量计算
- 综合脚手架
- individually priced scaffolds
- 满堂脚手架增加层
- interior scaffolding
- 外脚手架
- 建筑面积口径
- 投影面积
Related Cards
- →
Rules for pricing fencing (wall) and finishing works scaffolding by applying quota line items: the 3.60 m threshold, interior finish / birdcage (full-area) / cradle classification, and regional system differences (railway / Hunan / Jiangsu / Beijing)
Fencing (wall) scaffolding is banded by masonry height: ≤3.60 m by interior scaffolding, above that by the single-row exterior scaffolding item (TB/T 10831-2024; Hunan/Jiangsu likewise use the 3.6 m boundary). Finishing scaffolding by location: interior wall finishing above 3.60 m executes the interior-wall finishing scaffolding item; where the story height exceeds 3.60 m and the ceiling is finished, a birdcage (full-area) scaffold may be added and wall finishing scaffolding is not counted separately (mutually exclusive); exterior cradles by vertical projected exterior wall area without deducting openings; exterior masonry scaffolding beyond 15 m or with finished area over 60% executes double-row. Beijing's quantity-price-fee separation system sets no scaffolding items — priced as non-precisely-measurable preliminary items on a market basis.
- →
Screening double counting in budget documents: five high-frequency duplication scenarios and judgment principles
The general principle for judging double counting: content already included in the work content must not be charged again, separately listed items must not be recomputed, and mutually exclusive items can be taken only once. High-frequency duplication falls into five classes: ① between quota line items (cast-in-place concrete already includes formwork — no separate formwork item; auxiliary content such as machinery relocation and material transport already included); ② between preliminaries and work-sections (vertical transport covers only large machinery, the rest already being in the work-sections; costs of separately listed preliminary items must not be double-counted); ③ within preliminaries (comprehensive vs. individually priced scaffolds — choose one; birdcage (full-area) scaffold and wall-finishing scaffolding are mutually exclusive; height-increase fee keyed to work points above 25 m); ④ other-item fees (provisional sums reduced at settlement by price adjustments; claims carry taxes and duties only); ⑤ fee accrual and taxes and duties (the base to which percentage rates are applied and taxation of free-issue materials (by the employer) must not be duplicated).
- →
Conversion judgment and methods when a quota item's work content differs from site reality (no conversion for aggregated content; convert by difference type; supplementary valuation for missing items; "换" mark traceability)
Before converting, judge "whether conversion is allowed": content already aggregated in the quota (formwork support content aggregating steel/wood props, external scaffolding aggregating ramps/loading platforms, on-site handling already included) may not be adjusted even if inconsistent with reality; adjustment is allowed only where technical conditions differ significantly from the quota's basis. Convert by difference type: coefficient adjustment; strength grade / mix-proportion conversion (per mix tables or formulas); thickness increment/decrement items; material substitution (bracketed materials priced separately, ready-mixed concrete deducting mixing-equipment consumption). Missing items are not converted — prepare a supplementary unit valuation table per the quota compilation principles (GB/T 51095-2015 Clause 5.3.12); converted quota codes must carry the "换" mark for traceability.
Cited By
- ←
Decomposition of the external-wall scaffolding quantity formula: length of the external wall face x external wall height, the single-row and double-row switching criteria (15m masonry height / 60% openings-and-finishes ratio), the no-deduction rule for door and window openings, the 3.60m inside-outside scaffold boundary, and the item tiers FY-434 to FY-439 of the railway quota manual
The external-wall scaffolding quantity S(ext) = length of the external wall face (including pilasters and shafts attached to the wall, with no deduction for door and window openings) x external wall height (up to the top of the parapet where one exists), in m2. Single versus double row is not a multiplier on the area but a switch of quota line item, tiered by 'whether the masonry height from the design ground level to the eaves exceeds 15m' or by 'whether the area of openings and decorative finishes on the external wall exceeds 60% of the external wall surface' (FY-434 single row up to 15m; FY-435, 436, 437 and 438 double row up to 15, 20, 30 and 50m; FY-439 double row per additional 10m; the unit in every case being 100m2). In the whole volume only isolated columns and cast-in-place concrete beams take the double-row external scaffold item with a coefficient of 0.30; where one building has differing heights, each segment must be tiered on its own and summed segment by segment.
- ←
Recognising preliminaries costs of repeated scaffold erection and dismantling caused by the employer (instructions changing construction sequence): lump-sum exceptions, measurement anchors, pricing methods and procedural requisites (GB/T 50500-2024 clauses 3.3.7, 7.3.1, 7.4.4, 8.9.4~8.9.7, 8.11.10; GB/T 50854-2024 Appendix R, code 011601)
Preliminaries are lump-sum and unadjusted in principle, but clause 3.3.7 lists the exception: 'employer-caused extended use, reworking, addition or re-provision of preliminaries increasing their cost adjusts under chapter 8' - scaffolds re-erected after an employer instruction changing the sequence fall squarely under 'reworking' and 're-provision', with no need to prove excess over the bid scheme's assumptions, though a bid-versus-instructed scheme comparison must show the instruction caused it. Increments measure per 7.4.4 on the employer-approved scheme or actual content (extended use of existing preliminaries and management on non-critical paths never measures); material duration changes price per 8.9.4 as 'extended (shortened) duration x mid-term running costs', new plant and temporary works per 8.9.5; the scheme must be confirmed before execution (8.9.6), silence forfeiting (8.9.7). Codes: GB/T 50854-2024 Appendix R preliminaries run 011601 (scaffolds 011601001, unit 'item', no area rules at BOQ level); 011701 is the 2013 code - area / vertical-projection bases now serve only as increment pricing anchors, never to re-measure the whole scaffold list.
- ←
Judging double counting between masonry scaffolds and finishing scaffolds: exclusivity between the comprehensive and individual scaffold bases, position exclusivity (birdcage scaffold versus wall finish scaffold), the 3.60m height boundary, and one quota line item only where masonry, plastering and coating on the same wall share one scaffold
Non-duplication is judged on four exclusivity lines only: (1) basis exclusivity - wherever gross floor area can be calculated, the comprehensive scaffold applies, and it already covers 'external wall masonry and external wall finishes' and 'internal wall masonry, internal wall and ceiling finishes within 3.6m'; within that scope no interior scaffold or interior wall finish scaffold may be billed again; only works unsuited to the comprehensive scaffold (separately let finishes packages included) go to individual scaffolds. (2) Position exclusivity - 'where the storey height exceeds 3.60m and the ceiling requires plastering, painting, suspended ceilings or the like, a birdcage scaffold may be added and no wall finish scaffold is measured separately'; once a birdcage scaffold is measured for a space, its internal wall finishes attract only a scaffold alteration charge or no further scaffold. (3) Height boundary at 3.60m, but the masonry test is 'from the designed indoor floor level to the soffit (or mid-height of the gable)' while the finishes test is 'the internal wall finish height'; the two must not be mixed; above 3.60m additional quota line items apply to the excess only (masonry to single-row/double-row scaffolds, plastering to the interior wall finish scaffold). (4) Measurement is by scaffold area, not by trade count - interior scaffolds and interior wall finish scaffolds are both measured on the vertical projected area of the wall face; where masonry, plastering and coating on the same wall share one scaffold, only one quota line item is billed and it may not be billed once per trade; under the BOQ basis scaffolds up to 3.6m are not listed as separate preliminary items, their cost already sitting in the all-in unit rates of the divisional and sub-divisional work items (GB/T 50860-2024 clause 4.3.3).
- ←
Formwork and scaffolds of retaining walls: formwork by concrete contact area, the consumption of the wall-formwork item, and scaffolds of walls and slopes over 1.2m vertical height by vertical projected area
Formwork computes by the contact area with concrete in m2 (DB11/T 2382-2024 Appendix D Table D.1.31, item D1-7-6 'formwork, retaining wall body', unit m2, work content covering fabrication of formwork and supports, erection, release agent, removal, repair and stacking; per m2 - all-in labour I 0.2080 workdays, steel formwork connectors 0.2380 kg, steel props 0.5580 m, timber 0.0026 m3, release agent 0.0500 kg, nylon caps 4.8208, 4t truck 0.0042 machine-shifts, 8t crane 0.0177 machine-shifts). Cast formwork rules: single holes up to 0.3m2 not deducted and hole side faces not added; over 0.3m2 deducted with the side faces merged in. Scaffolds per SJG 181.2-2024 clause 8.2.4: retaining walls and slopes (over 45 degrees) with vertical height over 1.2m take scaffolds by vertical projected area, one or two faces per the approved execution plan.
- ←
Spatial-volume calculation rules for full-framing steel-pipe falsework in municipal and bridge/culvert works: the formula, the datum surface, the beam-body deduction issue and a cross-standard comparison (Shenzhen SJG 181.2-2024, Hunan 2025 edition, railway TB/T 10823-2024, highway JTG/T 3832-2018, Beijing DB11/T 2382-2024)
Full-framing steel-pipe falsework and assembled steel falsework are measured by spatial volume in m3: spatial volume = height (the longitudinal average height from the structure soffit/beam soffit to the original ground surface or the top of the working platform) x longitudinal distance x width (bridge width + 1.5 m; the Hunan basis uses +2 m). The beam body lies above the falsework space and is inherently excluded from the spatial volume; no standard contains any provision for "deducting the beam volume". The only express deduction is that falsework for cast-in-place bent caps deducts the volume occupied by the columns. Rental fees are calculated separately in tonne-months as spatial-volume weight x rental time (in the absence of a basis: 50 kg/m3 for the full-framing type, 125 kg/m3 for the assembled type, and 184 kg/m2 for the upper part of steel-pipe falsework); surcharge preloading is calculated separately as the design volume of the beam x 1.10 (railway: design beam weight x 1.2).
- ←
Distinguishing the birdcage scaffold (a work platform, by m2) from full-space steel-tube falsework (formwork support of cast-in-place beams, by m3): purpose, unit, quota volume, and non-interchangeability
The birdcage scaffold and full falsework are two different objects: the birdcage scaffold is a work platform for masonry, finishing and ceiling decoration, measured by net room area in m2 (railway FY-440 basic layer for clear heights of 3.6-5.2m, FY-441 one added layer per extra 1.2m, both per 100m2), belonging to building scaffold works; full steel-tube falsework supports the formwork of cast-in-place beams, slabs and bent caps, measured by space volume in m3 (railway QY-970 erection and removal per 100m3 of space; municipal SJG 181.2-2024 likewise m3 of space), belonging to bridge temporary structures. Different purpose and unit - never interchangeable; the building volume's separate FY-442 item (100m3) for true full-space steel falsework shows that only the platform-type birdcage scaffold bills by m2; bridge falsework items exclude soffit formwork and ground improvement.
- ←
Choosing the measurement basis for scaffold costs in tender rate build-up for building works (frame-structure office building): comprehensive scaffold by gross floor area versus individually priced scaffolds by vertical projected area / net room area, double-row external scaffold triggers, interior scaffolds and birdcage scaffold for ceilings
Building works whose gross floor area can be computed (including multi-storey frame-structure office buildings) always take the comprehensive scaffold basis first, measured by gross floor area; only projects unsuited to the comprehensive scaffold take the individually priced scaffold basis (external, interior and birdcage scaffolds measured by vertical projected area / net room area) - for the same element the two bases are mutually exclusive and must not be stacked. The external scaffold is measured by the length of the outer face of the external wall (including pilasters and attached shafts) x the external wall height (taken to the top of the parapet where one exists), with no deduction for door and window openings; the double-row item applies where the masonry height exceeds 15m, or is under 15m but door, window and decoration areas exceed 60% of the external wall surface. Interior wall masonry heights (indoor floor to soffit) up to 3.60m take the interior scaffold item (by vertical projected area of the wall face); over 3.60m the single-row external scaffold item applies instead. Where the storey height exceeds 3.60m and the ceiling needs plastering, painting or a suspended finish, a birdcage scaffold may be added (by net room area: the basic layer covers 3.60~5.20m, beyond 5.20m each extra 1.20m is one added layer, a fraction under 0.60m counting as one layer x 0.50), with no further wall-decoration scaffold.
- ←
The height boundary, quantity bases and base-layer / additional-layer computation of interior scaffolding and birdcage scaffolds (TB/T 10831-2024 and the Shaanxi, Hunan, Jiangsu and other local quota differences)
Interior scaffolding measures on vertical wall projection without deducting door and window openings, applying to masonry up to 3.60 m (internal walls from floor to soffit, or half the gable); birdcage scaffolds measure on clear room area, 3.60-5.20 m taking the base layer, each extra 1.20 m one additional layer, remainders under 0.60 m one layer x 0.50; where storeys over 3.60 m need ceiling finishing and a birdcage scaffold is added, wall finishing scaffolds are not counted again.
- ←
Rules for charging vertical transport in high-rise steel structure works, and its cost boundaries against comprehensive scaffolding and steel member erection lifting (preventing double counting)
Vertical transport and comprehensive scaffolding are two parallel preliminary items, each charged under its own rules with no inclusion of the other; steel member erection line items already include member lifting, which must not be charged again through vertical transport. Vertical transport covers only large vertical transport plant (tower cranes, builder's hoists, material hoists etc.), charged by gross floor area (including basements) with line items banded by structural type and eaves height: for steel structures within 20 m eaves height there are dedicated line items (single storey up to 7 m, multi storey up to 20 m and per additional 1 m); above 20 m eaves height the items are no longer split by structural type, only banded by eaves height (20-30 m, 30-40 m, per additional 10 m) and include external builder's hoist machine-shifts; single-storey buildings with eaves height within 3.60 m are excluded; the above-height increase applies one band per additional 10 m, where an excess under 10 m but over 5 m counts as 10 m and 5 m or less is not counted.
- ←
Wall and column plaster items in TB/T 10831-2024 Railway Works Budget Quota Manual Volume 10 (building works) - general plaster FY-1346 to 1358, decorative plaster FY-1359 to 1376 - the missing wall levelling screed, and plaster measurement rules
Volume 10 "section 2 wall and column works" sets only (1) general plaster (FY-1346 to FY-1358) and (2) decorative plaster (FY-1359 to FY-1376) - no standalone "wall levelling screed" item; general plaster content already includes "multi-coat levelling and finish trowelling", and only decorative backing runs on FY-1374 "decorative plaster, backing and levelling, 15 thick". Levelling a wall with no finish is a quota gap - never borrow FY-1189 to FY-1193 floor levelling screeds or roof screeds (position, process and measurement all differ).
- ←
Scaffolding calculation for water tanks (structures): measurement bases for the inner face of tank walls, the tank floor and birdcage (full-area) scaffolding for the roof slab, and the fee-route determination
First determine the route for tank scaffolding: where the water tank is located inside a building, the scaffolding cost is calculated as comprehensive scaffolding by gross floor area and must not be charged separately; where the tank is an independent work outside the building, the corresponding quota sub-items are applied per the approved scaffolding method statement. For an independent tank, measure part by part: tank walls (inner-face access scaffolding) by the wall area or the vertical projected area of the working face; the tank floor is generally not itemized separately (scaffolding with an erection height not exceeding 3.6 m is already included in the all-in unit rates of the divisional work items); the working-type birdcage scaffolding for the roof slab by the horizontal projected area of the erected zone (in some regions by spatial volume), with the basic lift for clear heights of 3.6 m < H <= 5.2 m and one additional lift per extra 1.2 m above 5.2 m; load-bearing formwork supports for the roof slab are measured separately by contact area, with formwork heights over 3.6 m adjusted "per additional 1 m".
- ←
The interface for charging superheight increment / efficiency-loss costs on separately tendered building decoration works (including door and window renewal): the trigger-height gate, the work-content gate and the tendering / pricing interface, and how to judge them
Whether separately tendered decoration (including door and window renewal) may charge superheight efficiency loss depends on passing three gates at once: (1) the trigger gate - eaves over 20 m or storeys over 6, either suffices (repair and refurbishment systems go by the work point exceeding 25 m; a building over but a work point not over the line takes nothing); (2) the work-content gate - doors and windows belong to the decoration discipline, sit within the applicable divisional items, and are charged on the decoration labour (in some regions labour plus plant) of the superheight part x the storey coefficient; the main-works "building superheight increment cost" by floor area must not double-count with decoration superheight; (3) the tendering / pricing interface - the cost enters the all-in unit rate of each bill item (SJG 77-2020 clause 5.1.4); where not allotted to the subcontract or already capped by the main contractor, the subcontractor may not claim it again.
- ←
Criteria for determining hollowness (debonding) of wall and floor tiles and rework cost calculation (demolition + re-laying quota line item pricing method)
First determine per acceptance criteria whether rework is mandatory: exterior wall face tiles shall have no hollowness or cracks (GB 50210-2018 Clause 10.3.5); interior fully-adhered face tiles shall have no hollowness on main faces and external corners, with only local edge/corner hollowness within 10 mm of the edge acceptable (Clause 10.2.4); floor tiles/stone allow local edge hollowness per tile and <=5% of the total count per natural room (T/CBDA 51-2021 Clause 18.3.8). Where rework is mandatory, price in two stages with "demolition quota line item + re-laying quota line item": demolition per renovation-work items (railway building quota norms FY-1050 floor tile removal, FY-1055 wall ceramic veneer chipping), re-laying per decoration-work items (FY-1215 floor tiles, FY-1393 wall tiles), with adjustment for price differentials applied to base-period prices and waste hauling counted separately; the cost outlet depends on responsibility (construction quality problems borne by the contractor; free-issue materials (by the employer)/design changes (designer-issued variation) claimable).
- ←
Distinguishing and applying tile (block) finishes vs stone finishes: separate BOQ items and three quota criteria (material -> size -> workmanship)
"Block finish" carries two senses — a collective chapter name (all slab finishes including stone) and a material-specific sense (non-stone tiles); which sub-item applies is decided by the face material, not the table name: those consuming natural-stone facing panels/marble apply stone sub-items; those consuming floor tiles, glazed tiles and other ceramics apply block sub-items; in GB/T 50854-2024, stone floors / rubble-stone floors / tile floors (code 011102) and stone wall-columns / rubble / tile wall-columns (code 011203) are separate BOQ items priced under their own quotas; the railway caliber expressly runs vitrified tiles under ceramic-tile sub-items and stone within 100x100 under accent sub-items.
- ←
Ground-based scaffold standing-pole foundation requirements: level, firm, drained ground; bearing verification formula and characteristic-value modification; staged inspection during use (GB 51210-2016 cl. 6.2.18/6.2.19/9.0.3/9.0.12)
Per GB 51210-2016: (1) erection ground shall be level, firm, well drained and free of standing water; backfilled ground shall be compacted before erection (cl. 9.0.3); (2) standing-pole foundation bearing must satisfy P = Nd/Ad <= gamma-u x fa, with gamma-u = 1.363 for permanent-load-governed combinations and 1.254 for variable-load-governed, fa being the characteristic bearing value modified per cl. 6.2.19 (cl. 6.2.18); (3) the characteristic value may be set comprehensively from load tests, other in-situ tests, formula computation and experience, modified for soil type and state (cl. 6.2.19); (4) staged inspection, monitoring, maintenance and upkeep during use (cl. 9.0.12).
- ←
Railway 2024 budget quota: item application and quantity rules for driven cast-in-place pile follower (送桩) and splicing of precast piles (TB/T 10823-2024 bridge/culvert volume vs TB/T 10831-2024 housing volume)
In the railway 2024 quotas, whether pile followers (sending piles below grade) and pile splices get their own items differs by volume: (1) In the bridge/culvert volume (TB/T 10823-2024 Volume 2), the pipe-pile sinking items' work content already includes "splice/disconnect and follower driving" — neither follower nor splice books a separate item; square-pile driving items include splicing and follower work, but square-pile joints must be listed separately by count (QY-245 sulphur mastic / QY-246 flange, unit 10 joints). (2) In the housing volume (TB/T 10831-2024 Volume 10), the follower books FY-141 square-pile follower / FY-142 pipe-pile follower (unit 10 m3), and splicing books arc-welding splice items (FY-138/139 square piles, FY-140 pipe piles, unit 10). Follower length runs from the design pile-top elevation to the natural ground level before driving plus 0.50 m; welded splices are counted by the number of pile-head splices required by the design.
- ←
The caliber of ceiling height: the definitional difference between indoor clear height and story height, computation rules, residential minimums, and term usage in pricing clauses
"Ceiling height" is understood and computed as indoor clear height: the vertical distance from this floor's finished floor surface to the ceiling soffit (GB 50352-2019 Clause 2.0.14; GB/T 50504-2009 Clause 2.4.30), not story height. Story height is the vertical distance between finished floor surfaces of adjacent floors (GB/T 50504-2009 Clause 2.4.29); the two differ by the plenum, slab (beam) depth, and upper-floor buildup, and must not be mixed. Residential bedrooms/living rooms: clear height not less than 2.40 m, local not less than 2.10 m with local area not more than 1/3 of usable area (GB 50096-2011 Clause 5.5.2). Pricing clauses use "story height" or "clear height/height to ceiling" as fixed terms — take values per the clause text.
- ←
Screening double counting in budget documents: five high-frequency duplication scenarios and judgment principles
The general principle for judging double counting: content already included in the work content must not be charged again, separately listed items must not be recomputed, and mutually exclusive items can be taken only once. High-frequency duplication falls into five classes: ① between quota line items (cast-in-place concrete already includes formwork — no separate formwork item; auxiliary content such as machinery relocation and material transport already included); ② between preliminaries and work-sections (vertical transport covers only large machinery, the rest already being in the work-sections; costs of separately listed preliminary items must not be double-counted); ③ within preliminaries (comprehensive vs. individually priced scaffolds — choose one; birdcage (full-area) scaffold and wall-finishing scaffolding are mutually exclusive; height-increase fee keyed to work points above 25 m); ④ other-item fees (provisional sums reduced at settlement by price adjustments; claims carry taxes and duties only); ⑤ fee accrual and taxes and duties (the base to which percentage rates are applied and taxation of free-issue materials (by the employer) must not be duplicated).
- ←
Railway 2024 quota: classification and application rules of cast-in-place concrete foundation items (TB/T 10831-2024 Volume 10 housing works, FY-458~470)
TB/T 10831-2024 "Railway works budget quota, Volume 10: housing works", Chapter 1 Section 5 "cast-in-place concrete members (1) foundations" sets 13 items FY-458~FY-470 (unit 10 m3): strip foundations are split by rubble/plain/reinforced concrete, the reinforced ones into ribbed and flat types with the boundary "rib-height:rib-width within 4:1 counts as ribbed; beyond 4:1 the base slab is flat-type and the portion above the slab counts as wall"; isolated foundations split three ways by rubble/plain/reinforced; a cup foundation counts as a high-cup foundation when the cup opening height exceeds the opening length; rafts split into without-beam / with-beam, "with-beam" meaning beams cast integrally with the base slab — the beam volume merges into the foundation and is computed as solid volume, with no further beam item; pile caps split into strip / isolated. Structure foundations use the corresponding building-foundation items; equipment foundations, except block type, are computed by the corresponding foundation, column, beam, wall and slab items, deducting reserved openings.
- ←
Conversion between the "basic lift plus additional lifts" of the birdcage (full-area) scaffold and the rounding treatment above 5.2m: additional lifts = (indoor clear height - 5.2) / 1.2, with a remainder under 0.6m taken as half a lift (factor 0.5) or rounded, covering the differences between the railway, Shaanxi, Hunan and Jiangsu standards
The number of additional birdcage-scaffold lifts = (indoor clear height - 5.2) / 1.2: where 3.6m < indoor clear height ≤ 5.2m one basic lift is counted; above 5.2m each further 1.2m counts as one additional lift; the quantity is the net indoor area (no deduction for columns or piers). Where the remainder is under 0.6m, rounding differs by standard - TB/T 10831-2024 and the Shaanxi quota count one additional lift multiplied by a factor of 0.50 (half lift); the Hunan 2025 consumption standard rounds to the nearest integer (a remainder under 0.6m is discarded); Jiangsu counts a basic lift within 8m, one further lift per 2m above 8m, decimals up to 0.6 being discarded and above 0.6 rounded up.
- ←
GB 51210-2016 Unified Standard for Construction Scaffold Safety, Chapter 10 quality control: stage inspection time points and completion acceptance pass criteria
GB 51210-2016 cl. 10.0.5 sets 5 time points where stage quality inspection is mandatory (after erection-ground completion and before erection; after installing the first level of horizontal tubes; before staged use after each storey-height of erection; before and after each lifting/lowering of attached climbing scaffolds; for support scaffolds every 2-4 lifts or not more than 6m of height); cl. 10.0.7 requires completion acceptance once ground/cantilever/support scaffolds reach design height and attached climbing scaffolds are installed in position; passing requires simultaneously: on-site inspection of materials/components passed, stable bearing of ground and supporting members, stage inspections passed, acceptable appearance, and complete technical records — use only after acceptance.
- ←
Railway 2024 quota Volume 10 building works (TB/T 10831-2024): scope, contents, and the volume attribution of external appurtenances (fences/roads/drainage ditches)
TB/T 10831-2024 Volume 10 "applies to works related to railway buildings"; column-free platform canopies count floor area by the horizontal projection of the outer edge, cantilevered platform canopies bounded by the station building's external wall line by projection; otherwise per GB 55031; telecom repeater/base/signal relay stations take labor and plant x 1.25 under this volume. In the TB 10801-2024 Appendix A chapters, building external appurtenances form "IV. building appurtenance works" (earthworks, retaining walls and slope protection, roads and hardened surfaces, fences with gates, heat-network piping, chimneys, greening, others including drainage ditches); by quota items: fences, retaining walls/slope protection, aprons, outdoor block paving, and brick trenches are in this volume; concrete/asphalt/clay-bound gravel pavements and cast-in-place drainage channels are not (they sit in Volume 13 station yard works or Volume 1 subgrade).
- ←
Does comprehensive scaffolding include interior and birdcage (full-area) scaffolds: what comprehensive covers (masonry/finishing within 3.6 m), birdcage (full-area) scaffolding above 3.6 m, and anti-duplication rules (Hunan/Shaanxi/Jiangsu/railway calibers)
The relation is not simple inclusion: interior and birdcage (full-area) scaffolds are individually priced scaffolds, chosen alternatively with comprehensive scaffolding — no double counting. Comprehensive scaffolding covers internal masonry and wall/ceiling finishing within 3.6 m (no separate interior-scaffold sub-items within that range); above 3.6 m the excess takes additional sub-items — where story height exceeds 3.60 m and ceilings need plastering, painting, or suspension, birdcage (full-area) scaffolding may be added (3.60-5.20 m = base layer; each 1.20 m above = one added layer), and wall finishing scaffolding is then not computed.
- ←
Railway 2024 quota norms, building works volume (TB/T 10831-2024 Volume 10): site leveling vs cut-and-fill earthwork boundary (±30 cm) and measurement rules
Under the railway 2024 quota norms system, cut-and-fill leveling within a thickness of ±30 cm uses "site leveling" (FY-65 manual 442.89 yuan/100 m2, FY-66 mechanical 97.43 yuan/100 m2, base-period prices); cut and fill beyond ±30 cm is treated as foundation-pit or general earth/rock work and measured by volume. Site-leveling quantity is computed from the building's (structure's) first-floor gross floor area (GFA) (the area enclosed by the structural perimeter) per the design drawings, with the portions where the basement structure projects beyond the first-floor perimeter merged into the calculation.
- ←
Railway building-works quota TB/T 10831-2024 earthworks: trench-pit vs general earthworks division, manual/mechanical boundary (depth >6 m mechanical), and the <=0.30 m manual bottom-cleaning included in mechanical excavation
Building pit excavation first tests "trench-pit" or "general earth-rock" per volume note 2: trench-pit means trenches with bottom width (design bedding or foundation width) <=7 m and length >3 x width, or pits with length <=3 x width and bottom area <=150 m2; beyond these, unless site grading, it is general earth-rock. Depth <=6 m: manual (FY-1~FY-12) or mechanical (FY-31~FY-42) per the actual method; depth >6 m "shall be treated as mechanical excavation". Mechanical earthwork already comprehends manual cleaning and trimming of the <=0.30 m left at base and slopes — "must not be adjusted in use"; no separate manual bottom-cleaning item.
- ←
TB/T 10831-2024 railway housing works quota: classification of cast-in-place slabs into beam-slab / flat-slab / plain-slab and the pricing rule of monolithic beams and slabs (FY-503~516)
Per TB/T 10831-2024 "Railway works budget quota, Volume 10: housing works", volume notes "10. Quantity calculation rules" item (7): beam-slab = slab cast integrally with primary and secondary beams, "computed as the sum of beam and slab volumes" — with monolithic casting the beam volume is merged into the beam-slab item and the beam is not applied separately; flat-slab = slab bearing directly on columns (with drop panels), "computed as the sum of slab and drop-panel volumes"; plain slab = slab bearing on walls (or ring beams), "computed as the solid volume of the slab". Corresponding items: FY-503~507 beam-slab, FY-508~512 flat-slab (both in five thickness steps <=100/<=150/<=200/<=300/>300 mm, unit 10 m3), FY-513 plain slab, FY-514/515 sloped roof slabs (with beams / without beams), FY-516 arch slab.
- ←
Suspended-basket scaffold quota-item selection: exterior paint/insulation/curtain wall per work type — FY-444/FY-445/FY-443 (TB/T 10831-2024 Volume 10, Building Works)
Exterior painting adopts the "painting (oil) paint" item (FY-444); exterior insulation (insulation-mortar plastering, bonding mortar and other mortar-type work) adopts the "mortar" item (FY-445); tiled and curtain-wall work adopts the "block-facing curtain wall" item (FY-443). Where several works proceed consecutively in the same basket, only one item is selected by the principal work type — two items must not be applied duplicatively; basket assembly/disassembly (including testing of the electric device, safety lock, and balance controller) is already included in the work contents and not charged separately. Basis: TB/T 10831-2024 Volume 10, Building Works.
- ←
Deciding the quota pricing attribution of substrate treatment in plastering works (spatterdash / bonding agent): contained in the plastering item, or taken as a separate item
Substrate treatment (bonding-agent application, spatterdash / cement-splash roughening) is listed separately from the plaster finish in current mainstream quotas. Decide by "three checks": (1) check whether the plastering item's work content already lists interface treatment (if listed, no separate charge); (2) check whether the quota carries a dedicated bonding-agent / substrate-treatment item (if so, apply it separately on the treated area in m2); (3) check whether the item's material column already contains the bonding agent (if contained, no separate charge). Beijing DB11/T 2382-2024 states expressly: general plastering sets items separately for substrate treatment, base coat and finish coat; the substrate treatment of decorative plastering and of tile and stone finishes follows the general plastering items, the finish being listed separately. Railway TB/T 10831-2024 Volume 10 general plastering work content excludes interface treatment, and bonding-agent details carry dedicated items (FY-1375 wall bonding agent, FY-1376 neat cement mortar bonding agent) applied when occurring. Note the double meaning of "spatterdash": railway FY-1370 / FY-1371 "decorative plastering spatterdash" contain red-earth powder and are finish-coat practices; substrate spatterdash / cement splash must take neat-cement-mortar bonding-agent items - never confuse the two.